Fractal approach for manufacturing project management/Fraktalu taikymai gamybos projektu valdymui.
Karaulova, T. ; Poljantshikov, I. ; Shevtshenko, E. 等
1. Introduction
This research paper is focused on the planning problems of
production processes in manufacturing for small and medium enterprises
(SMEs), which practice business activities that are performed based on
integrated multiple projects management. These problems have received a
major attention from researchers and practitioners over the last decade.
The reason is an exceptional importance for non-single project
implementations to reach total profitability, while complexity of the
project environment keeps increasing.
Individual projects management is usually a difficult task. The
situation becomes much more complicated when there are multiple on-going
projects within an organization. Projects need to be considered as an
integrated portfolio, rather than a disjointed collection. The process
of managing multiple projects requires maintaining control over a varied
range of projects, in order to balance the concurrent demands with
limited resources and to coordinate the project portfolio to achieve the
optimal outcome for organisation.
The multiple projects management (MPM) requires an efficient,
dynamic process for determining how to allocate resources and set a
realistic delivery schedule for new projects, especially when new
project is added to an existing portfolio. Besides the problem of scarce
resource allocation among the projects and their tasks, one of the
important challenges in any multi-project environment is the
coordination of the different tasks comprising those projects.
Coordination is especially difficult in situations where the complexity
of the comprised projects leads to their separation into concurrent and
interrelated tasks, the results of which must be integrated dynamically
into an entire portfolio of a satisfactory solution.
Practically every manufacturing enterprise manages a number of
projects or multiple projects. One of the major problems is dealing with
the complexity resulting from the multifunctional aspect of the
projects, which needs a clear definition of the objectives and the roles
of each manager on an enterprise.
The aim of the current research is to work out the method and
principles of multi-project management targeted to maximization of
existing resources utilization within a separate manufacturing
enterprise in the projects management environment.
1.1. MPM as a complex system
Projects are characterized by complexity (they include many
components and dependencies), uncertainty (availability of resources and
task durations), dynamic behaviour (changes in the scope of the project,
adding or removing unexpected tasks, re-scheduling processes) and are
inherently heterogeneous (each task may be completed by different
resources or in different geographical locations). In the case of a
multi-project environment, each one of these characters is severely
intensified.
Any project is a complex system with a lot of interconnected tasks,
number of targets and participants. The nature of the project is
characterized as an open system, due to interrelations with internal and
external environments. At the same time it causes interdependencies
among different components of the project in different scales and on
different levels.
Complex systems are never completely predictable, even if the
working principles are known. Managers should be prepared to deal with
the unexpected events that complexity most certainly will bring forth,
and should be able to correct any deviation from the planned course of
action as soon as possible. To achieve this kind of error-based
regulation they should not try to predict or determine the behaviour of
a complex system, but to be prepared for the most probable scenarios. It
will make easier to adapt when things go off-course [1]. Complexity is
an important criterion in selection of an appropriate organisational
form and inputs of the project.
There is hard base that enables to suppose that MP system may be
considered as a complex system. Complex system has multiple interacting
elements whose collective behaviour cannot be simply inferred from the
behaviour of its elements [2]. Therefore, MP system can be similarly
described by the means of complexity theory:
1. Complex systems consist of a large number of elements which
could be simple. A single project consists of a number of tasks;
portfolio consists of a number of projects.
2. The elements interact dynamically by exchanging resources or
information. These interactions are rich. Even if specific elements only
interact with a few others, the effects of these interactions are
propagated throughout the system. It means that the tasks and/or
projects are usually connected via the input/output chain with each
other, and any change of information may affect the whole task and/or
project.
3. The interactions are nonlinear. There is no confidence that a
double change in one project will cause the same change in other
projects [3].
4. There are many direct and indirect feedback loops. The
application of the system dynamics to project management has been
significant, especially in order to understand the feedbacks [4].
5. Complex systems are open systems--they exchange information with
their environment, where all processes are irreversible. Success of a
project depends on endogenous and exogenous factors, such as market
situation with all participants on it, supplier's operability,
contractor's prosperity, fund sources credibility and many others.
