Simulation-enhanced approach for ranking major transport projects.
Su, Cheng-Wei ; Cheng, Min-Yuan ; Lin, Feng-Bor 等
Abstract. Owing to financial constraints, it becomes imperative to
rank major transport projects to determine implementation priorities and
budget allocations. The central Government in Taiwan is using rankings
derived from the Analytic Hierarchy Process (AHP) and direct subjective
rankings to set funding priorities. The current approach does not
account for the variations in rankings for setting these priorities. Nor
does it adequately consider the compatibility with the proposed projects
and the national policies in transport infrastructure development. To
address these problems, the Central Government has revised the method
for project ranking. The revised method expands the matrix of the
attributes and impacts that are to be evaluated. It also uses a Monte
Carlo simulation analysis to help in determining the rank orders. A
pilot study was conducted to assess the revised method. The study uses
25 major rail projects proposed in 2002 as a test bed.
Keywords: analytic hierarchy process, Monte Carlo simulation,
project ranking, rail projects.
1. Introduction
The resources available in any country for transport infrastructure
improvement rarely meet the needs. Taiwan's central government
encounters this dilemma regularly. As an example, 25 rail projects were
proposed to the central government in 2002 for a total budget request of
US $ 2,2 billion but the funding level approved that year for the rail
projects was only $ 0,7 billion. Under this type of severe fiscal
constraints, it becomes imperative to employ a rational and structured
process to determine funding priorities.
Major transport projects require large capital spending, and they
invariably have a wide range of tangible and intangible impacts. To
facilitate an efficient, equitable and environment-friendly allocation
of limited resources, the impacts of a project should be weighed against
those of other projects to determine funding priorities. This is a
difficult task because of the lack of a single and objective measure
that can be used to determine the net worth of each competing project to
the society. In a democracy, this problem is compounded by the presence
of many stakeholders whose vested interests often make the funding of a
major transport project contentious. Under the circumstances,
Taiwan's central government has been using the Analytical Hierarchy
Process (AHP) and direct ranking to determine the funding priorities of
major transport projects (Su et al 2002).
Since its introduction by Saaty (1980) more than two decades ago,
the AHP has been used in many countries. In the US, for example, the AHP
has been used for evaluating urban transit alternatives (Kaysi and
Abdul-Malak, 2001). The Indiana Dept of Transportation (Kim and
Bernardin, 2002) has also used AHP for prioritising major highway
capital investments. And, because of its solid mathematical foundation,
the AHP has been recommended to the Michigan Dept of Transport to
develop a composite performance index for each transit service that
receives state funding (Khasnabis et al, 2002). In Europe, the AHP has
been used for resources allocation (Ramannathan and Ganesh 1995). AHP
application software has also been developed (Ossadnik and Lange 1999).
In Turkey, the AHP was the tool used for evaluating alternative rail
transit networks for Istanbul (Gercek et al, 2004).
The AHP provides an analytical foundation to combine both tangible
and intangible impacts into numerical scores for ranking alternatives.
It requires evaluators to perform pair-wise comparisons of the relative
importance of goals and objectives, as well as the relative desirability
of competing projects. For evaluating major transport projects in
Taiwan, however, the application of the AHP in the past has several
major weaknesses. To address this problem, the Central Government has
revised the current method for project ranking. As part of this effort,
a pilot study was conducted to assess the revised method. The study uses
25 rail projects proposed in 2002 as the test bed. This paper describes
the revised method and the findings of the pilot study.
