摘要:AbstractThis paper aims to investigate the current practice of extension of time claim assessment by contract administrators and identify difficulties faced by them during the assessment process. A survey approach using questionnaires as an instrument revealed that poor factual evidence and flaws in claim presentation are the principal factors leading to delays in the assessment process. The findings imply that efficient contract administration and well-organised record keeping will lead not only to successful project management but also will increase the chances of a successful contractual claim. These findings are expected to offer a significant contribution to industry players, researchers and also academics, thus helping to identify areas for further improvement.
关键词:Construction industry;delay;extension of time claim;record keeping