6. Complex systems have memory that is not located at a specific
place, but distributed throughout the system. Any complex system thus
has a history, and the history is of cardinal importance to the
behaviour of the system. Under the history in projects we understand an
experience, skills, and action policies of all participants.
7. The behaviour of the system isn't determined by the content
of the components, but by the nature of the interactions. Since the
interactions are rich, dynamic, fed back, and above all, nonlinear, the
behaviour of the system as a whole cannot be predicted from an
inspection of its components. The notion of 'emergence' is
used to describe this aspect. The presence of emergent properties does
not provide an argument against causality, only against purely
deterministic forms of prediction. It supports the
synergy/cannibalization nature in the multi-project (portfolio)
environment [5, 6].
8. Complex systems are adaptive. They can (re)organize their
internal structure without the intervention of an external context.
Principles of adaptive management are strongly endorsed and actively
used in many industries, such as information technology and
environmental protection.
Definitely, all these properties may exist or not in the system and
may affect it in a different manner. But few of them appear to be very
important in terms of validation of any scientific approach to studying
multi-project environment. They are: dynamic exchange in an open system
and nonlinearity.
There are several traditional approaches to modelling in dynamic
multi-project environment with respect to above discussed complexity
properties:
1. Discrete event (linear feedback modelling) and continuous
simulation (Simulink) [7].
2. Markov chains (sequence of random variables corresponding to the
system state; transition matrices) [8].
3. System dynamics (top-down view, feedback loops, etc.) [9, 10].
4. Agent-based modelling (autonomous rule-based agents) [11].
This research covers the overview of various complexity types and
measures. The fractal idea is applied and transformed into a framework
for production planning in MPM environment.
1.2. Theory of fractals in project management
Usually fractal is considered as geometric concept introducing the
quantity fractal dimension or the concept of self-similarity [12].
Fractal is a model of the modular component used to design, implement,
deploy and reconfigure any project context. It has a hierarchical
structure, and put an emphasis on reflexivity in order to support
adaptation and reconfiguration. It has to be more and more adaptive and
must perform reconfigurations in reaction to changes in its environment.
Indeed, when additional ideas or requirements appear during the project
portfolio implementation, new tasks or even projects are created in
order to adapt to changed environment.
Any project consists of at least one task, which includes one
operation or procedure (transportation, welding, machining, etc.). When
a project contains a single operation it is possible to magnify the
scope and scale of this operation in order to receive a number of
various tasks (sub-tasks) in it.
The use of fractal approach has been applied in a number of
different contexts: manufacturing, physics, biology, artificial
intelligence, and etc. [13-15]. The key to the project-based fractal
enterprise is establishing client-server relationships between an
"ends-manager" who manages projects and a
"means-manager" who ensures the resource usages as scheduled
while maximizing resource utilization over time (in an open market
economy) [16]. The fractal enterprise idea is the most appealing one
from the standpoint of the management tasks modelling since
self-organizing and self-optimizing unit characteristics allow to
differentiate goal management from resource management in the network of
SMEs.
1.3. Entropy theory of project management
The "entropy theory of project management" approach is
based upon analogies with the discipline of statistical thermodynamics.
This is an emergent theory of project management. The primary objective
is to reduce the inherent chaos and uncertainty associated with every
lifecycle stage of the project, by the transformation of information
into highly structured (i.e., low entropy) products or services.
Multi-project entropy is presented as follows. Each organization
has a limited amount of the liability that it can undertake. The entropy
helps a project manager to calculate the total amount of the uncertainty
for all the projects running in his company.
[FIGURE 1 OMITTED]
Project A may be in states ([A.sub.1], [A.sub.2], ..., [A.sub.n])
with probabilities ([p.sub.1], [p.sub.2], ..., [p.sub.n]) respectively.
