Comparison of schedule delay and causal factors between traditional and green construction projects.
Hwang, Bon Gang ; Leong, Lay Peng
Table 1. Factors causing project schedule delays
Authors
List of Factors Male (1988)
Project Project delivery methods V
related Project cost
factors Speed of decision making V
involving all project teams
Communication/coordination V
between key parties
Disputes/conflicts between
key parties
Client Speed of decision making
related by client
factors Delay in progress payment
by client
Client's level of experience V
in the construction
industry
Client initiated variation V
of works
Design team Mistakes and delay in V
related producing design
factors documents
Level of design team V
experience
Complexity in project
design
Misunderstanding of V
client's requirements
by design team
Consultant Delay in performing
related inspection and testing
factors Delay in approving major
changes in the scope
of works
Time for reviewing and
approval of design
documents by consultants
Conflict between consultants
and design engineers
Level of experience of
consultants
Contractor Poor site management and V
related supervision
factors Contractor's deficiencies in
planning and updating
schedule plans
Difficulties in financing
project by contractors
Construction methods
implemented by contractors
Rework due to defects during
construction
Labor Shortage of labor
related Low labor productivity
factors Unskilled labor
Equipment/ Equipment breakdown
material Unskilled operators
related Low productivity and
factors efficiency of equipment
Lack of high technology V
mechanical equipment
Availability of material
Changes in materials
during construction
Imported materials
External Unforeseen ground V
factors conditions
Unfavourable weather
condition on
construction activities
Accidents during
construction
Changes in government
regulations and law
Delay in performing final,
inspection and
certification by
third party
Delay in obtaining permits V
from political units/body
of officials
Authors
List of Factors Mansfield et
al. (1994)
Project Project delivery methods
related Project cost V
factors Speed of decision making
involving all project teams
Communication/coordination V
between key parties
Disputes/conflicts between
key parties
Client Speed of decision making
related by client
factors Delay in progress payment
by client
Client's level of experience
in the construction
industry
Client initiated variation
of works
Design team Mistakes and delay in V
related producing design
factors documents
Level of design team
experience
Complexity in project
design
Misunderstanding of
client's requirements
by design team
Consultant Delay in performing V
related inspection and testing
factors Delay in approving major V
changes in the scope
of works
Time for reviewing and
approval of design
documents by consultants
Conflict between consultants
and design engineers
Level of experience of
consultants
Contractor Poor site management and
related supervision
factors Contractor's deficiencies in
planning and updating
schedule plans
Difficulties in financing V
project by contractors
Construction methods V
implemented by contractors
Rework due to defects during V
construction
Labor Shortage of labor
related Low labor productivity
factors Unskilled labor
Equipment/ Equipment breakdown
material Unskilled operators
related Low productivity and
factors efficiency of equipment
Lack of high technology
mechanical equipment
Availability of material V
Changes in materials
during construction
Imported materials V
External Unforeseen ground V
factors conditions
Unfavourable weather V
condition on
construction activities
Accidents during
construction
Changes in government
regulations and law
Delay in performing final,
inspection and
certification by
third party
Delay in obtaining permits
from political units/body
of officials
Authors
List of Factors Chan, Kumaraswamy
(1996)
Project Project delivery methods
related Project cost V
factors Speed of decision making V
involving all project teams
Communication/coordination V
between key parties
Disputes/conflicts between V
key parties
Client Speed of decision making
related by client
factors Delay in progress payment
by client
Client's level of experience
in the construction
industry
Client initiated variation V
of works
Design team Mistakes and delay in V
related producing design
factors documents
Level of design team V
experience
Complexity in project V
design
Misunderstanding of
client's requirements
by design team
Consultant Delay in performing V
related inspection and testing
factors Delay in approving major
changes in the scope
of works
Time for reviewing and V
approval of design
documents by consultants
Conflict between consultants
and design engineers
Level of experience of
consultants
Contractor Poor site management and V
related supervision
factors Contractor's deficiencies in V
planning and updating
schedule plans
Difficulties in financing