2. Project funding process
In Taiwan, the funding of major highway or rail transport projects
follows a process (Fig 1). First, various transport agencies of the
local governments or the Central Government formulate projects based on
projected needs for transport services. At present, this initial effort
is often carried out without much coordination between agencies. Second,
each proposing agency has to conduct a feasibility study. According to the current regulations, such a study has to cover economic
feasibilities, financing issues, and socio-economic and environmental
impacts. Third, each agency must submit a comprehensive study report to
the Executive Yuan for review and approval. The Executive Yuan is the
highest executive branch of Taiwan's Central Government. Table 1
shows an example of the key items and findings included in the
feasibility study reports of two rail projects. Fourth, approved
projects are then presented to a panel of evaluators for ranking. The
panel is composed of 10-12 representatives from the Institute of
Transportation, the Dept of Highways and Railroads, and the Dept of
Accounting. Finally, the panel submits its recommendations to the
Executive Yuan the authority to make final funding decisions. It is not
bound by the recommendations made by the project evaluation panel.
[FIGURE 1 OMITTED]
The budget allocation is done on an annual basis. This means that
each proposing agency has to submit a budget request for the following
fiscal year. It also means that an ongoing project has to compete with
new or other ongoing projects for funding. As a result, whether a
project has received funding in the past and to what extent a funded
project has been completed are relevant concerns in project ranking.
This annual budgeting cycle has been criticised for running a high risk
of inefficient implementation of approved projects.
3. Ranking process
Taiwan's national polices for transport infrastructure
development are to: (1) foster an integrated multi-modal transport
network that links airports, harbours, highways, bus and rail transit
systems, and regional railways; (2) improve transport safety,
efficiency, and mobility; (3) ensure sustainable use of resources; and
(4) preserve cultural heritage and improve living environment. Because
of a very high population density (23 mil people in an area of 36 000
[km.sup.2]), Taiwan's central government views rail transport as a
key for promoting sustainable socioeconomic and land use development.
The Central Government has been using the AHP to evaluate major
transport projects. For rail transport projects, the evaluation is based
on the various items of project attributes and impacts, such as those
shown in Table 1. This practice has 3 major drawbacks. First, the AHP
requires pair-wise comparisons to determine: (1) the relative importance
of each attribute or impact (eg, rate of return vs air pollution level);
and (2) the relative desirability of each project as characterised by
each attribute or impact. The number of attributes and impacts that need
to be considered is large. This makes the evaluation process rather
tedious and prone to evaluator fatigue and inconsistency in exercising
judgment. This is compounded by the fact that the number of projects to
be evaluated in a typical year is also large. Second, current
regulations do not require a feasibility study to address the
compatibility of a proposed project with the national policy of
developing an integrated, multi-modal transport network. Furthermore,
because projects are independently initiated by various agencies,
feasibility studies do not address the issue of whether a proposed
project would complement other projects. Therefore, there is a need to
expand the evaluation criteria. And, finally, the ranking process as
practiced in the past reduces various ratings into an average rating for
each project according to the following formula:
[MATHEMATICAL EXPRESSION NOT REPRODUCIBLE IN ASCII] (1)
where
[r.sub.i]--average rating of project i; [??]--average weight of
evaluation criterion j; and [??]--average rating of project i with
respect to evaluation criterion j.
The average ratings of the competing projects become the basis for
determining the rank orders of the projects. It should be noted that
[??] and [??] are the averages of the respective weights and ratings
assigned by the evaluators. The averaging process would invariably
result in a loss of information concerning the true nature of the
desirability of a project.
To mitigate the drawbacks mentioned above, the Central Government
has revised the ranking method. This revised method consists of 5 tasks
as described below.
Task 1. Develop categories of evaluation criteria
This task is the responsibility of the evaluation panel that
usually consists of 10 to 12 evaluators. The evaluators are
representatives of 3 Central Government agencies: the Institute of
Transportation, the Dept of Highways and Railroad, and the Dept of
Accounting. As a pilot study of the revised ranking method, a panel of
12 evaluators was asked to evaluate 20 rail projects that were proposed
in 2002. Five of the projects were pending approval by the Executive
Yuan at the time of the study. The panel members were asked to treat
these projects as approved projects.
