Factors affecting labour productivity in building projects in the Gaza Strip/Veiksniai, lemiantys darbo jegos produktyvuma statybos projektuose Gazos ruoze.
Enshassi, Adnan ; Mohamed, Sherif ; Mustafa, Ziad Abu 等
Abstract. Productivity remains an intriguing subject and a dominant
issue in the construction sector, promising cost savings and efficient
usage of resources. Productivity is one of the most important issues in
both developed and developing countries. The developed countries are
aware of the importance of economic growth and social welfare. The
developing countries which face unemployment problems, inflation and
resource scarcity seek to utilise resources and in such a way to achieve
economic growth and improve citizens' lives. Productivity is an
issue of particular importance to projects located within the Gaza
Strip, as it is considered a newly-developed area, and a huge number of
projects have been planned for the near future. The aim of this research
is to identify factors affecting labour productivity within building
projects, and to rank these factors according to their relative
importance from a contractor's viewpoint. The analysis of 45
factors considered in a survey indicates that the main factors
negatively affecting labour productivity are: material shortage, lack of
labour experience, lack of labour surveillance, misunderstandings
between labour and superintendent, and drawings and specification
alteration during execution.
Keywords: productivity, labour, building projects, improvement.
Santrauka
Produktyvumas vis dar islieka viena is labiausiai dominaneiu ir
svarstomu statybos sektoriaus klausimu. Tai lemia sanaudu ir islaidu
taupyma, efektyvu istekliu naudojima. Produktyvumas yra vienas is
svarbiausiu tiek issivyseiusiu, tiek besivystaneiu saliu klausimu.
Besivystaneios salys, kurios susiduria su nedarbo problemomis,
infliacija ir istekliu stoka, siekia panaudoti turimus isteklius taip,
kad butu pasiektas ekonomikos augimas ir geretu pilieeiu gyvenimas.
Produktyvumas yra viena is problemu, turineiu itin daug reiksmes
projektuose, vykdomuose Gazos ruoze, kadangi ji yra laikoma naujai
susiformavusia zona, kurioje artimoje ateityje numatyta vykdyti daug
projektu. Sio tyrimo tikslas yra nustatyti veiksnius, veikianeius darbo
jegos produktyvuma statybos projektuose ir suskirstyti juos pagal
salygiska svarba rangovo poziuriu. Remiantis apklausa, buvo atlikta 45
veiksniu analize, kurioje buvo isskirti pagrindiniai veiksniai, darantys
neigiama poveiki darbo jegos produktyvumui: tai medziagu, patirties,
kontroles trukumas, darbuotoju ir darbu vykdytoju santykiai, breziniu
bei specifikaciju kitimas vykdant darbus.
Reiksminiai zodziai: produktyvumas, darbo jega, statybos projektai,
gerinimas.
1. Introduction
There is no doubt that construction is a key activity within any
economy; it influences, and is influenced by, the nation's gross
domestic product (GDP) (Cox et al, 1998, cited in Madi, 2003). Given the
uncertainties, management is to deal with, the construction industry is
a risky one. While these risks may be derived from either external or
internal factors, external factors have a greater influence on
construction industry than the internal ones (Zhi, 1995).
The construction sector in Palestine experienced a considerable
growth in the aftermath of 1967; its share of GDP increased from less
than 9 % in 1985 to more than 23 % in 1995. During that period the
sector's contribution fluctuated in an upward long-run trend
bounded by 9 % and 19 % from 1970 to 1980, and by 15,2 % and 23 % from
1989 to 1995 (PECDAR, 1997). However, it appears that in 2004 the
construction sector's contribution to the GDP was reduced to 9 %
due to the second Intifada in Palestine (World Bank, 2004; PCBS, 2004).
Due to increased demand from the first Intifada, and to accommodate
Palestinian returnees from the Gulf following the first Gulf War, the
construction sector experienced a steady increase from 1991 onwards. The
1994 peace process accelerated this increase, particularly after the
return of many Palestinians with the Palestinian National Authority (MAS, 2001). Expansion of construction activities has generated numerous
jobs for skilled, semi-skilled, and unskilled labour. Fig 1 shows the
distribution of the labour force within the construction sector from
1997 to 2001 (PASSIA, 2002). Building construction is one of the pioneer
sectors that achieved high growth rates during the last two decades, and
played a crucial role in absorbing gradual injections into the
Palestinian labour force (PCBS, 2004).
2. Productivity background
Improving productivity is a major concern for any profit-oriented
organisation, as representing the effective and efficient conversion of
resources into marketable products and determining business
profitability (Wilcox et al, 2000). Consequently, considerable effort
has been directed to understanding the productivity concept, with the
different approaches taken by researchers resulting in a wide variety of
definitions of productivity (Lema, 1995; Pilcher, 1997; Oglesby, 2002).
Productivity has been generally defined as the ratio of outputs to
inputs.
Construction projects are mostly labour-based with basic hand tools
and equipment, as labour costs comprise 30 to 50 % of overall projects
costs (Guhathakurta and Yates, 1993). Therefore, while numerous
construction labour productivity research studies have been undertaken,
only a few have addressed the productivity issue in developing
countries. Lema (1995) observed that labour productivity data were not
available from Tanzanian construction established on the basis of actual
site observations. Accordingly, on the basis of limited data, it was
concluded that labour utilisation on construction sites was less than 30
% in Tanzania.
Olomolaiye et al (1998) briefly studied labour productivity on
construction sites in Nigeria. Their study concluded that there was a
need for establishing output figures on various construction sites
through time study techniques. It was concluded that method studies and
research results should be disseminated not only to large firms but also
to small firms so the most productive working methods (or best
practices) could be adopted by operatives, resulting in increased output
without necessarily increasing physical efforts.