project by contractors
Construction methods
implemented by contractors
Rework due to defects during
construction
Labor Shortage of labor V
related Low labor productivity V
factors Unskilled labor V
Equipment/ Equipment breakdown V
material Unskilled operators
related Low productivity and V
factors efficiency of equipment
Lack of high technology
mechanical equipment
Availability of material V
Changes in materials V
during construction
Imported materials
External Unforeseen ground V
factors conditions
Unfavourable weather
condition on
construction activities
Accidents during
construction
Changes in government
regulations and law
Delay in performing final,
inspection and
certification by
third party
Delay in obtaining permits
from political units/body
of officials
Authors
List of Factors Majid, McCaffer
(1998)
Project Project delivery methods
related Project cost
factors Speed of decision making
involving all project teams
Communication/coordination
between key parties
Disputes/conflicts between
key parties
Client Speed of decision making
related by client
factors Delay in progress payment V
by client
Client's level of experience V
in the construction
industry
Client initiated variation
of works
Design team Mistakes and delay in
related producing design
factors documents
Level of design team
experience
Complexity in project
design
Misunderstanding of
client's requirements
by design team
Consultant Delay in performing
related inspection and testing
factors Delay in approving major
changes in the scope
of works
Time for reviewing and
approval of design
documents by consultants
Conflict between consultants
and design engineers
Level of experience of
consultants
Contractor Poor site management and
related supervision
factors Contractor's deficiencies in
planning and updating
schedule plans
Difficulties in financing
project by contractors
Construction methods
implemented by contractors
Rework due to defects during
construction
Labor Shortage of labor
related Low labor productivity
factors Unskilled labor V
Equipment/ Equipment breakdown V
material Unskilled operators
related Low productivity and
factors efficiency of equipment
Lack of high technology
mechanical equipment
Availability of material
Changes in materials
during construction
Imported materials
External Unforeseen ground
factors conditions
Unfavourable weather
condition on
construction activities
Accidents during
construction
Changes in government
regulations and law
Delay in performing final,
inspection and
certification by
third party
Delay in obtaining permits
from political units/body
of officials
Authors
List of Factors Assaf et. al
(2006)
Project Project delivery methods V
related Project cost
factors Speed of decision making
involving all project teams
Communication/coordination
between key parties
Disputes/conflicts between V
key parties
Client Speed of decision making V
related by client
factors Delay in progress payment V
by client
Client's level of experience
in the construction
industry
Client initiated variation V
of works
Design team Mistakes and delay in V
related producing design
factors documents
Level of design team V
experience
Complexity in project V
design
Misunderstanding of V
client's requirements
by design team
Consultant Delay in performing V
related inspection and testing
factors Delay in approving major V
changes in the scope
of works
Time for reviewing and V
approval of design
documents by consultants
Conflict between consultants V
and design engineers
Level of experience of V
consultants
Contractor Poor site management and V
related supervision
factors Contractor's deficiencies in V
planning and updating
schedule plans
Difficulties in financing V
project by contractors
Construction methods V
implemented by contractors
Rework due to defects during V
construction
Labor Shortage of labor V
related Low labor productivity V
factors Unskilled labor
Equipment/ Equipment breakdown V
material Unskilled operators V
related Low productivity and V
factors efficiency of equipment
Lack of high technology V
mechanical equipment
Availability of material V
Changes in materials V
during construction
Imported materials
External Unforeseen ground V
factors conditions
Unfavourable weather V
condition on
construction activities
Accidents during V
construction
Changes in government V
regulations and law
Delay in performing final, V
inspection and
certification by
third party
Delay in obtaining permits V
from political units/body
of officials
Authors
List of Factors Alaghbari
et al. (2007)
Project Project delivery methods
related Project cost
factors Speed of decision making
involving all project teams
Communication/coordination
between key parties
Disputes/conflicts between
key parties
Client Speed of decision making
related by client
factors Delay in progress payment
by client
Client's level of experience
in the construction
industry
Client initiated variation
of works