A major concern in the process of developing evaluation categories
is the ease in applying the AHP. After some discussions, the panel
members agreed to classify project attributes and impacts detailed in
feasibility studies, such as those shown in Table 1, into 6 evaluation
categories. These 6 categories include: (1) project development stage;
(2) degree of project completion; (3) safety, efficiency, and mobility;
(4) economic and financial feasibility; (5) level of pollution; (6)
social, cultural, and land-use impacts. Each category represents a group
of similar project attributes or impacts. In addition, compatibility
with the national transport policies makes up the 7th category of
evaluation criteria. This evaluation category covers concerns about the
energy policy, human resources development, cross-jurisdictional
coordination of transport service, equity of mobility, and national
transport development plan.
Task 2. Determine weights of evaluation categories
In this task the evaluators uses the AHP to determine the weight of
each evaluation category. The resulting weight reflects the relative
importance of that category as compared with all other categories.
Because project impacts and attributes are grouped rather than being
treated individually, the number of pair-wise comparisons that have to
be performed is quite manageable. Table 2 shows the weights derived from
the AHP in the pilot study.
It should be noted again that Taiwan's current regulations do
not require a feasibility study to address the compatibility of a
project with the national transport policies. Surprisingly, Table 2
reveals that the evaluators as a whole rate evaluation category 7
(compatibility with national transport policies) the most important by
giving it a mean weight of 0,3. Therefore, there is a need to change the
regulations to require that feasibility studies explicitly address the
compatibility issue.
Table 2 also shows that, among the first 6 evaluation categories,
category 1 (project development stage) and category 2 (degree of project
completion) are deemed more important. This implies that the ranking
process favours ongoing projects. It also implies that the
evaluators' judgments are consistent with the common practice of
not stopping an ongoing project.
Task 3. Rate project attributes and impacts
With respect to a given evaluation category, each evaluator would
assign an integer desirability rating to each competing project. This
rating is on a scale of 1 to 6, with 6 representing the most desirable.
Evaluators are required to review the feasibility study reports before
executing this task of direct rating.
At present, the feasibility study of a project does not have to
provide an analysis of the compatibility with the national transport
policies. Therefore, in terms of the compatibility issue, evaluators
have to assign a ranking for each project without input from a proposing
agency. The execution of this task is not a significant problem. This is
because the members of the evaluation panel are seasoned experts on the
national transport policies and needs, and they are familiar with the
potential impacts of the competing projects. Table 3 shows the ratings
of one of the projects included in the pilot study.
Task 4. Determine the distributions of aggregated ratings of
competing projects
Instead of using average weights and ratings in Eq 1 to determine a
single rating for each project, the revised method uses the weights and
ratings assigned by individual evaluators to determine the probability
distribution of the final rating of each project. This task requires the
use of Monte Carlo simulation. The project on rehabilitation of rail
line structure is used as an example to illustrate the simulation
process. The needed data are shown in Tables 2, 3.
Refer to Table 2. The weights assigned to each evaluation category
may differ from one evaluator to another. Therefore, the weight of each
evaluation category is not a constant and thus would be best represented
by a probability distribution. To facilitate simulation, the weights for
each category should be transformed into a cumulative distribution. For
evaluation category 1, which has weights ranging from 0,17 to 0,28, the
cumulative distribution is as shown in Fig 2. Given this distribution,
random number R with a value uniformly distributed between 0 and 1 can
be generated to represent the cumulative proportion shown in Fig 2.
Based on this random number and the cumulative distribution, a
corresponding weight [W.sub.1] can be determined for evaluation category
1. A large number of weights can be generated in this manner in a
simulation process. These weights will form a distribution that is
statistically identical to the original distribution. Similarly, the
ratings, shown in Table 3 with respect to each evaluation category can
be represented by a cumulative distribution for simulation analysis.
[FIGURE 2 OMITTED]
The simulation analysis requires a large number of simulation runs
in order to simulate the actual distribution of each weight or rating.
Each run would proceed in several steps. First, a weight is generated
randomly for each evaluation category, subject to the constraint that
the sum of the weights of all evaluation categories must equal 1,0.
