Risk management framework for build, operate and transfer (BOT) projects in Kuwait.
Al-Azemi, Khalid Fahad ; Bhamra, Ran ; Salman, Ahmed F.M. 等
Introduction
The worldwide need for development projects is increasing
continuously, particularly regarding all forms of infrastructure
facilities. An imbalance in the infrastructure projects and the ability
of countries to meet their development requirements has been caused by
population growth and the immense, rapid expansion of global economics.
The movement towards privatization, both in developed and developing
countries has resulted in the participation of the private sector in the
improvement of the infrastructure process as a more popular option. This
gradually led to the demise of the monopoly held by the public sector,
regarding basic infrastructure facilities.
As a result of the reduction in public funding, governments are
becoming increasingly dependent on the private sector for the
improvement and development of infrastructure projects. This is due to
the fact that the private sector is often better equipped in the
following ways: the mobilization of resources; the provision of
technical and managerial expertise; an improved operating efficiency;
the potential for large-scale injection of capital; a greater efficiency
in using the capital; utilization of rationalization/cost-base tariffs
for services; and a better understanding of customer needs.
Due to the number of parties involved and the corresponding amount
of interlocking contracts required, BOT projects are indisputably
complex. In this type of project, each party has to rely on the
performance of its counterpart, and is also dependent on the lead time
of each stage of the project, which can be lengthy. Furthermore, there
are high associated upfront costs. There are also a number of complex
issues, i.e. government stability, which have to be resolved,
specifically with respect to developing countries.
As a result of large capital outlays and the long timescales
required to generate returns for investors, BOT infrastructure projects
carry an inherent risk. There is an increased probability of problems
arising when such long timescales are involved. The relative amount of
loss could potentially be huge, given the very large capital outlays
required. Therefore, the decision to invest in BOT projects is affected,
to a large extent, by the perception of risk.
The purpose behind the Kuwaiti governments program of privatization
is essentially to ease the financial burden on the public by reducing
the costs connected with public debt. It also assists in the transition
of the central economy from a planned to a free market and in many cases
results in an improvement in public services. It involves a partnership
between the public and private sectors, which is essentially a service
contract in which the private sector plans the funding of the project
and provides the assets required to deliver it, while the public sector
selects and purchases the necessary services it provides a suitable
opportunity to provide high-quality services which are fully equipped
and well insulated, using private sector funding, with the risk factors
passing from the public to the private sector and avoids the need of the
public sector to purchase capital assets.
In order to study the impact on the economy of the general
privatization process, it is possible to measure the percentage increase
in the amount of private sector participation within the economy, the
improvement in the trade balance, the growth in the domestic capital
markets, decrease in the budget deficit, reduction in unemployment
levels, as well as the financial, quality of service and profitability
indicators.
The Sulaibiya Waste Water Treatment contract in Kuwait, signed in
May 2001, was commissioned in 2004 and currently processes 50 million
gallons of water per day for irrigation purposes. It is the largest BOT
project to date and revenues were projected of USD 390 million over 10
years. Privately owned Kuwaiti companies have launched projects in real
estate and one of these, the Kuwaiti National Real Estate Company
completed the USD 132 million Sharq Mall in 1998. In 2002 the Marina
Mall, a USD 162 million BOT, was completed by the Kuwaiti United Realty
Company. More recently, in February 2010, the Kuwaiti Government
approved a major development plan consisting of 1,100 projects totalling
KD 30.8 (USD 107.8 billion). The projects include a free trade zone with
700,000 residents, a planned financial and commercial hub and the
creation of a Silk City program all of which, according to the Minister
of State for Housing and Development Affairs, are intended to be
undertaken as BOT projects.
There are several disadvantages to the privatization process, which
include a lack of expertise, insufficient legislative cover, a lack of
regulations covering the relationship between the participating parties,
which would protect their rights and ensure compliance with the details
of the contract. The State authorities expended a great deal of effort
in order to achieve satisfactory results.
However, while bidding for BOT projects, some investors submitted
high offers, without realistically considering the risks and
opportunities involved. Also, many of the methods were not transparent
as the main concern of investors was to earn extra profit and guarantee
beneficial financial results. As a result, legal and contractual issues
have been raised, with a negative effect on the projects and a lack of
confidence and increasing tension between the parties involved in the
contract. The experience gained has had advantages as well as
disadvantages, but the problems have been emphasized for political
reasons, so it was necessary for the government to pay special attention
to Build-Operate-Transfer (BOT). This indicates the serious intention of
the government to implement privatization policy and to involve the
private sector in the execution and development of projects and
services.
Some articles within the legislation may have prevented investors
from participating in certain projects and public opinion is also an
important factor to consider. These issues have resulted from the new
BOT law and also the economic boom, which occurred during the recovery
period over the last five years. Even though only three years have
passed since the enactment of the law and decree, critics are still
requesting amendments to the law. This in fact occurred even before
there was an awareness of the unknown risks involved. The crisis of
confidence between the public and private sectors is still in existence
and so the causes need to be addressed so that all parties will benefit
from the legislation and so that it can lead to successful projects
resulting in improved development for the whole country.
Unfortunately, due to the extended process of procurement in
Kuwait, many accusations of attempted bribery and inducements have been
leveled at bidders. Several investigations and trials are currently in
process, which involve accusations against current or previous
government officials. Since the end of the Gulf War, however, there have
been no convictions for bribery
Law No. 25 was passed in 1996, in which all companies securing
contracts worth KD 100,000 (USD 364,931) or more must report all
payments made to Kuwaiti agents or advisors during the time of securing
the contract. In the same way, individuals in Kuwait should report any
compensation payments received when securing government contracts.
In 2010, Transparency International's Corruption Perceptions
Index (CPI) discovered Kuwait to be 54th out of 180 countries. Within
the Arab region, it was ranked seventh out of 18 countries. According to
Transparency International, Kuwait's CPI score of 4.5 (out of 10)
indicates that it suffers from a "serious corruption problem".
According to the World Bank (1994), it is widely accepted by
virtually all governments that one of the most important factors in
encouraging national economic growth is having an appropriate and
reliable infrastructure. Even though economists find it hard to agree
about the elasticity of infrastructure investment, studies have shown
that infrastructure is extremely important to successful economic
activity.
However, it is often the case that governments in countries with
developing economies rarely have the financial resources needed either
to create new, or maintain current, infrastructure facilities.
Unfortunately, inefficiency and a lack of openness in management
dealings and decisions, has resulted in a low standard of service to the
community development for the whole country.
It is inevitable that risks are a crucial part of BOT projects.
These risks are quite complicated because of the high levels of
investment, the length and complex nature of the project setup, which is
required when all of these risks are combined. The companies involved in
the BOT projects assume responsibility for a wide range of risks
throughout the life-cycle of the project, while the private sector
assumes responsibility for the finance, design, construction and
operating risks. This paper examines and discusses the risks faced in
BOT projects in the State of Kuwait, prioritizing them, and suggesting a
framework to manage the risks in the Kuwaiti environment.
1. Background
The previous tradition, in which government funds infrastructure
developments, has been changing Shen et al. (2007). More recently,
private businesses have been given opportunities for involvement in the
funding and development of infrastructure. The reason for this is that
private businesses have access to large amounts of capital and often
have greater management expertise than the government. The lack of
financial resources is particularly relevant in developing countries,
Shen et al. (2007).
According to Shen et al. (2002), the build-operate-transfer (BOT),
contractual arrangement enables governments to build more infrastructure
services by using private finance and management skills, rather than
public funds. The BOT concept has contributed to the development of
infrastructure works worldwide, most noticeably in developing countries,
Shen et al. (2007). This method mobilizes private funds and also
utilizes the available new technology, management skills, and
operational efficiencies which private businesses are able to provide in
the development of infrastructure Shen et al. (2007). In Southeast Asia,
in particular, according to Shen et al. (1996), governments have been
increasingly using BOT methods to build railways, highways, tunnels,
ports, bridges, reservoirs, power plants and hydraulic facilities.
According to Levy (1996), the first BOT contract project in modern
times dates back to the building of the Suez Canal, built in 1854. For
this project, the company, Compagnie Universelle du Canal Maritime de
Suez, received a concession from the Egyptian government lasting for 99
years, enabling it to construct and operate a canal which connected the
Mediterranean Sea to the Red Seas. However, as noted by Huang (1995),
the method was still rarely used until the mid-1980's but since
then the use of the BOT method has increased considerably, making a
significant contribution to the development of worldwide infrastructure.
Delmon (2000) carried out a study in which he found that there are
significant risks involved in achieving the objectives for a BOT project
and they come from various sources, such as: the economic environment,
the capital budget, the construction cost and time, the operational
costs, as well as the politics and policies prevalent at the time.
Current market conditions and cooperation credibility also play an
important role. Both the private sector and the government therefore
need to pay particular attention to the effect of these risks before
becoming involved in a BOT contract.
A hydropower plant project in Turkey was considered by (Ozdoganm,
Birgonul 2000), in order to discover the viability of qualitative
decision factors, using a checklist approach. To achieve this, they used
three criteria, which were government actions (Gas), country specific
(CS) and project specific (PS). As these were quite subjective criteria,
it was impossible to discover the precise influence of the qualitative
decision factors on the feasibility of the project. Using their
checklist approach could result in the neglect of possible strategies
which might have improved certain qualitative aspects of a project
decision.
A desirability model, which measures the competitiveness of a
company and the attractiveness of a project, from a private
promoter's point of view, was provided by Dias, Ioannou (1995b),
who analyzed a set of country and project decision factors and produced
a project attractiveness index. However, the difficulty with the
application of this method, in practice, is that it would take quite a
large amount of time and increase the cost of a project feasibility
study. It might also result in the misinterpretation of project decision
factors and some of them might actually be missed. In the desirability
model, the attribute worth score was only valid when the attribute
performance was between two extreme values P1 and P2. Where, P1 is the
minimum plausible performance level for an attribute and would indicate
the highest point on the performance scale where an attribute is worth
its minimum (i.e. 0 worth points). The maximum plausible performance
level, P2, indicates the lowest point on the performance scale and
occurs where an attribute value is at its maximum (i.e. 100 worth
points).
The different variables, which affect the concession period of a
BOT contract, were reviewed by Shen et al. (2002), who suggested that,
in order to determine a suitable time period for the project, taking
into account both the government's and the investor's
interests, a quantitative concession model (BOTCcM), should be
considered. Shen et al. (2005), in their investigations discovered that
the risks involved in the implementation of a BOT project, had a marked
effect on the cash flow for the project. Using Monte Carlo simulations,
they incorporated project risks into the BOTCcM. However, in a BOTCcM,
all BOT factors other than the concession period are predetermined, so
it does not allow for different combinations of the concession period
with other BOT financial variables.