Project B can occupy states ([B.sub.1], [B.sub.2], ..., [B.sub.m]) with
probabilities ([q.sub.1], [q.sub.2], ..., [q.sub.m]) respectively. If
the projects are considered as isolated from each other the information
flow, i.e. influences, changes, etc. (designated as arrows) is coming
from the external environment only, without exchanges between project
environments (Fig. 1). In the a) example a system is subject to exchange
only with its environment. In b) example the system is in exchange with
environment and another subsystem.
Projects A and B are then defined by their respective entropies:
H(A) = -[n.summation over (i=1)][p.sub.i][log.sub.2][p.sub.i]; (1)
H(B) = -[m.summation over (j=1)][q.sub.j][log.sub.2][q.sub.j]. (2)
The joint (multi-dimensional) entropy of the Projects A and B is:
H(A,B) = H(A) + H(B) - I(A,B), (3)
where I(A,B) is the average mutual information entropy measures how
knowledge of the value of one random variable reduces the uncertainty
about another:
I(A,B) = -[n.summation over (i=1)][m.summation over
(j=1)][p.sub.i][q.sub.j][log.sub.2]([p.sub.i][q.sub.j]). (4)
According to the second law of thermodynamics, if the system is in
the initial state [[SIGMA].sub.b] then, in the absence of any further
constraint, it will tend to converge to the state [[SIGMA].sub.a].
Clearly, the system is then disorganizing.
A system would be organized mainly because there is creation of
constraints that reduce its informational entropy. In the same way, it
would be self-organizing whenever there is self-creation of constraints.
In other words, the level and the grade of the organization capability
of the system would be directly characterized by the constraints [17].
2. Fractal structure for MPM
Fractal approach organizes the complex system that can be generated
through the iteration and integration of the simple units and the common
control rules. Fractal system possesses some advantageous features:
* Self-similarity (in terms of modality, information, function or
time, etc.).
* Simple, recursive and iterative structure (maybe the most needed
features for multi-project management).
* Adaptability and self-organization (finds popularity in rapid
exchanging highly competing environments).
Fractal approach is based on the assumption that there is a single
activity in the project, which is the smallest and similar part of the
whole project. Based on the same logic an elementary operation within an
activity is a component, which is similar to the entire activity; or
project is similar to the project portfolio (Fig. 2).
Similar feature of these parts (sub-parts, sub-sub, etc) that they
all contain three evolutionary stages: preparation ('Prep'),
realization ('Realization'), and finalization
('Finish'). Therefore we obtain a fractal structure of the
project regardless of its size and type. Square of rectangular is
proportional to the product of parameters N (number of people) and T
(parameters of time).
[FIGURE 2 OMITTED]
Depending on the magnitude of these values we can build a
parametrically scalable picture of a fractal. The underlying notion in
the fractal project (FP) is Effort, E. It could be defined by Eqs. 5 and
6. Constraints are: project time, which is limited by the contracted due
date [T.sub.lim] and resources in use [N.sub.lim]. The latter includes
equipment, machines, and staff. Schematic representation of the fractal
is given in Figs. 3 and 4.
E = NT; (5)
E = W/P, (6)
where W is the project work amount needed for the completion of
project; P is team productivity.
[FIGURE 3 OMITTED]
[FIGURE 4 OMITTED]
Number of simultaneous projects represents a system with properties
of self-organization. Using the proposed fractal approach allows the
manager to direct human resources, approaching the maximum use of their
effort. Principally, the effect of self-organization causes the
existence of synergy:
[E.sub.PR1] + [E.sub.PR2] + [E.sub.PR3] ... [greater than or equal
to] [E.sub.MP], (7)
where [E.sub.PR1], [E.sub.PR2], and [E.sub.PR3] indicate the effort
(which is a function of time and people involved) required to performing
three separate projects; EMP is a total effort in multiproject
realization.
The main part of the fractal, namely Realization takes, as usual,
most of the time from the whole activity. This is the phase, which adds
the value to our project as a whole, and to the goods, in particular.