Design team Mistakes and delay in
related producing design
factors documents
Level of design team
experience
Complexity in project
design
Misunderstanding of
client's requirements
by design team
Consultant Delay in performing
related inspection and testing
factors Delay in approving major
changes in the scope
of works
Time for reviewing and
approval of design
documents by consultants
Conflict between consultants
and design engineers
Level of experience of V
consultants
Contractor Poor site management and
related supervision
factors Contractor's deficiencies in
planning and updating
schedule plans
Difficulties in financing V
project by contractors
Construction methods
implemented by contractors
Rework due to defects during V
construction
Labor Shortage of labor
related Low labor productivity
factors Unskilled labor V
Equipment/ Equipment breakdown
material Unskilled operators
related Low productivity and
factors efficiency of equipment
Lack of high technology
mechanical equipment
Availability of material V
Changes in materials
during construction
Imported materials
External Unforeseen ground
factors conditions
Unfavourable weather
condition on
construction activities
Accidents during
construction
Changes in government V
regulations and law
Delay in performing final,
inspection and
certification by
third party
Delay in obtaining permits
from political units/body
of officials
Authors
List of Factors El-Razek et
al. (2008)
Project Project delivery methods
related Project cost V
factors Speed of decision making
involving all project teams
Communication/coordination V
between key parties
Disputes/conflicts between
key parties
Client Speed of decision making V
related by client
factors Delay in progress payment V
by client
Client's level of experience
in the construction
industry
Client initiated variation V
of works
Design team Mistakes and delay in V
related producing design
factors documents
Level of design team
experience
Complexity in project
design
Misunderstanding of
client's requirements
by design team
Consultant Delay in performing V
related inspection and testing
factors Delay in approving major V
changes in the scope
of works
Time for reviewing and
approval of design
documents by consultants
Conflict between consultants
and design engineers
Level of experience of
consultants
Contractor Poor site management and
related supervision
factors Contractor's deficiencies in V
planning and updating
schedule plans
Difficulties in financing
project by contractors
Construction methods
implemented by contractors
Rework due to defects during V
construction
Labor Shortage of labor
related Low labor productivity V
factors Unskilled labor
Equipment/ Equipment breakdown
material Unskilled operators V
related Low productivity and V
factors efficiency of equipment
Lack of high technology
mechanical equipment
Availability of material V
Changes in materials V
during construction
Imported materials
External Unforeseen ground V
factors conditions
Unfavourable weather V
condition on
construction activities
Accidents during V
construction
Changes in government
regulations and law
Delay in performing final,
inspection and
certification by
third party
Delay in obtaining permits V
from political units/body
of officials
Table 2. Profile of companies and respondents
Years of experience
Characteristics 1 to 2 years 2 to 3 years
C.I G C.I
Company Construction 0 2 0
Consulting 0 0 0
Development 0 0 0
Quantity Surveying 0 0 0
Total 0 (0%) 2 (6.67%) 0 (0%)
Respondent Project Manager/ 0 3 0
Construction Manager
Project Director/ 0 0 0
Higher Management
Project Personnel 0 0 0
Total 0 (0%) 3 (10%) 0 (0%)
Years of experience
Characteristics 2 to 3 years 3 to 4 years
G C.I
Company Construction 3 0
Consulting 0 0
Development 0 0
Quantity Surveying 0 0
Total 3 (10%) 0%
Respondent Project Manager/ 3 0
Construction Manager
Project Director/ 1 0
Higher Management
Project Personnel 1 1
Total 5 (16.67%) 1 (3.33%)
Years of experience
Characteristics 3 to 4 years >4 years
G C.I
Company Construction 4 18
Consulting 1 5
Development 1 3
Quantity Surveying 0 4
Total 6 (20%) 30 (100%)
Respondent Project Manager/ 5 18
Construction Manager
Project Director/ 3 4
Higher Management
Project Personnel 2 7
Total 10 (33.33%) 29 (96.67%)
Years of experience
>4 years Total
Characteristics (N = 30)
G
Company Construction 9 18 (60%)
Consulting 4 5 (16.67%)
Development 2 3 (10%)
Quantity Surveying 4 4 (13.33%)
Total 20 (63.33%) 30 (100%)
Respondent Project Manager/ 7 18 (60%)
Construction Manager
Project Director/ 0 4 (13.33%)
Higher Management
Project Personnel 5 8 (26.67%)
Total 12 (40%) 30 (100%)
C.I refers to years of experience in construction industry;
G refers to years of experience in green building construction;
Higher Management includes Executive president, Project
Director, General Manager and Managing Director;
Project Personnel includes Project Engineers,
Construction Engineers, and Quantity Surveyors.