Lim et al (1995) studied factors affecting productivity in the
construction industry in Singapore. Their findings indicated that the
most important problems affecting productivity were: difficulty with
recruitment of supervisors; difficulty with recruitment of workers; high
rate of labour turnover; absenteeism from the work site; and
communication problems with foreign workers. Olomolaiye et al (1996)
studied factors affecting productivity of craftsmen in Indonesia, with
their findings indicating craftsmen in Indonesia spent 75 % of their
time working productively. Five specific productivity problems were
identified: ie lack of materials; rework; absenteeism; lack of
equipment; and tools.
3. Factors affecting construction productivity
The factors influencing construction productivity have been the
subject of inquiry by many researchers. In order to improve
productivity, a study of the factors affecting it, whether positively or
negatively, is necessary. Making use of those factors that positively
affect productivity and eliminating (or controlling) factors that have a
negative effect, will ultimately improve productivity. If all factors
influencing productivity are known, it will also be possible to forecast
productivity (Lema, 1995). Several researchers have investigated the
factors influencing labour productivity (United Nations, 1965; Thomas et
al, 1991; Lim et al, 1995; Lema, 1995; Olomolaiye et al, 1996; Heizer
and Render, 1996; Olomolaiye et al, 1998; Kaming et al, 1998; Teicholz,
2001; Thomas and Sanders, 1991; Wachira, 1999; Rojas and Aramvareekul,
2003). Despite such intensive investigations, researchers have not
agreed on a universal set of factors with significant influence on
productivity; or any agreement has been reached on the classification of
these factors.
Several approaches have been adopted in relation to the
classification of factors affecting construction productivity. A United
Nations report (1995) stated that in ordinary situations two major sets
of factors affect the site labour productivity requirements:
organisational continuity and execution continuity. Organisational
continuity encompasses physical components of work, specification
requirements, design details etc. Execution continuity relates to the
work environment and how effectively a job is organised and managed.
Management aspects include weather, material and equipment availability,
congestion, and out-of-sequence work.
Kane et al (cited in Herbsman et al, 1990) classified factors
affecting construction productivity into two main groups: technological
factors and administrative factors. The technological factors encompass
those related mostly to the design of the project; the administrative
group factors relate to the management and construction of the project.
Technological factors comprise sub-groups such as design factors,
material factors and location factors. Administrative factors comprise
sub-groups, such as construction methods and procedural factors,
equipment factors, labour factors, and social factors.
Heizer and Render (1990) classified factors influencing site
productivity into 3 groups: labour characteristic factors; project work
conditions factors; and nonproductive activities. Olomolaiye et al
(1998) stated that factors affecting construction productivity are
rarely constant, and may vary from country to country, from project to
project, and even within the same project, depending on circumstances.
They classified factors influencing construction productivity into 2
categories: external and internal, representing those outside the
control of the firm's management, and those originating within the
firm. External factors included the nature of the industry, construction
client knowledge of construction procedure, weather, and level of
economic development. Internal factors included management, technology,
labour, and labour unions. Enshassi et al 2006, Enshassi et al 2007, and
Al Haddad 2007 stated that among the problems which the Palestinian
construction industry is facing are material supply schedules and
project scheduling techniques. Although a number of training courses
were conducted to local contractors, these training efforts did not
focus enough on the abilities to use project scheduling techniques such
as Microsoft project and Primavera. Therefore training effort should
also be tailored to improve methods of studying productivity and ways of
productivity improvement on construction sites.
4. Research method
This research is based on a survey designed to gather all necessary
information in an effective way. The survey presents 45 productivity
factors generated on the basis of related research work on construction
productivity (Thomas and Sanders, 1991; Guhathakurtal and Yates, 1993;
Lim and Alum, 1995; Lema, 1995; Olomolaiye et al, 1996; Heizer and
Render, 1996; Olomolaiye et al, 1998; Kaming, et al, 1998; Teicholz,
2001; Wachira, 1999; Rojas and Aramvareekul, 2003), together with input,
revision and modifications by local experts. These factors were divided
into 10 groups based on previous literature and as advised by local
experts: manpower, leadership, motivation, time, materials/tools,
supervision, project, safety, quality, and external factors.
The studied target population includes contractors who hold valid
registration from the contractors union in building specialisation
within the Gaza Strip. The total number of contractors who have valid
registration under the first, second and third categories are
represented by 105 companies. The main criteria for classification are
related to the company's previous experience; capital; the value of
executed projects, staffing, and financial situation during the last 10
years. The first class comprises 41 firms, the second class 47 firms,
and the third class 17 firms. A systematic random sample was selected to
ensure a representative sample of all contractors, using the following
formula (Hogg and Tannis, 1997):
m = [Z.sup.2] x [P.sup.*] x (1 - [P.sup.*]); / [[epsilon].sup.2]
n = m/(1 + m-1)/N,
where: m--sample size of unlimited population; n--sample size of
limited population; Z--value (eg 1,96 for 95 % confidence level);
[P.sup.*]--degree of variance between the elements of population (0,5);
[epsilon]--maximum error of the point estimate,
m = [(1,96).sup.2] x 0.5 x (1-0,5)/[(0.05).sup.2] = 384,16 = 385:
n = 385/(1 + 385-1/105) = 82,67 = 83.
A total of 83 contracting companies within the Gaza Strip were
surveyed; 33 first-class contractors, 37 second-class contractors, and
13 third-class contractors. The overall response to the survey comprised
a total of 76 completed questionnaires, representing approx 91 %
response rate. This result has been achieved by continuous following-up
and close personal contact with contractors. The respondents are
recognised experts from their respective organisations (mostly directors
and general managers) with at least 10 years' construction
experience. The sample was selected randomly from each level of the
three contractor's categories. The contractor's union list is
ordered by the company number, and 3 lists of contractors were prepared
to present the first, second and third categories. The random selection
among the three lists was done by using non-replacement random
selection.