Other phases, Preparation and Finishing are non-value-added, but they
are necessary in terms of technological and production requirements. The
former involves processes such as parts cleaning, drying, mounting and
others where the detail is involved. The latter includes local
enterprise features (e.g. long logistics chain, no painting chamber,
etc). Therefore, we suppose that ideally all these 0-value processes
should be conjugated (or combined) and proceeded during value-added
processes (Fig. 5).
[FIGURE 5 OMITTED]
3. Algorithm for FP output parameters definition
The project effort and its distribution over time can serve as a
basis for the obtaining of the total number of human actions and their
distribution over time (Fig. 6).
[FIGURE 6 OMITTED]
The basic objective of the proposed fractal approach is to
determine the minimal amount of resources required for the minimal
duration of project. The following algorithm is elaborated for this
purpose (Fig. 7).
[FIGURE 7 OMITTED]
The determination of [N.sub.min] begins with a description of each
project operations. For every operation the main manufacturing,
preparation and finishing time ([T.sub.P], [T.sub.R], [T.sub.F]) must be
defined. For the information processing it necessary to sort the data
based on different parameters, which could be performed in Excel or
Access tables. The realization time [T.sub.R] is used in order to
calculate the resource (machine + operator) utilization.
4. Realization of FP approach
In order to consider the real application of multiple project
management framework the local company has been chosen as a practical
example. The selected company is a small partner of ABB, which is one of
the largest enterprises in Estonia. It specializes in metal
constructions for huge equipment in various industries--forest, mining,
electrics, etc.
The average number of employees in case study company is about
12-14 persons. Two of them are managers; others are welders, metal
cutters, and technicians. There are about 3-4 projects in progress
simultaneously with an average duration of 6 weeks. This case-study
includes 3 projects with a brief description of the specifics of each:
Project 1--Spike rollers (Type A, 34 pcs.); Project 2 --Spike rollers
(Type B, 17 pcs.); Project 3--Stator bars, 72 pcs.
Next step--is sorting by performer, which enables to see how much
work each performer of the project has to do. This data is summarised in
Table 2. From this data could be calculated the amount of work to be
distributed among non-specialized professionals (not working on
machines, i.e., turner, welder, carver). This amount is equal to the sum
of preparation and finishing times. For example, if we require one month
160 hours to completing all three projects, it is evident that there is
no problems in resources besides the CNC machine resource capacity,
since it has 176 working hours.
Visual presentation of workloads in all projects allows the manager
to conveniently distribute the non-value-added operation stages among
general workers Fig. 8.
[FIGURE 8 OMITTED]
[FIGURE 9 OMITTED]
The distribution of effort among the team members is given in Table
3. Notice that 3 general workers were have been added to last row as
well as one person that help "Worker". The total effort added
by 4 workers is 235 (hour/person).
It is possible to build the complete fractal structure for three
projects. The sequence of operations for one project is introduced in
Figs. 10 and 11. There following work-groups are defined: WG1--turning,
WG2--welding, WG3--cutting, WG4--painting, WG5--others.
Fractals visually demonstrate ways of possible combinations of
activities, allow grouping and distribution of concurrent operations
between the simultaneously available resources, and enable to identify
the milestones in switching between different projects and different
stages. Depending on the established technological routing the total
project time may be changed. Duration of a project is limited by a
contract.
[FIGURE 10 OMITTED]
[FIGURE 11 OMITTED]
Naturally, the results of the approach implementation depends on
many factors such as the size and the complexity of projects, capacity
of resources (for machines) and their skills (for human), time limits
and number of projects, and so on. But no result could be achieved
without a proper integration of the FP approach in enterprise engaged in
MP.
5. Self-organization in MPM
The goal of FP approach is to provide general worker involved in
projects the possibilities for deployment of self-organization
capabilities into the MPM. Therefore, a measure of entropy or disorder
may be decreased by involvement of few general workers, who would be
sharing information about available tasks between each other. Of course,
the considerable directing work is performed by a manager [18, 19]. But
case study does not include his contribution to self-organization in the
MPM environment.
