出版社:Consejo Superior de Investigaciones Científicas
摘要:In many cases the only places available for the construction of a new car park are the existing streets or roads.These streets may also have important or historic buildings very close to the structure, which means that they cannot be disturbed in any way during the construction of the parking structure.In this particular case, the novelty is that the top deck is solved with a unique structure: a vault that interacts with the pile wall not only for vertical but also for horizontal loads due to the arch mechanism.The construction of the vault is solved as a large precast element of one piece of more than 16 in length and 2.40m in width, which is built in the factory, transported with the help of trucks and erected on site with large cranes.
关键词:Aparcamiento subterráneo; cimentación profunda; pantalla de pilotes; secuencia de montaje; elementos prefabricados; bóveda
其他关键词:Underground parking structure; deep foundation; pile walls; erection sequence of structure; precast elements; vault structure