An ordinal measurement scale, which is a ranking of rating data
that normally use integers in ascending or descending order, was used in
this study. The numbers assigned to the agreement scale (5, 4, 3, 2, 1)
do not indicate that the intervals between the scales are equal, nor do
they indicate absolute quantities (Naoum, 1998). The respondents were
asked to rank the factors affecting labour productivity according to the
degree of importance (1--affects with little degree; 2--affects
something; 3--affects with average degree; 4--affects with large degree;
5--affects with very large degree). For analysing data by ordinal scale,
an importance index (I) was used. This index was computed by the
following equation (Lim et al, 1995):
Importance index = 5n5 + 4n4 + 3n3 + 2n2 + n1/5(n1 + n2 + n3 + n4 +
n5) * 100,
where: n1--number of respondents who answered "little
effect"; n2--number of respondents who answered "some
effect"; n3--number of respondents who answered "average
effect"; n4--number of respondents who answered "high
effect"; n5--number of respondents who answered "very high
effect".
The importance index (I) for all factors was calculated. The group
index was calculated by taking the average of factors in each group.
5. Results and discussion
In this study, 45 factors negatively affecting labour productivity
in building construction of the Gaza Strip have been identified and
ranked according to their relative importance. These factors have been
classified into 10 groups: manpower, leadership, motivation, time,
materials/ tools, supervision, project, safety, quality, and external
factors.
Manpower group
Table 1 illustrates the ranking of the 8 factors in the group
related to manpower. The results show that the most important factor
negatively affecting the productivity is lack of labour experience,
followed by labour disloyalty, labour dissatisfaction, misunderstanding
among labour, lack of competition, increase in labourer age, labour
absenteeism, and labour personal problems.
The surveyed contractors ranked 'lack of labour experience it
the first position, with an importance index value of 84,21. This factor
was also ranked it the second position among all 45 factors, negatively
affecting labour productivity (Table 11), which indicates that lack of
labour experience has a very high effect on productivity. This result is
supported by Paulson (1975), who found that experience of the craftsmen
affects labour productivity. This result is also supported by Heizer and
Render (1990), who confirmed that experience of workforce affects job
site productivity. This result is justified, as experience improves both
the intellectual and physical abilities of labour which consequently
increase labour productivity. 'Labour disloyalty' had a high
effect on labour productivity, and was ranked in the second position in
the manpower group, with an importance index of 78,55. 'Labour
disloyalty' also ranked seventh among all 45 factors negatively
affecting labour productivity (Table 11).
Furthermore, results indicated that 'misunderstanding among
labour' has an average effect on labour productivity, as this
factor was ranked 17 among all factors negatively affecting labour
productivity. This result is justified, as misunderstanding among labour
creates disagreement among labour about responsibilities and work bounds
of each labourer, which leads to a lot of mistakes in work, and
consequently decreases labour productivity.
Findings also show that contractors' respondents rated
'lack of competition' as having an average effect on labour
productivity; this factor ranked at position 25 of all 45 factors
negatively affecting productivity. Findings also show respondents rated
'increase of labourer age' as having an average effect on
labour productivity, with this factor being ranked at number 30 of all
factors negatively affecting labour productivity (Table 11). Heizer and
Render (1990) support this result, citing that the age of the workforce
affects job site productivity. This result is justified, as labour
speed, agility, and strength decline over time and contributes to a
reduced productivity.
'Labour absenteeism' in particular had a low effect on
labour productivity, ranking at position 41 of all factors negatively
affecting productivity. This result might be justified, given the
transient nature of the local workforce and the ease with which
construction contractors could hire additional labour to cover
absenteeism. Personal problems are not considered to be as instrumental
as other factors, and ranked in position 42 of all factors negatively
affecting labour productivity. This result might be justified, as
personal problems cause only mental distraction for labour, and mental
distraction affects labour safety more than labour productivity.
Leadership group
The results in Table 2 illustrate the ranking of the 3 factors
under leadership group. Lack of labour surveillance was ranked first;
misunderstanding between labour and superintendents was ranked second;
and lack of periodic meeting with labour was ranked third. Lack of
labour surveillance has a high effect on labour productivity (imp. index
= 83,42), and ranked in position 3 of all 45 factors negatively
affecting labour productivity (Table 11). This result is justified, as
lack of labour surveillance increases labour mistakes at work, as well
as delaying corrective action for these mistakes.
Misunderstanding between labour and superintendents has a high
effect on labour productivity (imp. index = 80,26), and ranked in
position 4 of all factors negatively affecting labour productivity. This
result is justified, as misunderstanding between labour and
superintendents creates bad relations between them. Such
misunderstandings have adverse effects on labour mood, and consequently
decrease productivity. Finally, lack of periodic meetings with labour is
not considered to be as instrumental as other factors on labour
productivity, and ranked in position 38 of all factors negatively
affecting labour productivity. This result might be justified, because
building projects within the Gaza Strip are small and problems facing
work can be discussed at any time with superintendents; therefore there
is no need for periodic meetings with labour to discuss these problems.