1.1. Nature of infrastructure projects
Recently, the attention given to urban regeneration projects has
significantly increased. Such initiatives use redevelopment projects to
resolve the social and economic problems caused by antiquated buildings
and degraded infrastructure, Kim (2010). However, common infrastructure
projects such as power, water and sewerage, telecommunications and
transport facilities possess a number of characteristics: they lack
portability, are rarely convertible to other uses and it can be
difficult to reverse any investment made in them. The majority of
infrastructure projects require large investment capital, are
single-asset investments and developed over a long period of time; they
also have long periods of payback. However, they do provide important
services, which would usually fall to the public sector and they
generally operate as monopolies. The nature of infrastructure projects
makes them responsive to public opinion and political pressure. Contrary
to other types of foreign direct investment, most infrastructure
projects only generate local currency, but the dividends and loan
repayments are paid in foreign currency. The process of building
infrastructure facilities is also complex and very risky.
2. Definition of BOT approach
BOT is a term used for the financial involvement of the private
sector in various infrastructure projects. BOT should not be thought of
as a legal term, but rather as an economic and financial concept. As
defined by Tiong (1995a), it is "the granting of a concession by
the Government to a private promoter, known as the concessionaire, who
is responsible for financing, construction, operation and maintenance of
a facility over the concession period before finally transferring the
fully operational facility to the Government at no cost".
There are several different definitions of BOT:
--Tiong (1995c) states that it is a method of project financing in
which a government awards a concession to a group of investors, known as
the "Project Consortium" for the development, operation,
management, and commercial exploitation of a particular project;
--According to Esq (1996), BOT is a method of financing a project
in which the government grants a concession to a private entity or
project company to build and operate a project, which would usually be
operated by the government itself;
--Nassar (1996) defines BOT as the involvement of Concession
Company which provides the finance for, and then designs, constructs,
operates, and maintains a particular infrastructure project for a
pre-defined length of time, after which it is transferred back to the
host government without any charge.
In any BOT scheme the concession company finances, designs,
constructs, operates and maintains a particular facility for a fixed
period of time, which should be long enough to pay off all debts and
provide a reasonable profit to the equity investors. At the end of the
specified time, the facility passes, without charge, to the public
authority or the government (Walker, Smith 1995; Wilburn, Thomas 1994).
The BOT model is a method in which a group of private investors form a
consortium to complete an infrastructure project including its design,
finance and construction. It then operates the project for a period of
time on behalf of the promoter (which may be the government). This is
known as a franchise/concession and involves the building and operation
of the project for a length of time before it is passed back to the host
authority (Shen et al. 2002; Askar, Gab-Allah 2002).
2.1. Risk in BOT projects
One of the main methods for procuring and delivering public
infrastructure projects is the public-private partnership (PPP), and,
according to Regan et al. (2009), it has been used in over 85 countries.
Its specific features include improved public facilities and services, a
competitive bidding process, and a suitable balance of project risks,
together with the innovation and expertise of the private sector.
The National Council for Public-Private Partnerships, USA (2009),
have defined a public-private partnership as "a contractual
agreement between a public agency --federal, state, or local--and a
private sector entity", in which a sharing of the assets and skills
of each sector results in the provision of a public service or facility
for the use of the general public. According to Li et al. (2005), it is
considered to deliver value for money in the provision of public
services and infrastructure by combining the advantages of flexible
negotiation and competitive tendering and by allocating risk, on an
agreed basis, between the public and private sectors.
According to Kumaraswamy, Morris (2002), BOT schemes may be either
private participation (PP), or public-private partnerships (PPPs). Other
collective terms are: build and transfer (BT), build, transfer, and
operate (BTO), build, operate and own (BOO), build, operate, own, and
transfer (BOOT), operate and transfer (OT), reconstruct, operate, and
transfer (ROT), etc. all of which are subject to concession agreements.
As Tiong (1995a) states, a BOT infrastructure project may be implemented
by a government grant, with a concession company which will finance,
construct, operate and maintain the project before transferring
ownership back to the government after an agreed concession period.
Senturk et al. (2004), note that BOT schemes, as adopted in many
industrialized countries, use private sector participation to finance
new infrastructure projects. A number of studies (Tiong 1990; Dias,
Ioannou 1995b; Liddle 1997) show that government-sponsored BOT schemes
encourage the participation of the private sector in large public
infrastructure projects such as roads, expressways, bridges, railways,
ports and power plants, which are built and/or operated by private firms
under a procurement system. However, there is much risk attached to the
process and this must be carefully evaluated by both the private bidders
and the public client, throughout the whole duration of the project. An
effective management framework needs to be set up to deal with the risk
on a theoretical and practical basis.
There is risk involved throughout the life of the project and, as
BOT-type projects require large investments and cover long time periods,
as Shen et al. (2005) state, during the concession period, these many
risks and uncertainties could potentially affect the performance of the
project.
The BOT projects undertaken by the private sector contain many
risks and uncertainties (Songer et al. 1997). The BOT projects are
generally large-scale projects providing infrastructure facilities and
the transaction costs on average are between 5 and 10% of the overall
project cost (Klein et al. 1996).
Projects involving the building of infrastructure have a higher
risk element because the capital costs are usually high, there is often
a long lead-time and the resulting assets do not usually have any
alternative use. It is very important, therefore, to identify, analyze
and allocate the different risks when evaluating privately promoted
infrastructure projects. The risks involved in BOT projects are
two-fold. First, there are the risks involved in the start-up procedure
(financial and technical studies) and also finance and operational risks
due to the nature of the BOT approach; and secondly, being large-scale
projects, there are also regulatory, political and economic risks
involved (Ebrahimnejad et al. 2010).
According to Tiong, Alum (1997) due to the high level of risk
associated with BOT projects, the negotiators and Decision Makers (DMs),
for both the public and private sectors need to carry out a careful
analysis and then manage these risks. However, as pointed out by
Ozdogann, Birgonul (2000) the private sector and the government do not
share a set of principles covering the risks associated with BOT
projects, and so, according to Tiong (1995c), the promoter who wins the
concession is more likely to be the one who carries the risk and offers
suitable guarantees. According to Gunn (2005), risks and ambiguity will
be present in all construction projects and tend to involve the three
main project management restrictions of time, quality and budget. The
many risks involved in construction are considerably increased in BOT
projects, due to the complex combination of various issues such as
design, construction, operation and finance. The risks themselves are
more complex than for conventional projects because of the higher number
of parties and agreements concerned. The working environment is very
different in BOT projects and so both the private and public sectors
need a change in attitude towards the risks involved. Governments
usually attempt to transfer as much risk as possible to the private
sector, while the private sector is asked to assume that risks inherent
to the project are assigned to the appropriate party.
Public-Private Partnership (PPP) is a procurement approach where
the public and private sector join forces to provide a public service or
facility. In this agreement, usually both the public and private sector
will contribute their expertise and resources to the project and share
the risks involved, (Cheung et al. 2010). The Public-Private Partnership
(PPP) projects fall into two main groups, consisting of general and
project risks (Loosemore 2007; Loosemore et al. 2006). The risks within
a BOT project will change during the development process, and so they
will change at each stage, from the planning phase through to the
design, construction and operation phases.
There are six areas of risk associated with PPP projects, according
to Grimsey and Lewis (2004), and these are: financial, asset, sponsor,
operating, public and default risks. The main categories of risk in BOT
projects have been identified (Dey et al. 2002) as economic, political,
legal, construction, financial and operating risks. According to (Baloi,
Price 2003), the risks also need to be categorized as: static/dynamic,
individual/corporate, internal/external, positive/negative,
acceptable/objectionable and insurable/uninsurable. For this reason,
government assurance is extremely important in BOT projects. The more
easily observed risks are: economic, political, financial and related
risks.
2.2. Risk management in BOT projects
Risk management is an "activity that defines sources of
uncertainty (risk identification), estimating the consequences of
uncertain events/conditions (risk analysis), generating response
strategies in the light of expected outcomes and finally, based on the
feedback received on actual outcomes and risks emerged, carrying out
identification, analysis and response generation steps repetitively
throughout the life cycle of an object to ensure that the project
objectives are met" (Zavadskas et al. 2010). According to Gunn
(2005), the importance of risk management to the success of BOT projects
cannot be overestimated. There are many different types of risk and
uncertainty involved in every construction project, however small. These
may be: technical, economic, legal, etc. but they all ultimately involve
an organization in financial risk. The risks pertaining to BOT projects
are more complicated than the traditional methods, where the design is
separate from the construction and the client is responsible for the
project. This is not only due to the long duration, high investment and
complicated methods of procurement, but also because all of these risks
are combined, with the companies involved in the project assuming
responsibility for a whole range of risks within the life-cycle of the
project and the private sector taking responsibility for financial,
design, construction and operating risks. The three main areas of risk
generally center on the project management constraints of time, quality
and budget.
Dey and Ogunlana (2004) consider that ineffective risk management
is one of the major causes of failure of BOT projects, which are
considered to be the most risky project schemes. An understanding of the
contents and contexts of BOT projects is extremely important today, as
are the risk-management tools and techniques available. The application
of these tools will depend on various factors including the policy
requirements of the organization, the project management strategy, the
nature of the project, the attitude of the project team to risk taking
and the availability of resources.
Raz, Michael (2001) commented that risk management has been a main
topic of interest for researchers and practitioners who are involved in
project management. Flanagan, Norman (1993) have defined risk management
as a system which aims to identify and quantify all risks to which a
business or project is exposed so that a conscious decision can be taken
on how to manage those risks. Risk management acknowledges the
possibility that future events may produce negative or adverse effects
and employs the design and implementation of systems or procedures which
will control these risks. This definition also explains that the purpose
of risk management is to manage systems in order to control risks.
Although risk management need not be very complicated or involve
data collection on a large scale, it should be cost effective, practical
and, of course, realistic. Often, in addition to analysis, judgment and
experience, it is based on common sense, intuition and 'gut
feeling' but, most of all, there needs to be a willingness to adopt
a disciplined approach. Depending on the circumstances involved in each
project, there will be different degrees of analysis. It is therefore
important to formulate a structured risk-analysis system.
Experience shows that, the identification and classification of
risks is more difficult than actually controlling them. Decision-makers
therefore need to identify the risk and plan a risk-management system,
otherwise they will lose control of the system and fail to find
solutions to the risk or solve any of the problems within the system.
Ghosh and Jintanapakanont (2004) suggest that risk management is a
tool for managing projects effectively throughout their lifecycles.
Due to the uncertain nature of risks, decision makers need to
consider which specific risks need to be analyzed and then devise
strategies to deal with them. Although risk management will not remove
every risk from the project, it is intended to identify them early on so
that their relative importance can be assessed and recommendations made
on how best to control them in order to provide the best outcome for the
project.
3. Research methodology
The most important task of risk management is to analyze the risk
so that appropriate decisions can be taken. Ahmed et al. (2007), Zayed
and Chang (2002) have cited Dias, Ioannou (1995b), as providing a
proposal for both a qualitative and quantitative approach to risk
analysis. A risk index is derived using the main risk categories within
a concession-type agreement. These are then rated using a scaled value.
The first stage in this paper is to specify the different variables,
(numerical and linguistic), which would affect the project risk. This
can be achieved by gathering all the related variables from the database
of previous projects and the project environment, (e.g. conditions in
the host country, the characteristics of the project and its location).