Table 3. Project delay: traditional vs. green building projects
Characteristics (a) No. of (b) No. of
Traditional Projects
Projects Delayed
Performed among (a)
Project Type Commercial 48 12
Residential 91 9
Educational 81 14
Project Nature New Construction 184 32
Addition & Alteration 36 3
Project Size Less than $5M 32 4
$5M to less than $10M 6 0
$10M to less than $20M 35 5
$20M to less than $30M 33 0
$30M to less than $40M 15 1
$40M to less than $50M 27 4
$50M and Above 72 21
All Projects 220 35
Characteristics Percentage (c) No. of
Delayed Green
Projects
Performed
Project Type Commercial 25.00% 28
Residential 9.89% 21
Educational 17.28% 47
Project Nature New Construction 17.39% 93
Addition & Alteration 8.33% 3
Project Size Less than $5M 12.50% 3
$5M to less than $10M 0.00% 8
$10M to less than $20M 14.29% 6
$20M to less than $30M 0.00% 13
$30M to less than $40M 6.67% 16
$40M to less than $50M 14.81% 18
$50M and Above 29.17% 32
All Projects 15.91% 96
Characteristics (d) No. of Percentage
Projects Delayed
Delayed
among (c)
Project Type Commercial 16 57.14%
Residential 0 0.00%
Educational 15 31.91%
Project Nature New Construction 31 33.33%
Addition & Alteration 0 0.00%
Project Size Less than $5M 1 33.33%
$5M to less than $10M 2 25.00%
$10M to less than $20M 0 0.00%
$20M to less than $30M 3 23.08%
$30M to less than $40M 5 31.25%
$40M to less than $50M 7 38.89%
$50M and Above 13 40.63%
All Projects 31 32.29%
Table 4. Delay factors: traditional vs. green building projects
Within
Categories
Factors Traditional
Mean
Project P1 Project delivery methods 4.03
related P2 Project cost 4.03
factors P3 Speed of decision making 4.53
involving all project teams
P4 Communication/coordination 4.57
between key parties
P5 Disputes/conflicts between 3.17
key parties
Client CL1 Speed of decision making by client 4.53
related CL2 Delay in progress payment by client 4.07
factors CL3 Client's level of experience in 4.43
the construction industry
CL4 Client initiated variation 3.80
of works
Design DT1 Mistakes and delay in producing 4.47
team design documents
related DT2 Level of design team experience 4.03
factors DT3 Complexity in project design 4.13
DT4 Misunderstanding of client's 4.00
requirements by design team
Consultant CS1 Delay in performing inspection 4.13
related and testing
factors CS2 Delay in approving major changes 4.47
in the scope of works
CS3 Time for reviewing and approval of 4.60
design documents by consultants
CS4 Conflict between consultants and 4.17
design engineers
CS5 Level of experience of consultants 4.43
Contractor CO1 Poor site management and supervision 4.20
related CO2 Contractor's deficiencies in planning 4.20
factors and updating schedule plans
CO3 Difficulties in financing project 4.40
by contractors
CO4 Construction methods implemented 3.93
by contractors
CO5 Rework due to defects during 3.27
construction
Labor L1 Shortage of labor 4.13
related L2 Low labor productivity 3.63
factors L3 Unskilled labor 3.50
Equipment/ EM1 Equipment breakdown 3.40
material EM2 Unskilled operators 3.27
related EM3 Low productivity and efficiency 3.57
factors of equipment
EM4 Lack of high technology 3.60
mechanical equipment
EM5 Availability of material 3.63
EM6 Changes in materials during 3.83
construction
EM7 Imported materials 4.03
External E1 Unforeseen ground conditions 3.67
factors E2 Unfavourable weather condition 3.50
on construction activities
E3 Accidents during construction 3.97
E4 Changes in government regulations 3.73
and law
E5 Delay in performing final inspection 3.80
and certification by third party
E6 Delay in obtaining permits from 4.40