The calculation steps for the Project 1, see Table 4:
* No general workers were added in Project 1. Total effort is 405.
Entropy is maximal (but not absolutely, since realizes that it is
impossible).
* One general worker was added. He brings an effort level of the
carver ([E.sub.P] + [E.sub.F]) equalled 11. Calculate entropy, mutual
information and create plot.
* Two general workers were added
Logarithmic measures of different states and their total entropy
are calculated and results are demonstrated in Table 5. Graphical
expression is presented in Fig. 12.
[FIGURE 12 OMITTED]
The total values of self-organization measures in the project are
presented in Table 6 and plot is depicted in Fig. 13.
[FIGURE 13 OMITTED]
To sum up the description of self-organization in the projects
should say that there is no infinite entropy decrease and no limit
points in the mutual information. Hence, one can't expect a
considerable self-organisation growth by adding more general workers to
the project. In current consideration the average number of additional
workers to be added in the projects is 3 persons.
6. Conclusions
The production activities in numerous manufacturing companies
around the world are handled as separate projects. Specifically, the
success of projects performing depends on skills and techniques used by
the project manager. In the current research the new approach for
maximisation of existing resources utilization within a separate
manufacturing facility in the MPM environment was considered. The
Fractal approach was used for this purpose. It includes several methods
for calculation purposes, which are based on characteristics of complex
systems, such as entropy, self-organization, and adaptability. Moreover,
and more importantly, this approach is a novel way of thinking, fresh
point of view on processes within an enterprise.
In the case study, it was verified that the use of fractal approach
reduces the total production time, which enabled to add additional
project to existing multi-project portfolio and to decrease the total
cost of multi-project for 15%. The advantages are as follows: better
distribution of activity's main processes, higher productivity of
the qualified workers (welders, turners, etc.), and improved utilization
of machines during the value-added process. Entropy theory allows to
measure uncertainty and complexity in managing projects.
The more information is available, the better is picture received
about projects that will be implemented.
Acknowledgements
We would like to thank the Estonian Science Foundation for the
targeted financing scheme grant ETF9460.
References
[1.] Gershenson, C.; Heylighen, F. 2001. How can we think complex?
In: Richardson, Kurt (ed.), Managing Organizational Complexity:
Philosophy; Theory and Application 1: 47-62.
[2.] Smith, J.B. A 2003. Technical report on complex systems,
Villanova University, USA.
[3.] Richardson, K. 2005. Managing organizational complexity:
philosophy, theory and application, Information Age, 301-311.
[4.] Lyneis, J.M.; Ford, D.N. 2007. System dynamics applied to
project management: a survey, assessment, and directions for future
research, System Dynamics Review 23(2-3): 157-189.
http://dx.doi.org/10.1002/sdr.377.
[5.] Evaristo, R.; van Fenema, P.C. 1999. A typology of project
management: emergence and the evolution of new forms, Int. J. Proj.
Manag. 17(5): 271-281. http://dx.doi.org/10.1016/S0263-7863(98)00041-6.
[6.] McDermott, C.M.; O'Connor, G.C. 2002. Managing radical
innovation: an overview of emergent strategy issues, J. Prod. Innov.
Manag 19(2): 424-438. http://dx.doi.org/10.1016/S0737-6782(02)00174-1.
[7.] Majak, J.; Pohlak, M. 2010. Decomposition method for solving
optimal material orientation problems, Composite Structures 92(8):
1839-1845. http://dx.doi.org/10.1016/j.compstruct.2010.01.015.
[8.] Kulkarni, V.G.; Adlakha, V.G. 1986. Markov and
Markov-regenerative pert networks, Oper. Res. 34: 769-781.
http://dx.doi.org/10.1287/opre.34.5.769.
[9.] Abdel-Hamid, T.K. 1993. A multi-project perspective of
single-project dynamics, J. Syst. Soft. 22(3): 151-165.
http://dx.doi.org/10.1016/0164-1212(93)90107-9.