The BOT project risk factors can be selected by evaluating a wide range
of risk factors and their sub-factors can be obtained from the
literature (Tiong 1990, 1995a, b, 1996; Tiong et al. 1992; Levy 1996;
UNIDO 1996; Gupta, Narasimham 1998; Rana singhe 1999; Ozdoganm, Birgonul
2000). The second stage is to identify the variables and classify them
after removing the redundant ones. The risk factors can be grouped
within the main categories in order to reduce extensive effort and save
time in determining their interrelationships and evaluation. This should
be carried out by a group of experts in the field. The third stage is to
apply mathematical methods used for processing the data. In this study,
the methodology adopted will determine the most common and important
risk factors (variables), affecting the risk of BOT infrastructure
projects in Kuwait and, to then to discover the extent to which they can
be controlled. A set of linguistic variables are categorized according
to their relevance. The flow chart in Figure 1 demonstrates the
methodology used in this study. The absolute of project decision risk
analysis is the "risk index" V(x), which assesses the risk of
the project. This a non- dimensional risk measure shown in Eqn (1)
below:
V(x) = -[n.summation over (i=1)][w.sub.i][v.sub.i]([x.sub.i]). (1)
Dias and Ioannou (1995a) considered the value function as a
function used to transform an outcome (i.e. the performance level of an
attribute) into the decision-maker's relative worth for this
outcome. Transforming an attribute performance level to its
"worth" score, by means of a "value" function, is
more complicated than estimating the performance (quality), level of an
attribute directly through the use of a quantitative scale. It was very
difficult to choose appropriate quantitative constructs to represent the
model attributes, so a qualitative scale, common to all attributes, was
considered to be the best alternative for the development of the model.
The "worth" score of an attribute, [V.sub.i]([x.sub.i]), is a
non-dimensional number representing the performance level for a specific
project. In order to calculate the worth score of an attribute, its
performance level must be qualitatively assessed, and then the value
function used to transform the subjectivity assessment into a numerical
scale.
Questionnaire and expert criteria
The project risk attributes include a combination of qualitative
and quantitative factors and, in order to determine their
inter-relationships, it is necessary to assign "weights" to
the performance (quality), levels for each attribute contributing to the
project risk and to compare their relative importance. To carry out this
important process it is necessary to gather the required information
from experienced professionals in the industry, who are especially
involved in the development of BOT projects. For this research, the
selection of the professional group of respondents was based on the
following criteria:
--The expert should be involved in developing one of the BOT
projects;
--The expert should be one from the top project management team;
--A whole variety of project-type experience must be considered;
--Experts, (public or private agencies or financiers), were
selected from diverse project participants to reflect the likely
differences in opinions of project participants concerning the risk of
potential projects and the degree of importance of differing project
attributes.
A BOT project risk framework is an evaluation framework that is
multi-attributed and it was developed with information gathered from two
self-administered questionnaires, which were distributed with Kuwait.
The first questionnaire was designed to assess the common risk factors,
found in the literature, which affect the BOT project system. The first
questionnaire included 80 factors compiled from previous studies. These
were grouped together under the name of the corresponding risk factors.
Experts ranked the common BOT risks factors according to their relevance
in each of the project categories. These same experts were also asked to
add further attributes which they considered necessary to reinforce the
quality of the framework, (although no additional attributes were
actually identified in this method). The information gathered from the
first questionnaire was refined, compiled and screened by using mean
average and standard deviation and it resulted in five Risk Categories
with their related twenty-eight Risk Factors which were used to form a
hierarchical structure of the framework shown in Figure 2. Included in
the second questionnaire was the hierarchical structure of the
framework, which was designed to check the relevance of each factor with
regard to its corresponding category, to assign a weight and performance
level to each risk factor and also to evaluate the case study project
holistically. A variety of experts were chosen in order to identify and
evaluate the most common attributes, which would have the most
significant impact on the BOT project risk. The first questionnaire was
sent to sixteen local Kuwaiti BOT experts representing different sectors
(financial, legal, consultancy and development, university professors,
and official agencies). Their answers represented their understanding of
the problem. Five were project company managers involved in only one BOT
project, three were project heads of site offices, four were involved in
more than one BOT project as engineering consultants, two academic
experts were involved in a number of BOT projects as management
construction consultants, and two were involved in BOT projects as
financial consultants. The second questionnaire survey was sent to
fourteen of the original sixteen local Kuwait experts (two did not want
any further participation in the survey). These fourteen respondents
returned fully completed surveys and also had expressed a willingness to
offer more support to this study. It is possible that this low sample
number could be ascribed to the fact that the respondent criteria called
for very qualified experts in BOT systems who had the knowledge and
ability to deal with a whole complexity of qualitative decision factors
and their relationships. Previous studies have shown that the response
rates to requests for qualitative factor assessment has been very low:
for example, in Dias and Ioannou (1995b), only twelve and eight
respondents had accepted the invitation and completed the questionnaire
and in Ahmed et al. (2007), only twelve and fifteen respondents had
accepted the invitation and completed the survey. The resulting
"inconsistency ratio" of the pairwise comparison matrix was
< 0.1 for answers from every respondent. This represents a further
encouraging sign of the reliability of the responses received.
[FIGURE 1 OMITTED]
[FIGURE 2 OMITTED]
3.1. BOT risk model attributes selection
The first questionnaire assessed the common risk factors, which
affected the management systems for BOT infrastructure projects and also
ranked the common BOT risk factors according to their relevance to each
of the project categories on a qualitative scale of one to nine points.
After careful selection of the project risk factor model
attributes, 28 attributes were extracted from the first questionnaire.
The attributes were identified and classified under five main risk
categories. In order to reduce the size of the comparison matrix and
also to ensure that the comparison attributes were more meaningful, only
attributes of the same nature were compared and these were divided into
five categories. This was following the assumption made by Miller
(1956), that the brain could simultaneously process 7 [+ or -] 2 items.
3.2. BOT project risk attributes relative weights
From the responses obtained, pairwise comparison matrices of the
project risk model were constructed, which represented their relative
importance, based on a numerical scale of 1-9. By means of the
Eigenvalue Method (EM) in the Analytical Hierarchy Process (AHP) the
categories and their local weight attributes were calculated using the
computer software package "Expert Choice 11" which is a
computer application of the AHP technique. The input data included the
formatted risk framework categories and attributes as a hierarchical
structure with all the given relationships shown, as well as the
pairwise comparison matrix values for each participant. Expert Choice 11
was used to find the inconsistency ratio of each matrix. For each
respondent, the software output shows the inconsistency ratio for each
comparison matrix and the local importance weight for each decision
factor (alternative), within the category (objective), and the
importance of the composite weight of each factor to the total project
risk (goal).
3.3. Category weights
The project risk attributes were classified within five main
categories as shown in Figure 2. The individual results provided by
participants, for comparison of the relative importance of the different
categories, and the calculated category weights, are presented in Table
1.
The results indicate that 35.7% of the responses suggested that the
"Financial & Revenue" risk category is the most important
one (superior), within the project risk decision, while 28.5% find the
"Country Risks" category to be the most important, ranking it
second in the list. A further 21.5% thought that "Construction
& Operating" risk was the most important category, while 14.3%
found "Development Risk" to be the most important category.
"Promoting & Procurement" risks came out as the least
important of all. Taking average weights for the five categories,
indicates that "Financial & Revenue" risks carry 28% of
the total project risk, while "Country Risks" follow closely
with 27%, "Construction & Operating" risk carries 18%,
"Development Risk" has 17% and "Promoting &
Procurement" risk has 10% of the total.
From this it can be concluded that the "Financial &
Revenue" risks category is the most important, being slightly ahead
of the "Country Risks" category and about twice as significant
as the "Construction & Operating" risk and
"Development Risk" categories. It thus follows that the
decision-maker needs to give the highest priority to "Financial
& Revenue" risks and "Country Risk" factors when
carrying out an assessment for project risks in Kuwait.
In order to calculate the contribution weight of each category to
the total project risk, the overall weight of individual responses (the
group weight) for each category is required. A geometrical, rather than
the arithmetic, mean of responses was used to group the individual
judgments for each category, because, according to Saaty and Aczel
(1983), the method used to consolidate individual judgments, needs to
preserve the reciprocal nature of the comparison matrix. From Table 2 it
can be seen that the group weights of categories are approximately
similar to the average of the local weight. It is apparent that the
"Financial & Revenue" risks category has the highest
weight of 31.1%, followed by "Country" risks, which have 23.4%
and the "Promoting & Procurement" risks category, which
has the lowest weight of about 10%.
3.4. Attribute weights
The twenty-eight Risk Factors were classified and placed within
their respective Risk Category: six in the Financial & Revenue Risks
category, six within the Country Risks category, six within the
Promoting & Procurement Risks category, six under the Construction
& Operating Risks category and four attributes under the Development
Risks category.
The relative importance to the participants of each attribute
within each category and also the local attribute weights are presented
in Table 3. Considering the local weights of attributes within their
categories, it is apparent that "Changes in general
legislation" will affect the project and the regulations in the
"Country Risks" category. The "failure to raise the
necessary finance" will affect the "Financial &
Revenue" risks category. "Lack of integrity during the
tendering process" will affect the "Promoting &
Procurement Risks" category. "Changes in Design" during
the construction phase will affect the "Development Risk"
category. These are the most significant decision factors, which will
have the maximum impact on the project risk, and therefore should be
given a very high priority by the decision-maker.
The group weights of the Risk Factors were calculated by a similar
method to that used for the Risk Category group weights, in order to
find the contribution of each Risk Factor to its risk Category. From the
results in Table 4, it can be seen that the categories with the highest
weights are as follows. "Changes in General Legislation Affecting
the Project" in the "Country Risks" category, an
"Failure to Raise Finance" in the "Financial &
Revenue" risks category, a "Lack of Integrity in the Tendering
Process" in the "Promoting & Procurement Risks"
category, "Use of Technology" in the "Development
Risk" category and "Inappropriate Operating Methods" in
the "Construction & Operating Risk" category. These
weights are: 0.261, 0.248, 0.305, 0.408 and 0.242 respectively, within
their Risk Categories. The weights of the attributes within each Risk
Category, sum to unity.
Afterwards, the similarities and differences between individual
weights were checked and the contributions of individual Risk Factors to
the project risk were calculated. In order to do this, it was necessary
to determine the individual relative weight of each Risk Factor towards
the total project risk (composite weight "[W.sub.i]"). The
composite weight of an attribute is equal to the local weight of that
attribute "[W.sub.i]" multiplied by its local category weight
"[W.sub.c]":
[W.sub.i] = [W.sup.1] x [W.sub.c]. (2)
The sum of the composite weights of the attributes must equal
unity, so:
[summation] [W.sub.i] = 1. (3)
The composite weights of the twenty-eight Risk Factors were
calculated from Eqn (2) for each contribution, displayed in Table 5.