Motivation group
Table 3 indicates the ranking of 6 factors under the group related
to motivation. These factors were placed in descending order according
to their importance: payment delay, lack of financial motivation system,
lack of labour recognition programs, non-provision of transportation
means, lack of places for eating and relaxation, and lack of training
sessions. Results demonstrate that payment delay has a high effect on
labour productivity (imp. index = 78,68), and ranked in position 6 of
all 45 factors negatively affecting labour productivity. This result is
justified, as payment delay has a very bad effect on labour mood, and
consequently decreases its productivity. Contractors believed that lack
of financial motivation system has greater negative impact on labour
productivity than the lack of labour recognition programs, and ranked
'lack of financial motivation system' in position 21, while
'lack of labour recognition programs' was ranked in position
32 of all factors negatively affecting productivity. Motivation is
essential to labour, as it gives site workers satisfaction such as
achievement, sense of responsibility and pleasure of the work itself.
Non-provision of transport means and places for eating and
relaxation is not considered to be as instrumental as other factors on
labour productivity, and ranked in positions 39 and 40 respectively
among all factors negatively affecting productivity. This result is not
supported by Lema (1995), who mentioned that non-financial benefits such
as transport, meals, and uniforms have a high effect on labour
productivity. These results might be justified within the Gaza Strip
because its small area means transportation to any place within the Gaza
Strip can be made available easily; therefore there is no need to
provide transport to labour. Additionally, Palestinian labour is not
sensitive to their place of eating; according to their culture, any
place can be used for eating, so there is no need to provide a special
place for eating and relaxation. Furthermore, findings illustrate that a
lack of training sessions is not considered to be as instrumental as
other factors on labour productivity, and was ranked 44 of all negative
factors. Surveyed contractors illustrate there is no need for training
sessions, and labour can be trained more effectively on site by working
closely with experienced workers.
Time group
Table 4 shows the 5 factors in the group related to time; these
were ranked according to their importance in affecting labour
productivity as follows: working for 7 days per week without holiday was
ranked first; misuse of time schedule was ranked second; method of
employment (using direct work system) was ranked third; increasing
workforce to accelerate work was ranked fourth; and work overtime was
ranked fifth.
Working 7 days per week without holiday has a high effect on labour
productivity, while working additional hours during the working day has
an average effect. Hinze (1999) supported these results, stating that
working additional days and hours has a negative impact on labour
productivity. These results are not surprising, because working
additional days and hours creates an adverse effect on the motivation
and physical strength of labour, thus decreasing their productivity.
However, the impact of working additional hours for a short period may
be not noticeable, or non-existent.
Results also demonstrate that 'misuse of time schedule'
has a high negative impact on labour productivity. This result is
acceptable, as good use of time schedule leads to many advantages such
as continuous flow of work; reduced volume of rework; minimisation of
confusion and misunderstanding. Using a daily work system instead of a
unit rate system has an average negative effect on labour productivity,
and ranked in position 31 of all 45 factors negatively affecting labour
productivity (Table 11). This result is justified, as the labour desire
to work by unit rate system to earn more money. Therefore labour works
too hard to finish the greatest volume of work when working by the unit
rate system.
Increasing the workforce on the construction site has a moderate
effect on labour productivity, and is ranked in position 28 of all
factors negatively affecting labour productivity. This result was also
supported by Hinze (1999), who mentioned that increasing the workforce
on a construction site has an adverse impact on labour productivity.
This result is justified, as increasing the workforce on a construction
site causes overcrowding of labour and interference between labour and
gangs, which consequently reduces labour productivity.
Materials/tools group
The results in Table 5 demonstrate 3 factors in the materials/tools
group; these were ranked according to their importance in effecting
labour productivity as follows: material shortages; tool and equipment
shortages; and unsuitability of materials storage location. These
findings show that a material shortage is the most important of all
factors negatively affecting labour productivity. Material shortage was
ranked in the first position of all 45 factors negatively affecting
labour productivity, which is understandable, as work cannot be
accomplished without necessary materials. Material shortages rated in
the first position among factors affecting labour productivity in the
US, UK, Indonesia, Nigeria, Singapore, and Kenya (Guhathakurta and
Yates, 1993; Lim and Alum, 1995; Olomolaiye et al, 1996). This result is
justified in the Gaza Strip, as most materials used in construction
projects are imported from Israel; therefore any closure of crossing
points between the Gaza Strip and Israel stop work on all construction
projects.
Results also show that tool and equipment shortages have a high
effect on labour productivity, and ranked in position 10 of all factors
negatively affecting labour productivity. Tool and equipment shortages
also have a high effect in the US, UK, Indonesia, and Nigeria
(Guhathakurta et al, 1993; Olomolaiye et al, 1996). This result might be
justified, as labour needs a minimum number of tools and equipment to
work effectively. If there is lack of equipment and/or tools,
productivity will decrease. Results also illustrate that unsuitability
of materials storage location has an average effect on labour
productivity, and is ranked in position 20 of all factors negatively
affecting labour productivity. This result was supported by Thomas and
Sanders (1991), who stated that size and organisation of materials
storage location have a significant impact on masonry productivity. This
result is justified as labour needs more time to fetch required
materials from unsuitable storage locations, which negatively affects
productivity.
Supervision group
All supervision factors have a high impact on productivity, and
were ranked according to their importance as follows: drawings and
specifications alteration during execution; inspection delay; rework;
and supervisors' absenteeism (Table 6). Drawings and specification
alteration during execution is the most important factor in supervision
factors group, and is ranked within the 10 most important factors
negatively affecting productivity, with an importance index value of 80.
This result is supported by Thomas (1999), who stated there is a 30 %
loss of efficiency when work changes are being performed. This result
can be interpreted as changes of specifications and drawings that
require additional time for adjustments of resources and manpower so the
change can be met. Labour morale is also affected by extensive numbers
of changes.