Next, for each project, a rating is generated randomly with respect to
each evaluation category. And, finally, the generated weights and
ratings are used in the following equation to determine the aggregated
rating of each project:
[R.sub.i] = [n.summation over (i=1)] [W.sub.ji][K.sub.ji], (2)
where
[R.sub.i]--aggregated desirability rating of a project based on
simulation run i; [W.sub.ji]--weight generated for evaluation category j
in simulation run i; and [K.sub.ji]--rating generated for the project
with respect to evaluation category j in simulation run i.
The aggregated rating obtained from Eq 2 represents one possible
aggregated rating of a project. Based on the results of a large number
of simulation runs (eg, 5 000), the frequency distribution of the
aggregated ratings of each project can be identified. Fig 3 shows the
resulting frequency distribution for the project on rehabilitation of
rail line structures. This distribution has a mean rating of 4,15 and a
standard deviation (SD) of 0,34. Fig 3 shows that the distribution is
skewed to the right, with a probability of less than 20 % that an
aggregated rating would exceed 4,5. If the mean weights and ratings
shown respectively in Tables 2 and 3 were used in Eq 1, the result would
not be able to reveal that the rating of the project can vary between
3,0 and 5,5.
[FIGURE 3 OMITTED]
Task 5. Determine rank orders of competing projects
The rank order of a project is based primarily on the mean
aggregated rating of that project. It may not be adequate, however, to
determine the final rank order of a project solely on the basis of the
mean aggregated rating. This is because when the aggregated ratings of a
project in different simulation runs spread over a wider range, it
becomes less certain that the mean rating represents the true
desirability of the project. A project that has a wider spread of
ratings is also one that is more controversial and should be given a
lower priority. For this reason, the revised method for project ranking
requires the frequency distribution of the aggregated ratings of each
project be analysed to provide an additional information.
Based on the results of 500 000 simulation runs for all the
projects proposed in 2002, Fig 4 shows that, on average, there is only a
5 % probability that the aggregated ratings of a project would exceed
its mean by 0,74. Therefore, if a project has a much greater probability
that its aggregated ratings will deviate from the mean rating by 0,74,
the project can be reasonably judged as controversial. It is recommended
that the threshold probability be set at 9 % (ie, 1,8 times 5 %). This
threshold leads to 4 of the 25 competing projects (or 16 %) being
classified as controversial. This information is to be included in
future panel's recommendation to the Executive Yuan.
[FIGURE 4 OMITTED]
The results of the pilot study are summarised in Table 4 along with
the percentage of budget request actually granted for each project. Fig
5 shows that the funding level, expressed as percent of requested
budget, tends to increase with the mean aggregated rating of a project.
This implies that the mean aggregated ratings derived from the revised
method can be meaningfully used for budget allocation.
[FIGURE 5 OMITTED]
4. Conclusions
Taiwan's Central Government uses the AHP and direct rankings
to determine the relative desirability of major transport projects. To
address several weaknesses in the past practice of project ranking, the
Central Government has conducted a pilot study to assess a revised
method for project ranking. The pilot study findings show that the
revised method is easy to apply and can generate meaningful information
to help in budget allocation. It is expected that the revised method
implementation will enhance the ability of the Executive Yuan to
effectively and equitably utilise limited resources.
The revised method of project ranking is essentially a
methodological framework in which details of project evaluation can
evolve over time in response to changing regulations and goals of
transport infrastructure development. One area that the pilot study did
not address is the practical maximum number of evaluation categories
that evaluators can effectively handle in applying the AHP. The study
shows that the evaluators can easily carry out paired comparisons of 7
evaluation categories. Increasing this number of evaluation categories
would allow project attributes and impacts to be stratified into more
groups. This would minimise the possibility that evaluators may ignore
some project attributes or impacts in passing judgment.
Received 15 July 2005; accepted 12 Sept 2006
References
Gercek, H.; Karpak, B. and Kilincaslan, T. (2004) A Multiple
Criteria Approach for the Evaluation of the Rail Transit Networks in
Istanbul. Transportation, 31(2), p. 203-228.