The average composite weight of each Risk Factor to within [+ or -]
standard deviation is given in Figure 3. These results show that the
"use of technology", "unavailability of power
supply" and the "Government's failure to provide
permits", have the highest weights of 0.0707, 0.065 and 0.0636,
respectively, with the minimum standard deviation. However, a "lack
of experience", "error in operation" and
"maintenance cost estimates", as well as "lack of
commitment to concession contracts" attributes, have the minimum
weights of 0.0514, 0.0500 and 0.0464, respectively.
[FIGURE 3 OMITTED]
The respondents recommended that the BOT project participants
should pay particular attention to the "Country",
"Construction & Operating" and "Financial" Risk
categories. However, they also suggested that they need to consider all
the other model risks, because their weights are relatively close.
The relative importance of an attribute to the total project risk
is given by its group composite weight. This can be found by multiplying
the Risk Factor weights (Table 4) by the corresponding group Risk
Category weights (Table 2).
For example, to find the group composite weight of the attribute
"Government Instability", the group weight of this attribute
must be multiplied by the group weight of the "Country" Risk
category. Therefore, we find that the group composite weight of this
attribute is 0.126 x 0.234 = 0.02945. Table 6 shows the group composite
weights of attributes towards the project risk. The highest weights of
7.7%, 6.9%, 6.1%, 4.1% and 3.5% were allotted to "failure to raise
finance", "use of technology", "changes in general
legislation" affecting the project, "inappropriate operating
methods" and "lack of integrity on the t endering
process" attributes in the "Financial",
"Development", "Country", "Construction &
Operating", and "Promoting & Procurement" categories,
respectively.
In Figure 4, the individual range of each attribute weight, shown
in the form of a column, can be seen. For each attribute, the lower part
of the column represents the minimum importance weights, which were
assigned by respondents, while the top of the column indicates the
maximum importance weights.
The darker line in the middle indicates the group composite weight
of the attribute, while the dark regions, which can be seen above and
below the line of group composite weights, indicate the standard
deviation of the individual Group composite Risk Factors with individual
composite weights, where half of the standard deviation is above and the
other half is below the line. A table, which includes the data displayed
in Figure 4, can be found in the Appendix. A close look at these figures
indicates that three attributes have quite a large range between their
maximum and minimum importance weights. "Changes in the project
specifications" attribute will have the maximum range of weight
difference, with reference to the different replies from the
respondents, (the minimum weight was given by R13 'government
consultant' and the maximum weight was given by R6 'private
consultant'). Three attributes have quite a small range (i.e. the
difference in weight) with the 'lack of experience' attribute
having the smallest, due to the fact that respondents have approximately
the same view regarding the risk weight for the project team experience.
[FIGURE 4 OMITTED]
3.5. Attributes worth scores and the framework validation approach
It was Dias and Ioannou (1995b) who stated that, due to
multi-attribute decision models being essentially subjective in nature,
it is difficult to use external criteria to assess the validity of
evaluation models objectively. For this reason, previous researchers
have used indirect approaches, such as convergent validation, predictive
validation and axiomatic validation. Convergent validation involves
comparing the results obtained by a multi-attribute decision framework
with holistic evaluations made by the decision maker. For this approach,
several alternative projects are defined and then evaluations, based on
the framework and on the decision maker's judgments, are compared
from how they rate and/or rank the alternatives. If there is a good
correlation between the decomposed framework and the holistic
evaluation, then it can be verified that the framework meets the
decision maker's holistic evaluation. A convergent validation
approach was used to validate the risk multi-attribute decision
framework. An existing BOT projects, the Sulaibiya Waste Water Plant in
Kuwait, was described and presented to the respondents, who were then
asked to evaluate the performance of the framework attributes in the
three project profiles on a scale of 1-9 and then to rate them
holistically using a scale of 0-10. One of the most prominent of BOT
projects in Kuwait was the Sulaibiya Waste Water Plant and it was chosen
for this reason. In this case, unlike the Dias and Ioannou (1995b)
approach, the performance value of p1 is kept at zero in the other
alternative (P2 = 100) approaches. The reason for this assumption was
because experts considered that all of the selected risk factors were
significant and that their impact on the outcome of the project risk
would be measurable. The p2 = 100 approach involved keeping the
performance point P2 at 100 points in order to increase the range of
performance satisfaction. The "worth" of each project profile
was calculated using different decomposed evaluation approaches (that
due to Dias and Ioannou, P2 = 100). To achieve this, the following
approaches were used.
The decomposed evaluation approach (P2 = 100) was used to calculate
the "worth" score for each project profile in order to
establish the best approach to obtaining the holistic evaluation.
Dias and loannou (1995b) approach
For each model attribute, the worth score [V.sub.i]([x.sub.i]) was
calculated by means of the value curves, considering points P1 and P2 as
the performance extremes. However, when the attribute's performance
P [less than or equal to] P1, the attribute's worth will receive a
zero score, but if P < P2, a 100 score will result. In order to
ascertain the attributes' "worth", the value curve, based
on the modified value curve of Dias and Ioannou, was used.
P2 = 100 approach
For this approach, the P1 value is always equal to zero, based on
the logical assumption that all of the framework decision factors
(attributes) are important and will have some impact on the project
risk. Their performance level P must therefore be considered in the
evaluation (even for very small performance values where P [less than or
equal to] P1), whilst the P2 value is always equal to 9 (the extremely
desirable point on the performance scale). The value curve will
therefore extend from the origin to the extreme point of extremely
desirable.
4. Risk framework decision factors evaluation results
The attributes contribution to the project risk can now be found
for each approach by multiplying their worth scores by their composite
weights and the total project value (index) will be the result of the
decomposed evaluations according to Eqn (1). The individual holistic
evaluations and the decomposed evaluation by Eigenvalue Method (EM) of
the P2 = 100 approach for each project profile provided are shown in
Table 7.
The average results of the project profiles decomposed evaluations
for each of the respondents were calculated for the P2 = 100 approach
and plotted against the average holistic evaluation and the results are
given in Figure 3. The differences between the P2 approach and the
holistic evaluation are compared from observations, the P2 = 100
approach curve is found to be very close to the holistic curve, which
means that it captures the holistic approach. The group results of the
holistic and decomposed evaluations for each project profile were
calculated by taking the averages of the individual evaluations and the
results are shown in Table 7. In order to validate the framework, the
holistic and the decomposed evaluation were compared by Pearson's
product moment correlation coefficient (r). The correlation process
compared the individual holistic evaluations and decomposed evaluations,
which were obtained from the model. The results, as shown in Table 7,
indicate that the framework correlates well with the holistic approach
(the correlations range between 0.71 and 0.81).
[FIGURE 5 OMITTED]
5. Using the risk framework in the project risk study
The identified results and the participants' feedback were
used to assess the current BOT Risk Management Framework and to advise
concerning the amendments that need to be made to the Framework.
Feedback from the participants in the field study indicated that many
aspects of the proposed framework would be a helpful aid to
decision-makers, in both the public and private sectors.
The main reason for the development of the risk framework was to
help the decision-maker in evaluating the risk of their infrastructure
project during the preliminary stages, before proceeding with the
project. In this manner, both the private sector and the Government in
Kuwait should have a fuller picture of the most important BOT risks that
they will face when considering the initiation of BOT projects in
Kuwait. Having a more informed "picture" will facilitate the
process of risk management (risk allocation, mitigation) in the early
stages of procurement of BOT Infrastructure projects.
Using the Risk Management Framework involves the assignment of the
most important Risk Factor weights and their performance (quality)
levels, developing Risk Factor value curves (P2 = 100) and computing the
project risk index. When the Risk Factor indexes, which form the total
project risk index, have been determined, those Risk Factors that affect
the total project risk, will be apparent and the decision-maker can then
implement strategies to manage these risks and re-evaluate them, so that
their effect on the project can be mitigated and/or minimized.
For example, considering the use of the P2 approach in the
Sulaibiya Waste Water Treatment Plant Project, the resulting value
indices for the twenty-eight risk Factors, as shown in Table 8 and
Figure 6, indicate that the "Use of Technology" (UOT) Risk
Factor is the highest weighted Risk Factor in the project with a value
index of 3.30. Whereas, "Inappropriate Operating Methods"
(IOM) Risk Factor is the second highest weighed Risk Factor with a value
index of 3.0. "Unavailability and quality of personnel to operate
the facility", had a weighed Risk Factor of 2.98, closely followed
by "Performance Related Risk" (PRR) with a weighed Risk Factor
with a value index of 2.95. "Excessive Development Costs" has
a weighed Risk Factor with a value index of 2.52. "Change in
Project Specification" has a weighed Risk Factor with a value index
of 2.52, "Error in Forecasting Demand for Service" has a
weighed Risk Factor with a value index of 2.50, and "Failure to
receive revenues from principal (end user)" has a weighed Risk
Factor with a value index of 2.50. Therefore, the decision-makers should
pay more attention to the above Risk Factors than to the others, because
their effect on project risk/viability is more critical and risk
management techniques are required in order to mitigate and/or minimize
their effect by allocating the risks to a party which is capable of
handling them.
The most salient Risk Factors for the Sulaibiya Waster Water Plant
will be considered and the "Use of Technology" Risk Factor
indicating that there was public concern that the water (collected from
sewage) was not being treated correctly, nor thoroughly enough, to be
acceptable as drinking water. The second part to this was that the
equipment used in the filtering and cleaning processes was not up to
date and not operated correctly. Excessively sophisticated technology
may not be practicable in some BOT projects, not only increasing to the
initial cost of the project but increasing operation, maintenance and
repair costs. Suitable technology needs to be updated during the
operating time of the plant and be fit for purpose during, and after,
the handover at the end of the concession period.
Second Risk Factor was "Inappropriate Operating Methods"
at 3.00, relating to the unavailability of trained personnel, i.e.
whoever was operating the plant, would they do it right? And this posed
major concerns regarding safety of the water. It can be seen that these
first tow Risk Factors are closely linked. This risk factor is due to a
shortage of highly skilled productive workers, i.e. Scientists &
Engineers and of those working in the company, due to cultural values
and belief, there is a perception that there is a lack of work ethic. It
can be overcome by having experienced and reliable management personnel.
Good management personnel as well as experienced operating personnel are
needed to operate the plant. The senior management of the plant makes
the operating decision policy and arranges for the training, maintenance
and inspection regime of operation system of the plant.
In the third place is the "Unavailability and quality of
personnel to operate the facility" Risk Factor can be initially
addressed by the private sector who are required by the BOT contract to
provide the personnel and expertise to run and operate the facility to a
good standard including any technical documentation. BOT infrastructure
project contracts in future in Kuwait must include provisions that the
private sector provides education and training to Kuwaitis in order
ensure that the operation of the plant is maintained to a good standard.
This becomes crucial when approaching the end of the concession period
to allow a smooth transfer and operation of the plant.
The fourth Risk Factor was "Performance Risk Factor"
indicating that there is a perception that the monitoring of the BOT
infrastructure facility during the concession period is not carried out
correctly by the Kuwaiti government. Proper monitoring of performance
during the concession period is essential, not only for the success of
the project and its continued operation after the concession period, but
to ensure that the consumer is getting "value for money".
