Elements of pavement management system: case study/Dangu valdymo sistemos elementai: taikymo pavyzdys/Seguma vadibas sistemas elementi: gadijuma izpete/Katete korrashoiu susteemi (PMS) elemendid: juhtumianaluus.
Zofka, Adam ; Josen, Ramandeep ; Paliukaite, Migle 等
1. Introduction
Intensive pavement construction around the world has created a very
large road network that needs to be constantly maintained and preserved
to fulfill its socioeconomic role. Road maintenance is a general term
used for the set of activities that has the following overall goals:
1. provide and maintain serviceable roadways to ensure positive
social experience,
2. ensure cost-effectiveness by extending pavement life and
3. mitigate environmental footprint.
Road maintenance includes both preventive maintenance and
rehabilitation activities. They should be a part of well-defined
strategy that comprises appropriate maintenance methods and strategies
applied in specific climate conditions in order to address certain
distresses under administrative and budgetary constraints (Hicks et al.
1997; Moya et al. 2011; Shahin, Walther 1990).
One of the crucial aspects of the road maintenance is the proper
timing (Peshkin et al. 2004). The key is to apply a method/strategy when
the pavement is still in relatively sound condition with no structural
damage. Numerous research projects show that performing preventive
maintenance repairs at the optimal time provides the most sustainable
approach to the maintenance of roads. As a consequence, many countries
have implemented preventive maintenance programs into their strategies
to help them maintain their road network. However, the problem is that
the road maintenance process is a multi-objective issue that depends on
many factors, such as country development level, labour costs,
user-delay costs, vehicle-operation costs, traffic level and vehicle
type distribution, climate conditions, present road conditions,
construction quality, local experience, etc. There is no single model
that would fit in every situation, but that should not prevent agencies
from implementing a well-defined road maintenance system since its
already proven benefits far outweigh the implementation costs and
obstacles.
In more general terms, Pavement Management System (PMS) can be
viewed as a well-defined and transparent process of planning and
executing maintenance of a pavement network aimed to minimizing budget
expenditures and environmental impact while maximizing pavement life and
user safety. While the PMS can be implemented and structured in various
ways, it typically comprises the electronic inventory of the existing
pavement network together with the corresponding information on its
current and historical performance, traffic loadings, as well as
construction and maintenance history (Fig. 1). Based on this
information, pavement condition prediction models can be created and
assigned to the network pavement uniform segments (Braga, Cygas 2002;
Saliminejad, Gharaibeh 2012; Sivilevicius, Petkevicius 2002). When these
predictions are combined with the specific treatment policies, the PMS
optimizes the extend and timing of the repairs using various algorithms,
such as prioritization, enumeration, linear-, non-linear- and dynamic
programming, genetic algorithm etc. (Abaza, Ashur 1999; Camahan et al.
1987; Gao et al. 2012; Harvey 2012; Manik et al. 2008; Marzouk et al.
2012; Mbwana, Turnquist 1996). The constant pavement evaluation improves
performance predictions via the feedback loop (Fig. 1) and allows for
creating more precise planning scenarios. As mentioned before, the
modern and sustainable approach to maintaining a pavement network is to
keep as many roads as possible above fair condition, while minimizing
the number of roads in a poor condition.
There are three pavement performance indicators which are typically
used in the PMS at a network level. The first and most simple method
involves driving a van at a constant speed over network roads to
calculate and obtain the roughness (IRI) of the pavement. Based on how
the suspension of the vehicle behaves with respect to the distortions of
the road, a certain roughness value is calculated and stored in very
short incremental lengths. Although this value does not give a road
agency any exact distress which may be occurring, it does provide the
agency with the estimate of the ride quality currently being experienced
by citizens on the network. This is also one of the most universal
measurements currently, since most agencies worldwide can use the same
technology and get comparable results. On the other spectrum of the
performance indicators are the deflection measurements, nowadays
obtained in an automated fashion either by the Falling Weight
Deflectometer (FWD) or Traffic Speed Deflectometer (TSD). These
measurements allows for the non-destructive evaluation of the bearing
capacity of a pavement structure. Deflections can be implemented into
the PMS through standardized measured deflections or they can be a part
of a standalone or combined condition index, for example the Structural
Adequacy Index (SAI) and the Pavement Quality Index (PQI), respectively.