Kaysi, I. A. and Abdul-Malak, M. U. (2001) Decision Structuring and
Robustness Analysis in Selecting Transit Alternatives. Journal of Public
Transportation, 4(1), p. 73-102.
Khasnabis, S.; Alsaidi, E.; Liu, L. and Ellis, R. D. (2002)
Comparative Study of Two Techniques of Transit Performance Assessment:
AHP and GAT. Journal of Transportation Engineering, 128(6), p. 499-508.
Kim, K. and Bernardin, V. (2002) Application of an Analytical
Hierarchy Process at the Indiana Department of Transportation for
Prioritizing Major Highway Capital Investments. In: Proc of 7th
Transportation Research Board Conference on the Application of
Transportation Planning Methods, Boston, Massachusetts, March 7-11,
1999. Ed R. Donnelly, p. 266-278.
Ossadnik, W. and Lange, O. (1999) AHP-Based Evaluation of AHP-
Software. European Journal of Operational Research, 118(12), p. 578-588.
Ramannathan, R. and Ganesh, L. S. (1995) Using AHP for Resource
Allocation Problems. European Journal of Operational Research, 80(2), p.
410-417.
Saaty, T. L. (1980) The Analytic Hierarchy Process, New York:
McCraw-Hill.
Su, C. W.; Cheng, M. Y. and Lin, K. S. (2002) Data Preprocessing for Ranking of Projects-A Case Study of Rail Transportation Investment.
In: Proc of the 17th Conference of Transportation Association, ROC,
Chiayi, Taiwan, Dec 20-23, p. 1015-1026.
PAGRINDINIU SUSISIEKIMO PROJEKTU SUSKIRSTYMO PAGAL RANGUS BUDAS,
REMIANTIS MODELIAVIMU
Cheng-Wei Su, Min-Yuan Cheng, Feng-Bor Li
Santrauka
Del finansiniu apribojimu pagrindiniai susisiekimo projektai turi
buti suskirstyti pagal rangus, nustatant igyvendinimo prioritetus ir
biudzeto paskirstyma. Taivanio centrine vyriausybe rangams nustatyti
naudojasi analitiniu hierarchiniu procesu (AHP) ir tiesiogiai suteikia
rangus prioritetinei finansavimo eilei. Taciau sis metodas nera
adekvatus siulomu projektu ir nacionalines susisiekimo infrastrukturos
pletojimo politikos suderinamumui. Siai problemai spresti butina
perziureti projektu suskirstymo pagal rangus metoda. Patikslintame
metode isplesta atributu matrica. Rangu sekai nustatyti taikomas Monte Karlo modeliavimo metodas. Patikslinto metodo analizei atlikta bandomoji
studija. Kaip tyrimo objektai studijoje panaudoti 2002 m. pasiulyti 25
pagrindiniai gelezinkelio projektai.
Reiksminiai zodziai: analitinis hierarchinis procesas, Monte Karlo
modeliavimas, projektu suskirstymas pagal rangus, gelezinkelio
projektai.
Cheng-Wei SU. PhD of Construction Engineering, National Taiwan
University of Science and Technologicy. The Deputy Chief of the Division
of Transportation Planning at Taiwan's Institute of Transportation,
which is a branch of the Ministry of Transportation and Communications.
His research interest covers construction procedures, traffic modelling,
highway and railway capacity analysis methodologies, decision-making
processes, and environmental impact analysis. Member of Taiwan's
Association of Transportation Engineers.
Min-Yuan CHENG. Professor of Dept of Construction Engineering at
the National Taiwan University of Science and Technology. An Editorial
Board member of Automation in Construction Journal. His research
interests include construction automation, applications of artificial
intelligence in construction management, e-commerce in construction
industry, business process reengineering, RFID applications.