There may also be a concern during construction whereby, sub-contractors
do not complete their part of the project on time or to the required
standard or specification. Performance incentives could be introduced to
encourage the contractor to complete their part on time and to
specification.
The fifth Risk Factor of "Excessive Development Cost"
indicates that some private investors may be unenthusiastic about
bidding for a BOT project due to high development costs which they may
never recover. Decision-makers should pay more attention to the above
Risk Factors than to the others, because their effect on project
risk/viability is more critical and risk management techniques are
required in order to mitigate and/or minimize their effect by allocating
the risks to a party which is capable of handling them.
Sixth Risk Factor was the "Change in Project
Specification", a Risk Factor taken very seriously by the private
sector but not so seriously by the public sector (as Figure 4
demonstrates where the "group composite weights" of the
importance of this Risk Factor were completely opposite to each other
depending on the respondent place of work, i.e. Private company and very
important; or Public Sector and not so important).
Seventh Risk Factor was "Failure to receive revenues from
principal (end user)". For services such as electricity and water,
government officials do not collect/ask for payment. Therefore, ordinary
people just do not pay their bills. This has become the "norm"
in Kuwait and as a result, all moneys due are cancelled after 5 years
because people cannot be expected to pay the full accumulated amount in
one go. This extends to the private sector as well, where private
companies do not pay any utility bills either. This has become standard
practice and is a part of Kuwaiti culture as the government rarely
enforces existing laws and does not prosecute any people/companies.
Also, recently, people are advised by some MP's not to pay any
utility bills because the MP's are making promises that the bills
will be cancelled and paid by the government as a form of vote chasing.
The prevailing public attitude is: "As Kuwait is such a rich
country, then the government can afford to pay". There have been
various efforts by past governments to make people pay their utility
bills, including discounts, and even amnesties to make a fresh start,
but nothing has worked so far. The present government has recently taken
a tougher stance in that: if a citizen of Kuwait has an outstanding
utility bill then they are not allowed to leave the country without
paying the utility bill first, and the government has opened offices in
Airports and border crossings to enable citizens to pay their utility
bills before being allowed to leave the country.
The eight Risk Factor, but not the last, is "Error in
Forecasting Demand for Service" and could be due to changes in
demand of the product due to economic downturns or competition. In the
case of failure to receive sufficient revenues from the end user, the
Kuwaiti government should allow the private company to revise their
pricing structure, and even provide loans and/or grants whenever the
revenues drop below certain amounts agreed in the contract. In the case
of competition, the Kuwaiti government is in a unique position at the
outset of the procurement process to protect the project from
competition, i.e. there is a guarantee that a competing plant will be
built during the lifetime of the existing project. Changing economic
policies by the Kuwaiti government is another method of guaranteeing
agreed revenue earnings, i.e. the Kuwaiti government takes a lower
percentage of the profit thereby guaranteeing the private company's
profit margin. Error in forecasting long term demands for service(s) may
prompt the Kuwaiti government to change the length of the concession
period of the BOT project with compensation being paid to the private
company and the time of the handover brought forward.
The index value listing of the Risk Factors, determined by the
Kuwaiti respondents, may have been due to their perception of, and
attitude to, risk based on experience gained mainly in Kuwait.
Furthermore, the questionnaire was answered after all of the respective
BOT infrastructure projects had been completed and "hindsight"
may have played a significant part in their evaluation of the risks;
"Experience is something one gains a second after it is
needed". Although the Risk Management Framework was constructed
after the completion of the case study, it does still provide a valuable
insight into the potential risk areas of the case study with respect to
Kuwait.
Conclusions
This study has identified twenty eight major risk factors affecting
BOT infrastructure projects in Kuwait and these have then been
classified under their main relative categories, "Financial &
Revenue Risks", "Country Risks", "Construction &
Operating Risks", "Development Risks" and "Promotion
& Procurement Risks", in order to determine their
inter-relationships and their effect on the project. The project risk
factors were evaluated by means of a Risk Management Framework. The
importance of the decision factors were weighted by means of
'Expert Choice 11.5', utilizing the Analytical Hierarchy
Process (AHP), technique adopted by Saaty (1980). The results indicated
that the "Financial & Revenue" category was the most
important (31.10%), followed by "Country" Risks (23.40%), and
then "Construction & Operation" (17.10%), next in
importance are "Development" (17.00%) and finally
"Promoting & Procurement" (11.40%) categories. From these
results, it can be deduced that the project viability is mainly
dependent on the management of the financial and commercial Risk
Factors. It is important that, during the project feasibility study
stage, the crucial sensitive Risk Factors are taken into account and
evaluated. In an effort to determine the contributions of the decision
factors to the project risk index, the P2 = 100 approach was applied to
a case study project (The Sulaibiya Wastewater Treatment Plant in
Kuwait). The outcomes were correlated to the direct holistic evaluation
of the project profile and the indications were that the outcomes of the
P2 = 100 approach were very close to the holistic evaluation (the
Pearson coefficient lies between 0.77 indicating a good correlation).
In this paper, the Authors present the following contributions to
risk analysis of BOT infrastructure projects:
--A list of the most important qualitative decision factors
involving risk in BOT infrastructure projects, which have been carefully
identified, selected and then screened by a group of experts within
Kuwait was provided;
--This study makes a contribution to work in the field of BOT
Infrastructure projects in the context of Kuwait, as it is one of the
very few studies on Kuwait that have been conducted in this area.
Although the BOT method has been successfully used in many countries,
Kuwait has had little experience in using private finance for its
infrastructure projects, as it has certain characteristics requiring
special attention;
--The study will be of help to private sector companies who have
insufficient knowledge concerning the business environment within the
country and it will also benefit the public sector, which has limited
experience of partnership;
--A new framework "P2 = 100" approach, provides an
in-depth analysis of the qualitative, (linguistic), decision factors
which have previously been evaluated in an arbitrary way. Since the
decision-makers within the Kuwaiti Government and the private sector
usually consider only the project quantitative, (numeric), decision
factors, this could change their method of thinking and help them
re-evaluate their attitude and perception of risks effecting BOT
projects;
--An appropriate decision-support tool, which should help the
decision-maker to determine those risk decision factors which would
prove most effective in minimizing if not eliminating some project
risks, and we also put forward some strategies to increase the
performance of these factors is proposed. With regard to further work,
researchers need to track these critical factors during the life-time of
many BOT infrastructure projects. Specific software solutions that can
deal with the complex nature of such infrastructural projects should be
developed. The suggested output for such software should include indexes
for different options, supported by graphs and tables which illustrate
the inter-relationships between the factors which can be easily applied
by all parties involved in BOT infrastructure projects.
doi: 10.3846/13923730.2013.802706
References
Ahmed, F. M. S.; Miroslaw, J. S.; Ismail, B. 2007. BOT viability
models for large scale infrastructure projects, Journal of Construction
Engineering and Management ASCE 133(1): 50-63.
http://dx.doi.org/10.1061/(ASCE)07339364(2007)133:1(50)
Askar, M.; Gab-Allah, A. 2002. Problems facing parties involved in
build, operate, and transfer projects in Egypt, Journal of Management in
Engineering 18(4): 173-178.
http://dx.doi.org/10.1061/(ASCE)0742597X(2002)18:4(173)
Baloi, D.; Price, A. D. F. 2003. Modeling global risk factors
affecting construction cost performance, International Journal of
Project Management 21(4): 261-269.
http://dx.doi.org/10.1016/S0263-7863(02)00017-0
Cheung, E.; Chan, A. P. C.; Kajewski, S. 2010.The public
sector's perspective on procuring public works projects comparing
the views of practitioners in Hong Kong and Australia, Journal of Civil
Engineering and Management 16(1): 19-32.
http://dx.doi.org/10.3846/jcem.2010.02
Dey, P. K.; Ogulana, S. O. 2004. Selection and application of risk
management tools and techniques for build-operate-transfer projects,
Industrial Management and Data Systems 104(4): 334-346.
http://dx.doi.org/10.1108/02635570410530748
Dey, P. K.; Ogunlana, S. O.; Takehiko, N. 2002. Risk management in
build-operate-transfer projects, International Journal of Risk
Assessment and Management 3(2/3/4): 269-291.
Delmon, J. 2000. BOO/BOTprojects: a commercial and contractual
guide. London: Sweet & Maxwell Limited, 1: 40-62.
Dias, A. Jr.; Ioannou, G. Ph. 1995a. Debt capacity and optimal
capital structure for privately financed infrastructure projects,
Journal of Construction Engineering and Management, ASCE Dec, 404-H4.
http://dx.doi.org/10.1061/(ASCE)07339364(1995)121:4(404)
Dias, A. Jr.; Ioannou, G. Ph. 1995b. Desirability model for the
development of privately promoted infrastructure projects, UMCEE Report
No.95-09, Vol. 1, University of Michigan, USA.
Ebrahimnejad, S.; Mousavi, S. M.; Seyrafianpour, H. 2010. Risk
identification and assessment for build-operate transfer projects: a
fuzzy multi attribute decision making model, Expert Systems with
Applications International Journal 37: 575-586.
http://dx.doi.org/10.1016/j.eswa.2009.05.037
Esq, L. F. 1996. Introduction to B.O.T., in Proc., Conf. on
International Contracts of B.O.T. and Their Amicable Solutions, Vol. 1.
Flanagan, R.; Norman, N. 1993. Risk management and construction.
London: Blackwell Scientific Publications. 208 p.
Ghosh, S.; Jintanapakanont, J. 2004. Identifying and assessing the
critical risk factors in an underground rail project in Thailand: a
factor analysis approach, International Journal of Project Management
22(8): 632-642. http://dx.doi.org/10.1016/j.ijproman.2004.05.004
Grimsey, D.; Lewis, K. K. 2004. Public-Private Partnerships.
Cheltman, UK: Edward Elgar. http://dx.doi.org/10.4337/9781845423438
Gunn, S. 2005. Consideration of pre-contract risks in international
PFI projects. Risk Management Considerations in Construction Projects.
The University of Salford, Manchester, Salford Centre for Research and
Innovation (SCRI).
Gupta, M. C.; Narasimham S. V. 1998. Discussion of CSFs in
competitive tendering and negotiation model for BOT projects, Journal of
Construction Engineering and Management, ASCE, Sept./Oct. 430 p.
Huang, Y. L. 1995. Project and policy analysis of
build-operate-transfer infrastructure development: PhD thesis. UMI
Company, Michigan, 15-23.
Kim, G. 2010. Risk performance indexes and measurement systems for
mega construction projects, Journal of Civil Engineering and Management
1(4): 586-594. http://dx.doi.org/10.3846/jcem.2010.65
Klein, M.; So, J.; Shin, B. 1996. Transaction costs in private
infrastructure projects--are they too high? Public Policy of Private
Sector, The World Bank, Washington, DC.
Kumaraswamy, M. M.; Morris, D. A. 2002. Build-operate-transfer-type
procurement in Asian mega projects, Journal of Construction Engineering
and Management 128(2): 93-102.
http://dx.doi.org/10.1061/(ASCE)07339364(2002)128:2(93)
Levy, S. M. 1996. Build, operate, transfer paving the way for
tomorrow's infrastructure. Toronto, Frank Mercede and Sons, Inc.