Inspection delay is the second important factor in supervision
factors group, and is also ranked within the 10 most important factors
negatively affecting productivity. Inspection delay also has a high
impact in the US, UK, Nigeria, and Indonesia (Guhathakurta et al,
1993--Olomolaiye et al, 1996). This result is justified, as work
inspection by a supervisor is an essential process to proceed in work;
for example, as contractors cannot cast concrete before inspection of
formwork and steel work, inspection delay contributes to delays in work
activities.
Supervisors' absenteeism, the last factor in the supervision
factors group, is ranked in position 15 of all factors negatively
affecting labour productivity. This is not surprising in Gaza Strip
projects, as absenteeism of supervisors stops work totally in activities
that require attendance of supervisors, such as casting concrete and
backfilling. Additionally, supervisors' absenteeism delays
inspection of ready work, which, in turn, leads to delay in the
commencement of new work.
Project group
The most important factor in this group was working within a
confined space, followed by interference; construction method; and type
of activities in project (Table 7). Working within a confined space was
ranked in position 19 of 45 factors negatively affecting labour
productivity. This result is supported by Thomas and Sanders (1991), in
which it was reported that one of the common reasons for low
productivity is working within a confined space. This result might be
justified, as confined spaces reduce free movement of labour, and
consequently reduce their productivity.
Interference has an average impact on labour productivity, and was
ranked in position 24 of all factors. Interference also has a
significant impact on labour productivity in the US, UK, Nigeria, and
Indonesia (Guhathakurta and Yates, 1993; Olomolaiye et al, 1996).
Interference between gangs and workers is caused by mismanagement on
construction sites, with steel fixers suffering more of this, possibly
because they are more dependent on other trades. For example, if the
carpenters have not completed the formworks, steel fixers will have to
wait before fixing the reinforcement rods.
Results also indicate that the construction method and type of
activities in the project are not considered to be as instrumental as
other factors, and were ranked in positions 32 and 34 of all 45 factors
negatively affecting labour productivity. This result is not supported
by Thomas and Sanders (1991), who found that construction method and
project features have a high impact on labour productivity. This result
might be justified, because building projects within the Gaza Strip are
not complex and are small in size. Therefore activities in different
projects largely have the same features, and there is no major
difference between methods used in construction.
Safety group
The result in Table 8 depicts that the 7 factors under the safety
group have been placed in descending order as follows: accidents,
violation of safety precautions, insufficient lighting, bad ventilation,
working at high places, unemployment of safety officer on the
construction site, and noise.
Accidents have a high impact on labour productivity, and ranked in
position 13 of 45 factors negatively affecting labour productivity.
These results were supported by Thomas and Sanders (1991), who stated
that accidents have a significant impact on labour productivity. There
are 3 types of accidents:
* Accidents resulting in the death of an injured worker; this type
of accident lead to total stoppage of work a number of days.
* Accidents that cause an injured labourer to be hospitalised for
at least 24 h; this type of accident decreases productivity of the gang
in which this injured labourer was working.
* Small accidents that result from nails and steel wires; these
affect productivity in only a few cases.
Insufficient lighting has an average impact on labour productivity,
and ranked in position 27 of all 45 factors negatively affecting labour
productivity (Table 11). This result is justified, as labour needs
sufficient lighting to work effectively, and consequently, insufficient
lighting has a negative impact on labour productivity. Bad ventilation
and working at high places are not considered to be as instrumental as
other factors, and ranked in positions 35 and 37 of all factors
negatively affecting labour productivity. This result is justified, as
most building projects within the Gaza Strip are upgrade and have a
small number of storeys; therefore labour seldom face these problems in
building projects within the Gaza Strip.
The results also indicate that unemployment of the safety officer
on construction site is not considered to be as instrumental as other
factors on labour productivity. This result is justified within the Gaza
Strip, as contractors seldom employ safety officers in building
projects; therefore they are not aware of the importance of employing a
safety officer on construction sites. It should be noted that employment
of a safety officer on construction sites helps the labour to understand
the required safety regulations, and then to follow them. This prevents,
or at least reduces, the number of accidents, which consequently
improves labour productivity. Noise also is not considered to be as
instrumental as other factors on labour productivity, and ranked in the
last position of all factors affecting productivity. This result is
justified, as equipment and tools used in building projects within the
Gaza Strip cause little noise.
Quality group
The results in Table 9 depict the 3 factors under the quality
factors group; these are placed in descending order as follows:
inefficiency of equipment, poor quality of raw materials, and high
quality of required work. The surveyed companies have more tendencies to
place inefficiency of equipment as the most important factor within this
group, with an importance index value of 71.585. This result might be
justified, as the productivity rate of inefficient equipment is low, and
this consequently has an adverse impact on labour productivity depending
on this equipment. The type of equipment also affects labour
productivity; for example, new and modern equipment has a high
productivity rate, while old equipment has a low one, and is subject to
large number of breakdowns.
The surveyed companies ranked poor quality of raw materials at
position 18 of all factors affecting labour productivity, with an
importance index value of 71.32. This result might be justified, as the
time needed to build with materials of poor quality is greater than the
time needed to build with high quality materials. Additionally, wastage of materials of poor quality is high, particularly during handling.
Furthermore, using materials of poor quality leads to poor quality work,
which is consequently rejected by the supervisor. Quality of required
work has an average impact on labour productivity, and ranked in
position 22 of all 45 factors negatively affecting labour productivity.
This result is acceptable, as time required to finish work depends
greatly on allowed tolerance of required work; ie when the tolerance of
required work is very low, labour work slowly in order to avoid
unacceptable mistakes.