[10.] Kavadias, S.; Loch, C. 2003. Optimal project sequencing with
recourse at a scarce resource, J. Prod. Oper. Manag. 12(4): 433-444.
http://dx.doi.org/10.1111/j.1937-5956.2003.tb00213.x.
[11.] Shevtshenko, E.; Kuttner, R.; Karaulova, T. 2006. Using of
Multi-Agents in Intelligent Decision Support System for Collaborative
SME-s, In: NordPLM'06, 123-134.
[12.] Takayasu, H. 1990. Fractals in the Physical Sciences,
Manchester University Press, Manchester, 170 p.
[13.] Polyantchikov, I.; Shevtshenko, E.; Kramarenko, S. 2010.
Fractal management approach for the manufacturing projects in the
collaborative networks of SME-s. Journal of Machine Engineering 9(4):
81-93.
[14.] Ramanathan, Y. 2005. Fractal architecture for the adaptive
complex enterprise, Communications of ACM 48(5): 51-67.
http://dx.doi.org/10.1145/1060710.1060739.
[15.] Ryu, K.; Jung, M. 2003. Fractal approach to managing
intelligent enterprises, Creating Knowledge Based Organisations, In:
Gupta and Sharma (Eds.), Idea Group Publishers, 312-348.
[16.] Canavesio, M.; Martinez, E. 2007. Enterprise modeling of a
project-oriented fractal company for SMEs networking, Computers in
Industry 58(8-9): 794-813.
http://dx.doi.org/10.1016/j.compind.2007.02.005.
[17.] Jumarie, G. 2000. Maximum Entropy, Information without
Probability and Complex Fractals, Kluwer Academic Publishers, Dordrecht.
http://dx.doi.org/10.1007/978-94-015-9496-7.
[18.] Karaulova, T.; Kostina, M.; Sahno, J. 2012. Framework of
reliability estimation for manufacturing processes, Mechanika 18(6):
713-720. http://dx.doi.Org/10.5755/j01.mech.I8.6.3168.
[19.] Kramarenko, S.; Shevtshenko, E. 2009. Decision support system
for multi-project cash-flow management, Annals of DAAAM For 2009 &
the 20th International DAAAM Symposium Book Series: Annals of DAAAM and
Proceedings, 20: 1111-1112.
Received December 06, 2013
Accepted May 30, 2014
T. Karaulova *, I. Poljantshikov **, E. Shevtshenko ***, S.
Kramarenko ****
* Tallinn University of Technology, Ehitajate tee 5, 19086 Tallinn,
Estonia, E-mail: tatjana.karaulova@ttu.ee
** OU Densel Baltic, Silikaltsiidi 8 str., 11216, Tallinn, Estonia,
E-mail: igor.polyantchikov@denselbaltic.ee
*** Tallinn University of Technology, Ehitajate tee 5, 19086
Tallinn, Estonia, E-mail: eduard.sevtsenko@ttu.ee
**** ANK Technology OU Kurekivi 3/Gaasi tee 1, 75312, Harjuma,
Estonia, E-mail: sergei@anktec.eu
cross ref http://dx.doi.org/10.5755/j01.mech.20.3.6755
Table 1
Basic parameters of projects
Project Order Activities Performer Time, hours TOTAL
1
TP TR TF
P1 1 Cutting Tubes Carver 4 16 1 21
P1 2 Cutting Shafts Carver 4 22 1 27
P1 3 Cutting Plates Carver 4 16 1 21
P1 4 Machining Turner 2 24 2 28
Tubes
P1 5 Machining Turner 2 24 2 28
Shafts
P1 6 Machining Turner 2 28 2 32
Plates
P1 7 Welding Plat- welder 8 42 2 52
Tub-Shafts
P1 8 Welding Surface welder 4 16 2 22
P1 9 Welding Spikes welder 4 16 2 22
P1 10 Machining Turner 2 18 2 22