Stamford, CT. 411 p.
Li, B.; Akintoye, A.; Edwards, P. J.; Hardcastle, C. 2005. The
allocation of risk in PPP/PFI construction projects in the UK,
International Journal of Project Management 23(1): 25-35.
http://dx.doi.org/10.1016/j.ijproman.2004.04.006
Liddle, B. T. 1997. Privatization decision and civil engineering
projects, Journal of Management in Engineering 13(3): 73-78.
http://dx.doi.org/10.1061/(ASCE)0742597X(1997)13:3(73)
Loosemore, M. 2007. Risk allocation in the private provision of
public infrastructure, International Journal of Project Management
25(1): 66-76. http://dx.doi.org/10.1016/j.ijproman.2006.06.005
Loosemore, M.; Raftery, J.; Reilly, C.; Higgon, D. 2006. Risk
management in projects. London: Taylor & Francis. 260 p.
Miller, G. A. 1956. The magical number seven, plus or minus two:
some limits on our capacity for processing information, Psychological
Review 63(2): 81-97. http://dx.doi.org/10.1037/h0043158
Nassar, G. 1996. What is B.O.T. in Proc., Conf. on International
Contracts of B.O.T. and Their Amicable Solutions, Vol. 1.
National Council for Public-Private Partnerships, USA 2009. How
PPPs work-Public-private partnerships defined [online], [cited 26 August
2009]. Available from Internet: http://www.ncppp.org/howpart/index.shtml
Ozdoganm, I. D.; Birgonul, M. T. 2000. A decision support framework
for project sponsors in the planning stage of build-operate-transfer
(BOT) projects, Journal of Construction Management and Economics 18(3):
343-353. http://dx.doi.org/10.1080/014461900370708
Ranasinghe, M. 1999. Private sector participation in infrastructure
projects: a methodology to analyze viability of BOT, Journal of
Construction Management and Economics 17(5): 613-623.
http://dx.doi.org/10.1080/014461999371222
Raz, T.; Michael, E. 2001. Use and benefits of tools for project
risk management, International Journal of Project Management 19(1):
9-17. http://dx.doi.org/10.1016/S0263-7863(99)00036-8
Regan, M.; Smith, J.; Love, P. 2009. Public-private partnerships:
what does the future hold, in Proc., RICS Construction and Building
Research Conf. (COBRA), Royal Institution of Chartered Surveyors,
London, 462-474.
Saaty, T. L. 1980. The analytical hierarchy process. USA:
McGraw-Hill, Inc. 287 p.
Senturk, H. A.; Yazici, G.; Kaplanoglu, S. B. 2004. Case study:
Izmit domestic and industrial water supply build-operate-transfer
project, Journal of Construction Engineering and Management 130(3):
449-454. http://dx.doi.org/10.1061/(ASCE)07339364(2004)130:3(449)
Shen, L. Y.; Bao, H. J.; Wu, Y. Z.; Lu, W. S. 2007. Using
bargaining-game theory for negotiating concession period for BOT-type
project, Journal of Construction Engineering and Management, ASCE
133(5): 385-392. http://dx.doi.org/10.1061/(ASCE)07339364(2007)133:5(385)
Shen, L. Y.; Lee, K. H.; Zhang, Z. 1996. Application of BOT system
for infrastructure projects in China, Journal of Construction
Engineering and Management 122(4): 319-323.
http://dx.doi.org/10.1061/(ASCE)07339364(1996)122:4(319)
Shen, L. Y.; Li, H.; Li, Q. M. 2002. Alternative concession model
for build operate transfer contract project, Journal of Construction
Engineering and Management, ASCE 128(4): 326-330.
http://dx.doi.org/10.1061/(ASCE)07339364(2002)128:4(326)
Shen, L. Y.; Wu, Y. Z. 2005. Risk concession model for build
operate transfer contract projects, Journal of Construction Engineering
and Management, ASCE 131(2): 211-220.
http://dx.doi.org/10.1061/(ASCE)07339364(2005)131:2(211)
Songer, A. D.; Diekmann, J.; Pecsok, R. S. 1997. Risk analysis for
revenue dependent infrastructure projects, Construc tion Management and
Economics 15(4): 377-382. http://dx.doi.org/10.1080/014461997372935
Tiong, R. L. K. 1990. Comparative study of BOT projects, Journal of
Management in Engineering, ASCE, January, 6: 107-122.
Tiong, R. L. K. 1995a. Risks and guarantees in BOT tender, Journal
of Construction Engineering and Management, ASCE, June, 183-188.
http://dx.doi.org/10.1061/(ASCE)07339364(1995)121:2(183)
Tiong, R. L. K. 1995b. Competitive advantage of equity of BOT
tender, Journal of Construction Engineering and Management, ASCE, Sept.,
282-289. http://dx.doi.org/10.1061/(ASCE)07339364(1995)121:3(282)
Tiong, R. L. K. 1995c. Impact of financial package versus technical
solution in BOT tenders, Journal of Construction Engineering and
Management, ASCE, Sept, 304-311.
http://dx.doi.org/10.1061/(ASCE)07339364(1995)121:3(304)
Tiong, R. L. K. 1996. CSFs in competitive tendering and negotiation
model for BOT projects, Journal of Construction Engineering and
Management, ASCE, Sept, 202-211.
Tiong, R. L. K.; Alum, J. 1997. Final negotiation in competitive
BOT tender, Journal of Construction Engineering and Management, ASCE
6-10. http://dx.doi.org/10.1061/(ASCE)07339364(1997)123:1(6)
Tiong, R. L. K.; Yeo, K. M.; McCarthy, S. C. 1992. Critical success
factors in winning BOT contracts, Journal of Construction Engineering
and Management, ASCE, June, 217-228.
http://dx.doi.org/10.1061/(ASCE)07339364(1992)118:2(217)
United Nations Industrial Development Organisation UNIDO 1996.
Guidelines for Infrastructure Development through Build-Operate-Transfer
(BOT) Projects, Vienna.
Walker, C.; Smith, A. 1995. Privatized infrastructure the build
operate transfer approach. London: Thomas Telford Services Ltd.
http://dx.doi.org/10.1680/pitba.20535
Wilburn, W. K.; Thomas, J. R. 1994. Build-operate-transfer. An
emerging trend in project financing, Construction Business View,
May/June.
World Bank. 1994. World development report: infrastructure for
development. Rep. No. 13184, Washington, D.C.
Zayed, T. M.; Chang, L. M. 2002. Prototype model for
build-operate-transfer risk assessment, Journal of Management
Engineering 18(1): 7-16.
http://dx.doi.org/10.1061/(ASCE)0742597X(2002)18:1(7)
Zavadskas, E. K; Turskis, Z.; Tamosaitiene, J. 2010. Risk
assessment of construction projects, Journal of Civil Engineering and
Management 16(1): 33-46. http://dx.doi.org/10.3846/jcem.2010.03
Khalid Fahad AL-AZEMI (a), Ran BHAMRA (a), Ahmed F. M. SALMAN (b)
(a) Wolfson School of Mechanical and Manufacturing Engineering,
Loughborough University, Loughborough, LE11 3TU, UK
(b) Construction Engineering Department, College of Engineering,
Dammam University, Dammam, KSA
Received 25 Oct 2011; accepted 10 Jul 2012
Corresponding author: Ran Bhamra
E-mail: r.s.bhamra@lboro.ac.uk
Khalid Fahad AL-AZEMI. He is a member of the Kuwait Society of
Engineers, and a PhD Graduate of Wolfson School of Mechanical and
Manufacturing Engineering, Loughborough University, UK, received his MSc
in Engineering and Manufacturing Management from Coventry University,
UK. His main research interest is risk management in
build-operate-transfer (BOT) infrastructure projects.
Ran BHAMRA. A Senior Lecturer in Engineering Management in the
Wolfson School of Mechanical and Manufacturing Engineering at
Loughborough University. He has over 15 years of manufacturing industry
experience in manufacturing engineering and management. His main
research interests include organisational strategy, resilience and
sustainability.
Ahmed F. M. SALMAN. Assistant Professor of Construction Engineering
and Management, BSc in Civil Engineering, from Zagazig University in
Egypt in 1986, MSc in Construction Management from Zagazig University,
Egypt in 1994, and PhD from, Zagazig University, Egypt, and Purdue
University, USA "Joint Supervision grant". His main research
interest areas are in construction project management, Build-Operate and
Transfer (BOT), construction engineering modeling and decision making,
and international construction contracting.