Feng-Bor LIN. Professor, Dept of Civil and Environmental
Engineering, Clarkson University. His research interests include traffic
operations, systems analysis and modelling, and highway capacity
analysis. Member of American Society of Civil Engineers, served on
several committees of the US Transportation Research Board.
Cheng-Wei Su (1), Min-Yuan Cheng (2), Feng-Bor Lin (3)
(1) Dept of Construction Engineering, National Taiwan University of
Science and Technology. Deputy Chief, Division of Transportation
Planning, Institute of Transportation, Ministry of Transportation and
Communications, 240 Tunhwa N. Road, Taipei, Taiwan. E-mail:
jason@iot.gov.tw
(2) Dept of Construction Engineering, National Taiwan University of
Science and Technology, 43, Keelung Road, Sec. 4, Taipei, Taiwan.
E-mail: myc@mail.ntust.edu.yw
(3) Dept of Civil and Environmental Engineering, Clarkson
University, Potsdam, New York 13699, U.S.A. E-mail: iu00@clarkson.edu
Table 1. Example of project attributes and impacts revealed in
feasibility studies
Status
Project attributes
and impact Tainan City Kuoshiung City
underground underground
Category Item rail project rail project
Project Network integration Completed Completed
development plan
Stage Land-use plan Completed Completed
Right-of-way Completed Completed
acquisition plan
Degree of Previous budget 1,9 27,0
project allocation
completion (US$million)
Unused budget 1,9 0
(US$million)
Percent completion 0 1,11
Safety, Reduction in fuel 7,8 17,4
efficiency, consumption
and Mobility (US$million/year)
Travel time savings/ 46,5 176,9
year
(US$million/year)
Number of at-grade 8 5
crossings eliminated
Increase in ridership 7,200 9,600
(persons/day)
Economic and Planning, design and 910,3 2,422
financial construction costs
feasibilities (US$ in million)
Net present value of -765,8 -1 004,0
capital investment,
revenue, operating
and maintenance
costs, and salvage
value (US$ million)
Economic internal 7,26 8,03
rate of return (%)
Level of Construction period 8 12
pollution (years)
Maximum air pollution 344 325
level during
construction
Water pollution 72 130
during construction
(liter/day)
Increase in noise 10/-5 dBA 12/-8 dBA
pollution during/
construction/
operation
Social, Earthwork (10,000 153 50
cultural, and [m.sup.3])
land use Historical sites 0 0
impact affected
Ecological systems None None
and watershed
affected
Esthetics Significant Significant
improvement improvement
on along along existing
existing line
line
Table 2. Weights of evaluation categories
Evaluation category
Evaluator
ID 1 2 3 4 5 6 7
1 0,21 0,11 0,05 0,11 0,04 0,08 0,40
2 0,28 0,15 0,10 0,11 0,02 0,14 0,20
3 0,17 0,16 0,07 0,08 0,09 0,03 0,40
4 0,21 0,17 0,06 0,13 0,08 0,06 0,29
5 0,21 0,27 0,21 0,02 0,04 0,14 0,11
6 0,18 0,15 0,09 0,07 0,07 0,05 0,39
7 0,24 0,19 0,08 0,13 0,06 0,10 0,20
8 0,25 0,07 0,05 0,11 0,02 0,10 0,40
9 0,20 0,19 0,15 0,01 0,07 0,07 0,31
10 0,24 0,19 0,08 0,13 0,09 0,06 0,21
11 0,18 0,15 0,07 0,09 0,02 0,10 0,39
12 0,24 0,13 0,06 0,12 0,08 0,06 0,31
Mean 0,22 0,16 0,09 0,09 0,06 0,08 0,30
Weight