political units/body of officials
Within Categories
Traditional Green Spearman
Rank
Rank Mean Rank Correlation P-value
Coefficient
Project P1 3 4.30 3 0.895 0.040
related P2 4 4.30 4
factors P3 2 4.77 1
P4 1 4.70 2
P5 5 3.47 5
Client CL1 1 5.00 1 1.000 0.000
related CL2 3 4.17 3
factors CL3 2 4.67 2
CL4 4 4.13 4
Design DT1 1 4.27 3 0.400 0.600
team DT2 3 4.63 1
related DT3 2 4.53 2
factors DT4 4 4.17 4
Consultant CS1 5 4.00 5 0.700 0.188
related CS2 2 4.57 3
factors CS3 1 4.63 2
CS4 4 4.43 4
CS5 3 4.70 1
Contractor CO1 3 4.53 2 0.975 0.005
related CO2 2 4.47 3
factors CO3 1 4.70 1
CO4 4 4.27 4
CO5 5 3.43 5
Labor L1 1 4.10 1 1.000 0.000
related L2 2 3.67 2
factors L3 3 3.57 3
Equipment/ EM1 6 3.37 7 0.685 0.090
material EM2 7 3.53 4
related EM3 5 3.50 5
factors EM4 4 3.37 6
EM5 3 4.17 2
EM6 2 4.07 3
EM7 1 4.33 1
External E1 5 3.53 5 0.943 0.095
factors E2 6 3.37 6
E3 2 4.13 2
E4 4 3.90 3
E5 3 3.87 4
E6 1 4.47 1
Cross Categories
Traditional Green Spearman
Rank
Overall Overall Correlation
Rank Rank Coefficient P-value
Project P1 18 16
related P2 18 16
factors P3 3 2
P4 2 3
P5 39 35
Client CL1 3 1
related CL2 17 20
factors CL3 7 6
CL4 26 23
Design DT1 5 18
team DT2 18 7
related DT3 14 10
factors DT4 22 20
Consultant CS1 14 27
related CS2 5 9
factors CS3 1 7
CS4 13 14
CS5 7 3
Contractor CO1 11 10 0.913 0.000
related CO2 11 12
factors CO3 9 3
CO4 24 18
CO5 37 36
Labor L1 14 25
related L2 30 30
factors L3 34 31
Equipment/ EM1 36 37
material EM2 37 32
related EM3 33 34
factors EM4 32 37
EM5 30 20
EM6 25 26
EM7 18 15
External E1 29 32
factors E2 34 37
E3 23 23
E4 28 28
E5 26 29
E6 9 12
Table 5. Solutions for improving green building project
schedule performance
Solutions for Schedule Frequency of Percentage Rank
Improvement of Green Top 5 Selected
Buildings
Ensure that the actual 23 76.67% 1
construction schedule and
resources are seriously
monitored and reviewed so
that the performance is in
line with as planned to
avoid the chances of cost
overrun and disputes
Check for mistakes and 19 63.33% 2
discrepancies in design
documents to avoid redoing
of designs and drawing
before submission for
approval to avoid
variations or
necessary corrections
Alternative procurement 16 53.33% 3
method should be analysed
to ensure it meets the
project requirements
and complexity
Ensure that design 14 46.67% 4
documents are produced
on time
Ensure that there is 14 46.67% 5
optimum number of labours
to be assigned for
individual activities
and motivate the workers
to increase productivity
Pay progress payment to the 12 40.00% 6
contractor timely to
facilitate the contractors'
ability to finance the work
To minimize variation 11 36.67% 7
orders to avoid delays
Contractor should manage his 7 23.33% 8
financial resources and plan
cash flow by utilizing
progress payment
Avoid delay in when reviewing 6 20.00% 9
and approval of documents,
materials or others are needed
Ensure that contractor have 4 13.33% 10
the capability and the
resources for constructing
the project before awarding
the tender
Administrative and technical 4 13.33% 11
staff should be appointed as
soon as project is awarded to
facilitate the project is
completed within specified
time with the required
quality and estimated cost
Consultants should not delay 3 10.00% 12
the checking, reviewing and
approving of design documents
leading to a delay in
construction phase
Consultant should be flexible 3 10.00% 13
in evaluating contractors work
and balance between the
required quality with cost
Contractor should carry out 3 10.00% 14
a comprehensive economic
analysis and workable
financial plans