Table 1. Category pairwise comparison matrix and
relative weights
R1 R2 R3 R4 R5 R6 R7
Category
Relative
Importance
CR versus FR 1 1/9 1/3 6 1 1/3 1/2
CR versus PP 2 1/7 1/4 9 3 1/3 1/2
CR versus DR 2 1/6 1/5 9 1 1/3 2
CR versus Co 8 1 1/5 9 1 1/5 2
FR versus PP 7 3 1/2 9 1 1/3 6
FR versus DR 4 5 1/3 9 1/3 1/7 5
FR versus CO 4 5 1/5 7 2 1/3 3
PP versus DR 1/5 1 1/6 1 1 1 1
PP versus CO 1 1 1/5 1 2 1/3 1/2
DR versus CO 4 1 1/2 1 3 1/2 1/2
Weights
CR 0.30 0.05 0.05 0.61 0.25 0.06 0.17
FR 0.39 0.51 0.09 0.26 0.17 0.09 0.46
PP 0.07 0.18 0.12 0.04 0.18 0.19 0.13
DR 0.18 0.15 0.32 0.04 0.29 0.27 0.09
CO 0.06 0.11 0.43 0.04 0.12 0.38 0.15
R8 R9 R10 R11 R12 R13 R14
Category
Relative
Importance
CR versus FR 1/3 4 5 1 1 1/2 2
CR versus PP 1/3 7 5 3 2 7 5
CR versus DR 1/3 7 5 1 1 1/3 7
CR versus Co 1/5 9 5 1 9 1/3 7
FR versus PP 1/4 9 3 1 9 9 7
FR versus DR 1 9 3 1/2 2 3 9
FR versus CO 1/3 5 3 3 5 2 7
PP versus DR 1 1 1/3 1 1/5 1/6 2
PP versus CO 1/3 1 1/3 1 1/2 1/4 1/3
DR versus CO 1/5 1/3 1/2 3 5 1/2 1/5
Weights
CR 0.06 0.55 0.53 0.24 0.28 0.13 0.44
FR 0.12 0.29 0.20 0.21 0.36 0.38 0.37
PP 0.22 0.05 0.06 0.16 0.06 0.04 0.06
DR 0.14 0.04 0.09 0.27 0.24 0.20 0.03
CO 0.46 0.07 0.12 0.13 0.06 0.25 0.10
Table 2. Category group pairwise comparison and group
relative weights
Category Comparison Relative
Importance
(Geo-mean)
Country Risk (Political & Regulatory) vs 0.90
Financial & Revenue Risks
Country Risk (Political & Regulatory) vs Promoting 1.61
& Procurement Risks
Country Risk (Political & Regulatory) vs 1.19
Development Risk
Country Risk (Political & Regulatory) vs 1.65
Construction & Operating Risk
Financial & Revenue Risks vs Promoting & 2.62
Procurement Risks
Financial & Revenue Risks vs Development Risk 1.94
Financial & Revenue Risks vs Construction & 2.19
Operating Risk
Promoting & Procurement Risks vs Development Risk 0.60
Promoting & Procurement Risks vs Construction & 0.56
Operating Risk
Development Risk vs Construction & Operating Risk 0.83
Category group weights Country Risk (Political 0.234
& Regulatory)
Financial & Revenue Risks 0.311
Promoting & Procurement Risks 0.114
Development Risk 0.170
Construction & Operating Risk 0.171
Table 3. Risk decision factors: local attributes weights
R1 R2 R3 R4 R5 R6 R7
Country Risk (Political & Regulatory)
GI 0.453 0.029 0.037 0.274 0.124 0.026 0.431
GFP 0.024 0.093 0.059 0.061 0.347 0.196 0.033
NLS 0.078 0.347 0.171 0.334 0.189 0.086 0.135
OH 0.116 0.03 0.193 0.028 0.224 0.102 0.153
CGL 0.262 0.244 0.159 0.281 0.07 0.187 0.194
LCCC 0.067 0.278 0.382 0.026 0.45 0.202 0.053
Financial & Revenue Risks
FRF 0.478 0.056 0.24 0.282 0.294 0.044 0.327
UGBE 0.092 0.386 0.206 0.256 0.037 0.073 0.186
FRRFP 0.115 0.3 0.084 0.184 0.302 0.077 0.164
CIDP 0.154 0.059 0.206 0.175 0.202 0.309 0.234
CIEP 0.08 0.099 0.152 0.026 0.12 0.32 0.047
EIFDS 0.086 0.1 0.111 0.078 0.045 0.177 0.041
Promoting & Procurement Risks
LOE 0.030 0.074 0.026 0.040 0.029 0.066 0.026
LE 0.099 0.162 0.041 0.202 0.083 0.039 0.040
LIM 0.113 0.200 0.078 0.112 0.119 0.127 0.057
CIPS 0.153 0.156 0.206 0.431 0.221 0.225 0.237
ELTP 0.117 0.210 0.367 0.094 0.313 0.306 0.226
LOI 0.487 0.197 0.281 0.121 0.235 0.237 0.414
Development Risks
EDC 0.046 0.06 0.08 0.333 0.076 0.09 0.065
DIDA 0.065 0.493 0.095 0.06 0.083 0.138 0.076
UOT 0.368 0.181 0.413 0.274 0.481 0.502 0.401
CIDDC 0.521 0.261 0.413 0.333 0.36 0.27 0.458
Construction & Operating Risk
COR 0.232 0.047 0.056 0.233 0.087 0.05 0.278
PRR 0.387 0.16 0.122 0.047 0.105 0.056 0.327
UOPS 0.033 0.08 0.058 0.152 0.315 0.176 0.032
EIO 0.209 0.117 0.243 0.03 0.168 0.116 0.157
UPO 0.061 0.11 0.37 0.208 0.144 0.287 0.062
IOM 0.078 0.485 0.15 0.33 0.181 0.307 0.144
R8 R9 R10 R11 R12 R13 R14
Country Risk (Political & Regulatory)
GI 0.042 0.484 0.027 0.1 0.152 0.056 0.096
GFP 0.059 0.056 0.088 0.378 0.056 0.107 0.057
NLS 0.096 0.216 0.416 0.162 0.431 0.134 0.039
OH 0.175 0.028 0.089 0.211 0.037 0.261 0.478
CGL 0.376 0.187 0.314 0.099 0.278 0.258 0.128
LCCC 0.252 0.03 0.066 0.049 0.048 0.184 0.202
Financial & Revenue Risks
FRF 0.041 0.196 0.186 0.28 0.307 0.452 0.564
UGBE 0.079 0.216 0.033 0.024 0.093 0.03 0.03
FRRFP 0.128 0.215 0.062 0.279 0.096 0.73 0.202
CIDP 0.902 0.15 0.1 0.217 0.43 0.248 0.044
CIEP 0.124 1.217 0.353 0.105 0.044 0.118 0.6
EIFDS 0.226 1.075 0.265 0.095 0.058 0.078 0.1
Promoting & Procurement Risks
LOE 0.058 0.028 0.050 0.196 0.084 0.025 0.113
LE 0.115 0.037 0.028 0.028 0.028 0.215 0.286
LIM 0.088 0.083 0.079 0.037 0.066 0.106 0.045
CIPS 0.168 0.135 0.216 0.097 0.078 0.115 0.284
ELTP 0.266 0.272 0.274 0.256 0.367 0.122 0.239
LOI 0.035 0.445 0.353 0.387 0.375 0.418 0.034
Development Risks
EDC 0.096 0.312 0.042 0.062 0.06 0.167 0.658
DIDA 0.169 0.045 0.581 0.057 0.064 0.193 0.083
UOT 0.368 0.378 0.218 0.44 0.497 0.047 0.048
CIDDC 0.368 0.266 0.159 0.442 0.379 0.593 0.212
Construction & Operating Risk
COR 0.066 0.084 0.042 0.074 0.087 0.112 0.109
PRR 0.088 0.089 0.069 0.105 0.192 0.204 0.028
UOPS 0.153 0.241 0.07 0.309 0.137 0.066 0.422
EIO 0.203 0.271 0.135 0.161 0.171 0.285 0.23
UPO 0.297 0.104 0.342 0.199 0.137 0.074 0.143
IOM 0.194 0.205 0.342 0.153 0.276 0.26 0.069
Note: GI = government instability; GFP = government failure to
provide permits; NLS = non-existence of the legal and
regulatory system; OH = outbreak of hostilities (wars, riots,
and terrorism); CGL = changes in general legislation affect the
project; LCCC = lack of commitment to concession contracts; FRF
= Failure to raise finance; UGBE = Undeveloped general business
environment; FRRFP = Failure to receive revenues from principal
(end user); CIDP = Changes in demand of the facility over
concession period; CIEP = Change in economic policies; EIFDS =
Error in forecasting demands for service; LOE = Lack of
experience; LE = Lack of expertise; LIM = Lack of independent
management; CIPS = Changes in project specifications; ELTP =
Expensive and long tendering process; LOI = Lack of integrity
on the tendering process; EDC = Excessive development cost;
DIDA = Delays in design approval; UOT = Use of technology;
CIDDC = Changes in design during construction; COR = Cost-
overrun risks; PRR = Performance related risk; UOPS =
Unavailability of power supply; EIO = Error in operation and
maintenance cost estimate; UPO = Unavailability and quality of
personnel to operate the facility; IOM = Inappropriate
operating methods.
Table 4. Group weights for comparison
of attributes within their categories
Attribute Group
Weight
Country Risk
(Political &
Regulatory)
Government 0.126
instability
Government failure 0.101
to provide permits
Non-existence of 0.242
the legal and
regulatory system
Outbreak of 0.142
hostilities (wars,
riots, and
terrorism)
Changes in general 0.261
legislation
affecting the
project
Lack of commitment 0.128
to concession
contracts
Financial & Revenue
Risks
Failure to raise 0.248
finance
Undeveloped general 0.103
business
environment
Failure to receive 0.165
revenues from
principal end user
Changes in demand 0.222
of the facility
over concession
period
Change in economic 0.130
policies
Error in 0.132
forecasting demands
for service
Promoting &
Procurement Risks
Lack of experience 0.056
Lack of expertise 0.079
Lack of independent 0.088
management
Changes in project 0.207
specifications
Expensive and long 0.264
tendering process
Lack of integrity 0.305
in the tendering
process
Development Risks
Excessive 0.113
development cost
Delays in design 0.115
approval
Use of technology 0.408
Changes in design 0.364
during construction
Construction &
Operating Risk
Cost-overrun risks 0.106
Performance related 0.130
risk
Unavailability of 0.150
power supply
Error in operation 0.184
and maintenance
cost estimate
Unavailability and 0.188
quality of
personnel to
operate the
facility
Inappropriate 0.242
operating methods
Table 5. Local composite weights of the attribute
towards the project risk (x 10E-2)
R1 R2 R3 R4 R5
Country Risk (Political & Regulatory)
GI 13.7 0.1 0.2 16.6 3.1