External group
The results in Table 10 demonstrate that 2 factors of the external
factors group have been ranked according to their importance as follows:
weather changes and augmentation of government regulations related to
the construction sector. Weather changes have an average impact on
labour productivity, and ranked in position 29 of all factors affecting
the productivity. Thomas and Sanders (1991) support this result in their
study of factors affecting productivity in the US. The temperature in
the Gaza Strip is moderate; therefore, increase and decrease of
temperature have a low effect on labour productivity. However, adverse
winter weather such as winds and rains reduce labour productivity;
particularly external work such as formwork, steel work, concrete
casting, external plastering, external painting, and external tiling.
Adverse weather sometimes stopped work totally.
Augmentation of government regulations related to the construction
sector is not considered to be as instrumental as other factors, and
ranked in position 36 of all factors negatively affecting labour
productivity. This result might be justified within the Gaza Strip,
where government regulation of construction projects has been subjected
to minor changes only during the last years.
Overall ranks of all factors negatively affecting labour
productivity
The results in Table 11 depict that the most 5 important factors
negatively affecting labour productivity are: material shortages; lack
of labour experiences; lack of labour surveillance; misunderstanding
between labour and superintendents; and drawings and specifications
alteration during execution, with important indexes values of 89.47,
84.21, 83.42, 80.26, and 80 respectively. On the other hand, results
indicate that labour absenteeism, labour personal problems, unemployment
of safety officer on the construction site, lack of training sessions,
and noise were the lowest factors negatively affecting labour
productivity, with important index values of 55, 54.74, 53.16, 50.26,
and 45 respectively.
Ranking groups negatively affecting labour productivity
The results in Table 12 demonstrate the ranking of 10 groups that
affect labour productivity. It is noted that the materials/tools factors
group was ranked first of 10 factor groups negatively affecting labour
productivity; this result is justified, as any project cannot be
executed without availability of materials and tools. The current
political situation within the Gaza Strip causes frequent closures of
crossing points between the Gaza Strip and Israel, which results in
shortages of materials and some tools in the local market, which affects
labour productivity too much. On the other hand, the safety factors
group was ranked last of the 10 groups affecting labour productivity,
which can be readily interpreted as that the government shows little
concern about safety, and that contracting companies have little
awareness of the impact of safety factors on labour productivity.
Therefore these safety factors were rated as having only an average or
low impact on labour productivity.
6. Conclusions
Productivity is considered the main value-adding function within
the construction sector. The aim of this research was to identify
factors affecting labour productivity in building projects, and to rank
these according to their relative importance from the contractor's
viewpoint within the Palestinian construction industry. A total of 45
factors were identified in this study, with identification of factors
influencing construction productivity being based on a careful review of
literature and suggestions from local experts in building construction.
The results indicated that the main 10 factors negatively affecting
labour productivity are:
1. Materials shortages.
2. Lack of labour experiences.
3. Lack of labour surveillance.
4. Misunderstanding between labour and superintendents.
5. Drawings and specification alteration during execution.
6. Payment delay.
7. Labour disloyalty.
8. Inspection delay.
9. Working seven days per week without holiday.
10. Tool / equipment shortages.
Furthermore, 45 factors considered in the study were divided into
10 groups, which were ranked according to their importance index:
1. Materials/tools factors group.
2. Supervision factors group.
3. Leadership factors group.
4. Quality factors group.
5. Time factors group.
6. Manpower factors group.
7. Project factors group.
8. External factors group.
9. Motivation factors group.
10. Safety factors group.
It is recommended that contracting companies should provide a
materials supply schedule for each project. This schedule should include
the time required to supply materials and the availability of materials
on the local market to furnish the required materials in time.
Contracting companies should also select a suitable storage location for
purchased materials in each project, which should be easily accessible
and close to constructed buildings to avoid wastage of labour time for
multiple-handling materials. Contracting companies have to pay more
attention to the quality of construction materials and tools used in
their projects, as using appropriate materials and tools reduces both
the time taken to finish the work and wastage of materials. Using
appropriate materials and tools also has a positive effect on the
quality of work, which consequently improves labour productivity.
Project management has to assign or recruit the right people to do the
job, and should also keep a close eye on labour work to make sure they
understand site instructions. Furthermore, it ought to maintain friendly
relations with labour and let them know they are important to the
organisation, and involve them in decisions affecting their jobs, such
as process improvements.
It is necessary to use project scheduling techniques (such as
computer-aided construction project management) in each project to
optimise the times of related activities, and to ensure that works allow
continuous task performance, so as to reduce idleness of the labour
force to a minimum. It is important for each contracting company to
adopt motivational or personnel management measures to boost
workers' morale. For example, tying compensation to performance;
ensuring that pay, fringe benefits, safety, and working conditions are
all at least adequate; and enlarging the jobs to include challenge,
variety, wholeness, and self-regulation. Contracting companies have to
conduct productivity studies at the activity/ operation level, such as
studying factors affecting labour productivity and labour productivity
measurement to describe the detailed tasks performed for an activity/
operation by individual or group in order to establish problem areas and
propose ways to improve labour productivity. Contracting companies are
also encouraged to keep historical data of productivity studies in
completed projects to improve the effectiveness and accuracy of cost
estimation of future projects.
It is necessary to conduct training courses and seminars in the
topics that will improve productivity in construction projects. The
training effort should be tailored to improve abilities to use project
scheduling techniques such as Microsoft project and Primavera. The
training effort should also be tailored to improve methods of studying
productivity and ways of productivity improvement on construction sites.
There is a need to increase the number of trade schools that focus on
teaching construction trades such as block work, formwork, painting,
plastering, plumbing etc to improve the abilities and skills of
craftsmen working on construction projects. More efforts should be made
by contracting companies to benefit from what other developed countries
have achieved through technology transfer and best use of benchmarking.