Table 3. Ratings of project on rehabilitation of rail line structures
Evaluation category
Evaluator
ID 1 2 3 4 5 6 7
1 4 3 3 3 4 4 4
2 5 4 4 3 4 5 4
3 3 2 3 2 1 2 4
4 4 3 3 3 4 6 4
5 6 5 5 5 6 6 4
6 6 5 5 5 6 6 4
7 4 3 3 3 4 4 4
8 6 5 5 5 6 6 5
9 4 3 3 3 4 4 3
10 5 4 4 4 5 5 4
11 6 5 5 5 6 6 4
12 4 3 3 3 4 4 4
Mean
ranking 4,75 3,75 3,83 4,67 4,50 4,83 4,00
Table 4. Results of project ranking and budget allocation for 25 rail
projects proposed in 2002
Aggregated rating
% deviating
from mean Rank
Project j mean by 0,74 order
1. Connector System for High-Speed 4,81 4,1 4
Rail
2. Wanhaw-Bachaw Underground Rail 4,69 11,8 5
3. Engineering of Taipei Metro Mass 5,20 0,1 1
Transit
4. CKS Airport-Taipei Transit Line 4,03 6,1 14
5. Improvement of Eastern Rail 4,86 8,6 3
Lines
6. Rehabilitation of Rail Line 4,15 3,5 10
Structures
7. Kaoshung Mass Transit-Phase I 4,22 2,1 9
8. High-Speed Rail ROW Acquisition 4,35 1,1 7
9. Taipei Metro Mass 3,02 6,8 21
Transit--Shingyee Line
10. Taipei Metro MRT--Nangan 3,91 0,0 17
Extension
11. Rail-Highway Crossing Safety 4,34 0,8 8
Improvement
12. Rail Car Purchase 5,04 7,2 2
13. Relocation of Chusung 4,11 0,1 12
Maintenance Shop
14. Taipei Underground Line 3,65 0,0 18
Extension--Shonsan Line
15. Taipei Underground Line 4,09 0,3 13
Extension to Nangung
16. Improvement of Security Systems 4,45 0,4 6
17. Kaoshung Underground Rail 2,97 9.1 22
18. Purchase of Cars for Regional 3,96 6,3 16
Passenger Rail
19. Replacement of Freight Cars 4,00 6,4 15
20. Underground Relocation of 1,92 17,9 23
Taichung-Chayi Line
21. Tainan Metro MRT 1,69 6,05 25
22. Taichung Metro Mass Transit 1,85 7,03 24
23. Relocation of Dado Maintenance 3,46 1,83 19
Shop
24. Taipei MRT- Singzung and LuZou 4,13 5,64 11
Lines
25. Elevation of Taoyuan-Chungli 3,07 9,38 20
Metro Line
% of
budget
request
Project j Remark granted
1. Connector System for High-Speed 100
Rail
2. Wanhaw-Bachaw Underground Rail controversial 93,1
3. Engineering of Taipei Metro Mass 100
Transit
4. CKS Airport-Taipei Transit Line 100
5. Improvement of Eastern Rail 100
Lines
6. Rehabilitation of Rail Line 75,6
Structures
7. Kaoshung Mass Transit-Phase I 90,1
8. High-Speed Rail ROW Acquisition 100
9. Taipei Metro Mass pending approval NA
Transit--Shingyee Line
10. Taipei Metro MRT--Nangan 99,8
Extension
11. Rail-Highway Crossing Safety 100
Improvement
12. Rail Car Purchase 100
13. Relocation of Chusung 83,3
Maintenance Shop
14. Taipei Underground Line pending approval NA
Extension--Shonsan Line
15. Taipei Underground Line 92,8
Extension to Nangung
16. Improvement of Security Systems 68,4
17. Kaoshung Underground Rail controversial 67,2
18. Purchase of Cars for Regional 100
Passenger Rail
19. Replacement of Freight Cars pending approval NA
20. Underground Relocation of pending approval NA
Taichung-Chayi Line controversial
21. Tainan Metro MRT 4,54
22. Taichung Metro Mass Transit 0,0
23. Relocation of Dado Maintenance 0,0
Shop
24. Taipei MRT- Singzung and LuZou 90,8
Lines
25. Elevation of Taoyuan-Chungli pending approval NA
Metro Line controversial