roller end
P1 11 Assembling Worker 6 16 2 24
P1 12 Painting Painter 4 36 2 42
P1 13 Greasing Worker 2 18 2 22
P1 14 Packing Worker 4 32 2 38
P1 15 Delivery Manager 2 6 0 8
Project Activities Performer TP TR TF TOTAL
2
P2 1 Cutting Tubes Carver 2 8 1 11
P2 2 Cutting Shafts Carver 2 12 1 15
P2 3 Cutting Plates Carver 2 8 1 11
P2 4 Machining Turner 2 12 1 15
Tubes
P2 5 Machining Turner 2 12 1 15
Shafts
P2 6 Machining Turner 2 14 1 17
Plates
P2 7 Welding Plat- welder 4 20 1 25
Tub-Shafts
P2 8 Welding Surface welder 2 8 1 11
P2 9 Welding Spikes welder 2 8 1 11
P2 10 Machining Turner 1 8 1 10
roller end
P2 11 Assembling Worker 3 8 1 12
P2 12 Painting Painter 2 18 1 21
P2 13 Greasing Worker 1 10 1 12
P2 14 Packing Worker 2 16 1 19
P2 15 Delivery Manager 2 4 0 6
Project Activities Performer TP TR TF TOTAL
3
P3 1 Cutting of Carver 2 15 1 18
Materials
P3 2 Sharp edge Carver 1 2 1 4
carping
P3 3 Drilling Turner 2 16 1 19
P3 4 Milling Turner 2 20 2 24
P3 5 Sand Painter 1 4 1 6
blasting
P3 6 Sharp edge Carver 1 2 1 4
removing
P3 7 Assembling Worker 2 8 2 12
P3 8 Packing Worker 2 4 1 7
P3 9 Delivery Manager 2 6 0 8
Table 2 Sorted parameters of the projects
Sum of Realization
Performer Project 1 Project 2 Project 3 Grand Total
Carver 54 28 19 101
Manager 6 4 6 16
Painter 36 18 4 58
Turner 94 46 36 176
Welder 74 36 110
Worker 66 34 12 112
Grand Total 330 166 77 573
Sum of Preparation
Performer Project 1 Project 2 Project 3 Grand Total
Carver 8 12 4 24
Manager 2 2 2 6
Painter 4 4 1 9
Turner 8 8 4 20
Welder 16 16 32
Worker 12 12 4 28
Grand Total 50 54 15 119
Sum of Finishing
Performer Project 1 Project 2 Project 3 Grand Total
Carver 3 3 3 9
Manager 0 0 0 0
Painter 2 2 1 5
Turner 8 8 3 19
Welder 6 6 12
Worker 6 6 3 15
Grand Total 25 25 10 60
Table 3 Effort distribution among the team
members
Performer Effort Persons Time
Carver 101 2 50.5
Manager 16 1 16
Painter 58 1 58
Turner 176 2 88
Welder 110 2 55
Worker 112 2 56
General worker 179 3 60
TOTAL 752 13
Table 4
Efforts in Project 1
Carver Turner Welder Worker Remained
effort
No workers -- -- -- -- 405
General worker 11 -- -- -- 394
General worker 11 16 -- -- 378
General worker 11 16 22 -- 356
General worker 11 16 22 18 338
Shared Remained Shared
effort effort, % effort, %
No workers 0 100.0 0
General worker 11 97.2 2.8
General worker 27 92.9 7.1
General worker 49 86.2 13.8
General worker 67 80.2 19.8
Table 5
Self-organization in Project 1
(remained) log I Self-
* (shared) (remained) * (remained * organization
log(shared) shared) (H-I)
0.000 -- -- --
0.027 -5.203 0.141 0.039
0.066 -3.914 0.260 0.093
0.119 -3.075 0.365 0.167
0.159 -2.654 0.422 0.225
Table 6 Self-organization in three projects
Number of Project 1 Project 2 Project 3
state
Nobody is added 1 0 0 0
Carver + worker 2 0.038781 0.095434 0.107178
Turner + worker 3 0.09338 0.196654 0.212512
Welder + worker 4 0.167051 0.319341 0.212512
Worker + worker 5 0.225271 0.399081 0.306378