Received 16 Jan 2007; accepted 06 June 2007
References
AL HADDAD, A. A. (2007) Construction materials management system
for Gaza Strip building construction. Unpublished MSc thesis, Islamic
University of Gaza, Palestine.
ENSHASSI, A.; HALLAQ, K.; and MOHAMED, S. (2006) Causes of
contractors' business failure in developing countries: the case of
Palestine. Journal of Construction in Developing Countries, 11(2), p.
1-14.
ENSHASSI, A.; MOHAMMED, SH. MAYER, P. E.; ABEED, K. Benchmarking
masonry labor productivity. International Journal of Productivity and
Performance Management (Accepted for publication 2007).
GUHATHAKURTA, S.; and YATES, J. (1993) International labour
productivity. Cost Engineering Journal, 35(1), p. 15-25.
HEIZER, J.; RENDER, B. (1990) Production and operations management "strategic and tactical decisions". Prentice Hall, New Jersey.
HERBSMAN, Z.; and ELLIS, R. (1990) Research of factors influencing
construction productivity. Construction Management and Economics, 32(8),
p. 49-61.
HINZE, J. W. (1999) Construction planning and scheduling.
Prentice-Hall, New Jersey.
HOGG, R. V.; TANNIS, E. A. (1997) Probability and statistical
inferences. Prentice Hall.
KAMING, P. F.; HOLT, G. D.; KOMETA, S. T.; OLOMOLAIYE, P. O. (1998)
Severity diagnosis of productivity problems--reliability analysis.
International Journal of Project Management, 16(2), p. 107-113.
LEMA, N. M. (1995) Construction of labour productivity modeling.
University of Dar Elsalaam.
LIM, E. C.; ALUM, J. (1995) Construction productivity: issues
encountered by contractors in Singapore. International Journal of
Project Management, 13(1), p. 51-58.
MADI, I. M. (2003) Essential factors affecting accuracy of cost
estimation of building contractors. Unpublished MSc thesis, Islamic
University--Gaza, Palestine.
MAS (Palestinian economic policy research institute), 2001.
Economic monitoring report. Available from Internet:
<www.palecon.org/masdir/monitor/monitor.html>.
NAOUM, S. G. (1998) Dissertation research and writing for
construction students. Butterworth-Heinemann.
OGLESBY, C. H.; PARKER, H. W.; HOWELL, G. A. (2002) Productivity
improvement in construction. McGraw-Hill, USA.
OLOMOLAIYE, P.; JAYAWARDANE, A.; HARRIS, F. (1998) Construction
productivity management. Chartered Institute of Building, UK.
OLOMOLAIYE, P.; KAMING, P.; HOLT, G.; HARRIS, F. (1996) Factors
influencing craftsmen's productivity in Indonesia. International
Journal of Project Management, 15(1), p. 21-30.
PASSIA (2002) Jerusalem, Palestine.
PAULSON, B. C. (1975) Estimation and control of construction labour
costs. Journal of Construction Division, ASCE, 101 (CO3), p. 623-633.
PCBS (the Palestinian central bureau of statistics) (2004) Number
of enterprises and persons engaged for construction contractors
(1995-2000).
PECDAR (1997) Housing in Palestine. Palestine.
PILCHER, R. (1997) Principles of construction management.
McGraw-Hill, London.
ROJAS, M. E.; ARAMVAREEKUL, P. (2003) Labour productivity drivers
and opportunities in the construction industry. Journal of Management in
Engineering, 19(2), p. 78-82.
TEICHOLZ, P. (2001) US Construction labour productivity trends,
1970-1998. Journal of Construction Management and Engineering, ASCE,
127(5), p. 427-429.
THOMAS, H. R. (1999) Construction baseline productivity: theory and
practice. Journal of Construction Management and Engineering, ASCE,
125(5), p. 295-303.
THOMAS, H. R.; SANDERS, S. R. (1991) Factors affecting masonry
productivity. Journal of Construction Engineering and Management, ASCE,
117(4), p. 626-644.
United Nations (1965) The effect of repetition on building
operations and processes on site. New York.
WACHIRA, L. N. (1999) Labour productivity in the Kenyan
construction industry. University of Nairobi, Kenya.
WILCOX, S.; STRINGFELLOW, B.; HARRIS, R.; MARTIN, B. (2000)
Management and productivity. Transportation research board, committee on
management and productivity. Washington, USA.
World Bank (2004) Two years of Intifada, closures and Palestinian
economic crisis. Washington, USA.
ZHI, H. (1995) Risk management for overseas construction projects.
International Journal of Project Management, 13(4), p. 231-237.
Adnan Enshassi (1), Sherif Mohamed (2), Ziad Abu Mustafa (1) and
Peter Eduard Mayer (3)
(1) School of Civil Engineering, Islamic University of Gaza, P.O.
Box 108, Gaza, Palestine
(2) School of Engineering, Griffith University, Gold Coast Campus,
QLD 4222, Australia
(3) Projektmanagement und Baurecht, Technische Universitat Munchen,
Arcisstrasse 21, D-80333 Munchen, Germany
Adnan Ali ENSHASSI. Professor of Construction Engineering and
Management in the Civil Engineering Dept at IUG with over 20 years of
research, teaching, and consulting experience in various construction
project management disciplines. A visiting Professor at Clemson
University (USA), Bremen University, Stuttgart Technical University,
Berlin Technical University, and Munich Technical University (Germany),
Graz University (Austria) and Liverpool University (UK). His research
interests include occupational safety and health, contract management,
productivity measurement and improvement. Member/Fellow of a number of
international professional institutions in USA and UK. He is listed in
Marquis "Who's Who in Science and Engineering". The
University scientific research prize for Science and Engineering in
2005.