GFP 0.7 0.3 0.3 38 8.6
NLS 2.3 1.7 0.8 2.5 4.7
OH 3.5 0.2 0.9 1.7 5.6
CGL 7.9 1.2 0.7 17.2 1.7
LCCC 2 1.4 1.8 1.6 1.1
Financial & Revenue Risks
FRF 18.7 2.9 2.1 7.4 5
UGBE 3.6 19.8 1.8 6.7 0.6
FRRFP 4.3 15.4 0.8 4.8 0.51
CIDP 6 3 1.8 4.6 34
CIEP 3.1 5.1 1.4 0.7 2
EIFDS 3.4 5.1 1 2 0.8
Promoting & Procurement Risks
LOE 0.2 1.3 0.3 0.2 0.5
LE 0.7 2.8 0.5 0.8 1.5
LIM 0.8 3.5 0.9 0.5 2.1
CIPS 1 2.7 2.4 1.8 3.9
ELTP 0.8 3.7 4.2 0.4 5.5
LOI 3.3 3.5 3.2 0.5 4.1
Development Risks
EDC 0.8 1 2.6 1.4 2.2
DIDA 1.2 7.6 3 0.2 2.4
UOT 6.7 2.8 13.2 1.1 0.13
CIDDC 9.5 4 13.2 1.4 10.4
Construction & Operating Risk
COR 1.3 0.5 2.4 1 1
PRR 2.2 1.7 5.3 0.2 1.2
UOPS 0.2 0.9 2.5 0.7 3.7
EIO 1.2 1.3 10.4 0.1 2
UPO 0.3 1.2 15.9 0.9 1.7
IOM 0.4 5.5 6.5 1.4 2.1
R6 R7 R8 R9 R10
Country Risk (Political & Regulatory)
GI 0.2 7.5 0.2 2.64 1.4
GFP 1.2 0.6 0.3 3.1 4.7
NLS 1.7 2.3 0.6 11.8 22.1
OH 0.6 2.7 1 1.5 4.7
CGL 1.1 3.4 0.2 10.3 16.7
LCCC 1.2 0.9 1.5 1.7 3.5
Financial & Revenue Risks
FRF 0.4 14.9 0.5 4.3 3.8
UGBE 0.7 8.5 1 6.3 0.7
FRRFP 0.7 7.5 1.5 6.3 1.3
CIDP 2.8 10.7 4.8 4.4 2
CIEP 2.9 2.1 1.5 6.4 7.2
EIFDS 1.6 1.9 2.7 1.7 4.5
Promoting & Procurement Risks
LOE 1.3 0.3 1.3 0.1 0.3
LE 0.7 0.5 2.5 2 0.2
LIM 2.4 0.7 1.9 0.4 0.4
CIPS 43 3.1 3.7 0.7 1.2
ELTP 5.9 3 5.8 1.4 1.5
LOI 4.6 5.5 6.7 2.2 2
Development Risks
EDC 2.5 0.6 1.3 1.3 0.4
DIDA 3.8 0.7 2.4 0.2 5.3
UOT 13.7 3.5 5.1 1.6 2
CIDDC 7.4 4 5.1 1.1 1.4
Construction & Operating Risk
COR 1.9 4.2 3 0.6 0.5
PRR 2.5 5 4.1 0.6 0.8
UOPS 6.7 0.5 7.1 1.6 0.8
EIO 4.5 2.4 9.4 1.8 1.6
UPO 11 0.9 13.7 0.7 4.1
IOM 11.7 2.2 9 1.4 4.1
R11 R12 R13 R14
Country Risk (Political & Regulatory)
GI 2.4 0.43 0.7 4.2
GFP 9.2 1.6 1.4 2.5
NLS 3.9 11.2 1.8 1.7
OH 5.1 1 3.5 21.1
CGL 2.4 7.9 3.4 5.7
LCCC 1.2 1.3 2.5 8.9
Financial & Revenue Risks
FRF 5.8 11 17.2 20.7
UGBE 0.5 3.3 1.1 1.1
FRRFP 5.8 2.5 2.8 7.4
CIDP 4.5 15.4 9.5 1.6
CIEP 2.2 1.6 4.5 2.2
EIFDS 2 2.1 3 3.7
Promoting & Procurement Risks
LOE 3 0.5 0.1 0.6
LE 4 0.2 0.8 1.6
LIM 0.6 0.4 0.4 0.2
CIPS 1.5 0.5 0.4 1.6
ELTP 4 0.2 0.34 1.3
LOI 6 2.2 1.5 0.2
Development Risks
EDC 1.7 1.4 3.3 2.3
DIDA 1.5 1.5 3.8 0.3
UOT 11.19 11.9 0.9 0.2
CIDDC 11.9 9 11.6 0.7
Construction & Operating Risk
COR 0.9 0.5 2.8 1.1
PRR 1.3 1.2 5.2 0.3
UOPS 3.9 0.8 1.7 4.3
EIO 2 1 7.2 2.3
UPO 2.5 0.8 1.9 1.5
IOM 1.9 1.7 6.6 0.7
Table 6. Attribute group composite weight
Attribute Group
Composite
Weight
(x 10E-2)
Country Risk (Political & Regulatory)
Government instability 2.90
Government failure to provide permits 2.40
Non-existence of the legal and regulatory system 5.70
Outbreak of hostilities (wars, riots, and terrorism) 3.30
Changes in general legislation affecting the project 6.10
Lack of commitment to concession contracts 3.00
Financial & Revenue Risks
Failure to raise finance 7.70
Undeveloped general business environment 3.20
Failure to receive revenues from principal (end user) 5.l0
Changes in demand for the facility over the 6.90
concession period
Change in economic policies 4.00
Error in forecasting demands for service 4.10
Promoting & Procurement Risks
Lack of experience 0.60
Lack of expertise 0.90
Lack of independent management 1.00
Changes in project specifications 2.40
Expensive and long tendering process 3.00
Lack of integrity in the (tendering process) 3.50
Development Risks
Excessive development cost 1.90
Delays in design approval 2.0
Use of technology 6.90
Changes in design during construction 6.20
Construction & Operating Risk
Cost-overrun risks 1.80
Performance related risk 2.20
Unavailability of power supply 2.60
Error in operation and maintenance cost estimate 3.10
Unavailability and quality of personnel to operate 3.20
the facility
Inappropriate operating methods 4.10
Table 7. Local composite weights of the attribute
towards the project risk (x 10E-2)
R1 R2 R3 R4 R5
Country Risk (Political & Regulatory)
GI 13.7 0.1 0.2 16.6 3.1
GFP 0.7 0.3 0.3 38 8.6
NLS 2.3 1.7 0.8 2.5 4.7
OH 3.5 0.2 0.9 1.7 5.6
CGL 7.9 1.2 0.7 17.2 1.7
LCCC 2 1.4 1.8 1.6 1.1
Financial & Revenue Risks
FRF 18.7 2.9 2.1 7.4 5
UGBE 3.6 19.8 1.8 6.7 0.6
FRRFP 4.3 15.4 0.8 4.8 0.51
CIDP 6 3 1.8 4.6 34
CIEP 3.1 5.1 1.4 0.7 2
EIFDS 3.4 5.1 1 2 0.8
Promoting & Procurement Risks
LOE 0.2 1.3 0.3 0.2 0.5
LE 0.7 2.8 0.5 0.8 1.5
LIM 0.8 3.5 0.9 0.5 2.1
CIPS 1 2.7 2.4 1.8 3.9
ELTP 0.8 3.7 4.2 0.4 5.5
LOI 3.3 3.5 3.2 0.5 4.1
Development Risks
EDC 0.8 1 2.6 1.4 2.2
DIDA 1.2 7.6 3 0.2 2.4
UOT 6.7 2.8 13.2 1.1 0.139
CIDDC 9.5 4 13.2 1.4 10.4
Construction & Operating Risk
COR 1.3 0.5 2.4 1 1
PRR 2.2 1.7 5.3 0.2 1.2
UOPS 0.2 0.9 2.5 0.7 3.7
EIO 1.2 1.3 10.4 0.1 2
UPO 0.3 1.2 15.9 0.9 1.7
IOM 0.4 5.5 6.5 1.4 2.1
R6 R7 R8 R9 R10
Country Risk (Political & Regulatory)
GI 0.2 7.5 0.2 2.64 1.4
GFP 1.2 0.6 0.3 3.1 4.7
NLS 1.7 2.3 0.6 11.8 22.1
OH 0.6 2.7 1 1.5 4.7
CGL 1.1 3.4 0.2 10.3 16.7
LCCC 1.2 0.9 1.5 1.7 3.5
Financial & Revenue Risks
FRF 0.4 14.9 0.5 4.3 3.8
UGBE 0.7 8.5 1 6.3 0.7
FRRFP 0.7 7.5 1.5 6.3 1.3
CIDP 2.8 10.7 4.8 4.4 2
CIEP 2.9 2.1 1.5 6.4 7.2
EIFDS 1.6 1.9 2.7 1.7 4.5
Promoting & Procurement Risks
LOE 1.3 0.3 1.3 0.1 0.3
LE 0.7 0.5 2.5 2 0.2
LIM 2.4 0.7 1.9 0.4 0.4
CIPS 43 3.1 3.7 0.7 1.2
ELTP 5.9 3 5.8 1.4 1.5
LOI 4.6 5.5 6.7 2.2 2
Development Risks
EDC 2.5 0.6 1.3 1.3 0.4
DIDA 3.8 0.7 2.4 0.2 5.3
UOT 13.7 3.5 5.1 1.6 2
CIDDC 7.4 4 5.1 1.1 1.4
Construction & Operating Risk
COR 1.9 4.2 3 0.6 0.5
PRR 2.5 5 4.1 0.6 0.8
UOPS 6.7 0.5 7.1 1.6 0.8
EIO 4.5 2.4 9.4 1.8 1.6
UPO 11 0.9 13.7 0.7 4.1
IOM 11.7 2.2 9 1.4 4.1
R11 R12 R13 R14
Country Risk (Political & Regulatory)
GI 2.4 0.43 0.7 4.2
GFP 9.2 1.6 1.4 2.5
NLS 3.9 11.2 1.8 1.7
OH 5.1 1 3.5 21.1
CGL 2.4 7.9 3.4 5.7
LCCC 1.2 1.3 2.5 8.9
Financial & Revenue Risks
FRF 5.8 11 17.2 20.7
UGBE 0.5 3.3 1.1 1.1
FRRFP 5.8 2.5 2.8 7.4
CIDP 4.5 15.4 9.5 1.6
CIEP 2.2 1.6 4.5 2.2
EIFDS 2 2.1 3 3.7
Promoting & Procurement Risks
LOE 3 0.5 0.1 0.6
LE 4 0.2 0.8 1.6
LIM 0.6 0.4 0.4 0.2
CIPS 1.5 0.5 0.4 1.6
ELTP 4 0.2 0.34 1.3
LOI 6 2.2 1.5 0.2
Development Risks
EDC 1.7 1.4 3.3 2.3
DIDA 1.5 1.5 3.8 0.3
UOT 11.19 11.9 0.9 0.2
CIDDC 11.9 9 11.6 0.7
Construction & Operating Risk
COR 0.9 0.5 2.8 1.1
PRR 1.3 1.2 5.2 0.3
UOPS 3.9 0.8 1.7 4.3
EIO 2 1 7.2 2.3
UPO 2.5 0.8 1.9 1.5
IOM 1.9 1.7 6.6 0.7
Table 8. Risk index value for the Sulaibiya Wastewater
Treatment plant project in Kuwait
Risk Attribute P2 = 100
Value Index
Government instability GI 2.03
Government failure to GFP 1.85
provide permits
Non-existence of the NLS 2.46
legal and regulatory
system
Outbreak of hostilities OH 1.93
(wars, riots, and
terrorism)
Changes in general CGL 2.20
legislation affecting
the project
Lack of commitment to LCCC 1.85
concession contracts
Failure to raise finance FRF 1.87
Undeveloped general UGBE 2.01
business environment
Failure to receive FRRFP 2.50
revenues from principal
(end user)
Changes in demand for CIDP 1.41
the facility over
concession period
Change in economic CIEP 2.49
policies
Error in forecasting EIFDS 2.50
demands for service
Lack of experience LOE 2.48
Lack of expertise LE 2.43
Lack of independent LIM 2.10
management
Changes in project CIPS 2.52
specifications
Expensive and long ELTP 1.96
tendering process
Lack of integrity in LOI 1.65
the (tendering process)
Excessive EDC 2.52
development costs
Delays in DIDA 2.46
design approval
Use of technology UOT 3.30
Changes in design CIDDC 2.06
during construction
Cost-overrun risks COR 1.96
Performance PRR 2.95
related risk
Unavailability of UOPS 2.06
power supply
Error in operation EIO 2.11
and maintenance
cost estimate
Unavailability and UPO 2.98
quality of personnel
to operate the facility
Inappropriate IOM 3.00
operating methods
Fig. 6. Risk index value for the Sulaibiya
Wastewater Treatment Plant project in Kuwait
IOM 3
UPO 2,98
EIO 2,11
UOPS 2,06
PRR 2,95
COR 1,96
CIDDC 2,06
UOT 3,3
DIDA 2,46
EDC 2,52
LOI 1,65
ELTIP 1,96
CIPS 2,52
LIM 2,1
LE 2,43
LOE 2,48
EIFDS 2,5
CIEP 2,49
CIDP 1,14
FRRFP 2,5
UGBE 2,01
FRF 1,87
LCCC 1,85
CGL 2,2
OH 1,93
NLS 2,46
GFP 1,85
GI 2,03
Note: Table made from bar graph