Peter Eduard MAYER. Professor for Project Management and
Construction Law at the Technische Universitaet in Munich (Germany). His
research interests include new forms of construction contracts, site
organization and management. He is also a sworn expert witness at court.
Sherif MOHAMED. Professor and Director of the Centre for
Infrastructure Engineering and Management at Griffith University,
Queensland (Australia). His research interests: project and construction
management. He focuses on the development of theoretical knowledge and
operational tools needed for effective process management. Author and
co-author of over 100 refereed journal and conference publications in
the last 10 years.
Ziad Abu MUSTAFA. Project manager with a local contracting company
in Gaza. Experience in the construction industry of more than 10 years.
Master degree in Construction Management from IUG.
Table 1. Ranking factors under manpower group
Factors Imp. index Rank
Lack of labour experience 84,21 1
Labour disloyalty 78,55 2
Labour dissatisfaction 72,11 3
Misunderstanding among labour 71,58 4
Lack of competition 66,84 5
Increase of labourer age 62,63 6
Labour absenteeism 55,00 7
Labour personal problems 54,74 8
Table 2. Ranking factors under leadership group
Factors Imp. index Rank
Lack of labour surveillance 83,42 1
Misunderstanding between labour/
superintendents 80,26 2
Lack of periodic meeting with labour 56,84 3
Table 3. Ranking factors under motivational group
Factors Imp. index Rank
Payment delay 78,68 1
Lack of financial motivation system 68,95 2
Lack of labour recognition programs 61,84 3
Non-provision of transport means 56,05 4
Lack of places for eating and relaxation 55,53 5
Lack of training sessions 50,26 6
Table 4. Ranking factors in the time group
Factors Imp. index Rank
Working 7 days per week without
taking a holiday 76,58 1
Misuse of time schedule 74,74 2
Method of employment (using direct
work system) 65,79 3
Increasing No of labour in order to
accelerate work 64,47 4
Work overtime 62,37 5
Table 5. Ranking factors under materials/tools group
Factors Imp. index Rank
Material shortages 89,47 1
Tool and equipment shortages 75,26 2
Unsuitability of materials storage location 69,21 3
Table 6. Ranking factors under supervision group
Factors Imp. index Rank
Drawings and specifications alteration
during execution 80,00 1
Inspection delay 77,63 2
Rework 75,00 3
Supervisors' absenteeism 71,84 4
Table 7. Ranking factors under the project group
Factors Imp. index Rank
Working within a confined space 70,26 1
Interference 67,11 2
Construction method 62,11 3
Type of activities in the project 61,58 4
Table 8. Ranking factors under safety group
Factors Imp. index Rank
Accidents 72,37 1
Violation of safety precautions 67,63 2
Insufficient lighting 64,74 3
Bad ventilation 61,32 4
Working at high places 58,68 5
Unemployment of safety officer on
the construction site 53,16 6
Noise 48,42 7
Table 9. Ranking factors in the quality group
Factors Imp. index Rank
Inefficiency of equipment 71,58 1
Low quality of raw materials 71,32 2
High quality of required works 67,89 3
Table 10. Ranking factors under external group
Factors Imp. index Rank
Weather changes 63,95 1
Augmentation of Government regulations 60,79 2
Table 11. Overall ranking of factors negatively affecting labour
productivity
Factors Imp. index Rank
Material shortages 89,47 1
Lack of labour experience 84,21 2
Lack of labour surveillance 83,42 3
Misunderstanding between labour
and superintendents 80,26 4
Drawings and specifications alteration
during execution 80,00 5
Payment delay 78,68 6
Labour disloyalty 78,55 7
Inspection delay 77,63 8
Working 7 days per week without
taking a holiday 76,58 9
Tool and equipment shortages 75,26 10
Rework 75,00 11
Misuse of time schedule 74,74 12
Accidents 72,37 13
Labour dissatisfaction 72,11 14
Supervisors' absenteeism 71,84 15
Inefficiency of equipment 71,585 16
Misunderstanding among labour 71,58 17
Low quality of raw materials 71,32 18
Working within a confined space 70,26 19
Unsuitability of materials storage
location 69,21 20
Lack of financial motivation system 68,95 21
High quality of required work 67,89 22
Violation of safety precautions 67,63 23
Interference 67,11 24
Lack of competition 66,84 25
Method of employment
(using direct work system) 65,79 26
Insufficient lighting 64,74 27
Increasing number of labours 64,47 28
Weather changes 63,95 29
Increase of labourer age 62,63 30
Working overtime 62,37 31
Lack of labour recognition programs 61,84 33
Construction method 62,11 32
Type of activities in the project 61,58 34
Bad ventilation 61,32 35
Augmentation of Government regulations 60,79 36
Working at high places 58,68 37
Lack of periodic meeting with labour 56,84 38
Non-provision of transport means 56,05 39
Lack of place for eating and relaxation 55,53 40
Labour absenteeism 55,00 41
Labour personal problems 54,74 42
Unemployment of safety officer on
the construction site 53,16 43
Lack of training sessions 50,26 44
Noise 48,42 45
Table 12. Ranking factors negatively affecting productivity
among groups
Factors groups Imp. index Rank
Materials / Tools factors 77,98 1
Supervision factors 76,12 2
Leadership factors 73,51 3
Quality factors 70,36 4
Time factors 68,79 5
Manpower factors 68,16 6
Project factors 65,26 7
External factors 62,38 8
Motivation factors 61,85 9
Safety factors 60,90 10
Fig 1. Labour forces employed in the Palestinian construction
industry (PASSIA, 2002)
2001 15.10%
2000 19.70%
1999 22.30%
1997-1998 20.09%
1996 12.60%
Note: Table made from pie chart.