Deflections can be also included in the maintenance and rehabilitation
(M&R) decision process, for example as a screening tool for
homogenous pavement segments or they can be implemented into
deterioration models in order to increase their prediction accuracy.
Lastly, pavement performance distresses are obtained by the specialized
equipment mounted on vehicles as they travel over the network. This
method typically allows determining physical surface distresses, such as
rutting or cracking. This information when properly stored and processed
allows agencies to have very detailed pavement condition understanding
throughout the network.
[FIGURE 1 OMITTED]
In this paper, aforementioned elements of the PMS were developed
and presented. Subsequently they led to the development of the
performance models at a network-level based on three pavement
performance indicators: longitudinal cracking, transverse cracking, and
the IRI combined into a Pavement Condition Index (PCI). Next, pavement
families were created which had similar characteristics with respect to
their pavement type, traffic, climate, and structure. For the entire
network, 32 different performance families were created. A decay
function was then created to quantify the different rates at which each
family is deteriorating. Once this was finalized, different sequences of
treatment options were created and different management scenarios were
applied to all segments in the network. In the final step, the
simulation was conducted for the 20-year period and different scenarios
were compared in terms of their net present values (NPV).
2. Elements of Pavement Management System
Due to several data sources with different data formats, a great
effort was made to merge different records correctly and to check the
quality of the processed data before the analysis. Processed data which
constitutes the fundamental elements of every PMS can be grouped in
three main categories, i.e. pavement inventory and related historical
data, traffic data and finally historical climatic data (Fig. 2).
2.1. Inventory
Several units within the Connecticut Department of Transportation
(ConnDOT) provided pavement-related data.
The data is comprised of five main elements: traffic, pavement type
and structure, pavement age since last resurfacing project, and pavement
performance data. Average Daily Traffic (ADT) was obtained as geospatial
vector data with respect to state routes. This format allowed for
geospatial manipulation of climate and traffic data which was a key step
in the initial phase of this study. Age of the top asphalt layer since
the last resurfacing project as well as pavement type (flexible vs.
composite) was determined by exploring historical maintenance and
construction project files.
Transverse and longitudinal cracking at 5 m increments throughout
the entire state was collected in 2010 by the Automatic Road ANalyzer
(ARAN) van. The van provided high-quality laser-scan images that were
next processed by Wisecrax[c] software by ConnDOT personnel. This
software outputs linear meters of transverse and longitudinal cracking
at three severity levels with respect to five different zones across the
width of the pavement lane to allow for more in depth analysis.
In order to create a Pavement Management System in this study, the
network needed to be well defined and organized. All road segments were
initially split into uniform sections based on similar characteristics
on pavement type, total thickness, and traffic volumes, resulting in 13
505 segments which cover a length of 5250 km of state roads. All
segments which had pavement types which were not either asphalt concrete
or composite were removed. Since two separate ARAN vans with different
imaging technologies were used in the collection process, only data from
the newer van was used in this study. Furthermore, a filter was used to
eliminate all segments which were less than 150 m. At the end, a total
of 5581 segments were eliminated translating to 2208 km that had been
filmed by the older van, and 3854 segments totalling 216 km were
eliminated for being less than 150 m. This left the usable dataset to be
4070 segments totalling 2816 km, or approx 54% of the entire state
network. The segments lengths ranged from 151 m to 7500 m with the
average value of 687 m and the median value of 452 m (Fig. 3). Fig. 4
below shows a spatial representation of segments used in the study
(darker in red), as well as segments which were eliminated (lighter in
grey).
2.2. Climatic data
Climatic data was providing several factors potentially affecting
the considered pavement segments. In order to obtain detailed yet
accurate data, three high quality sources were queried: National
Climatic Data Center (NCDC), Quality Controlled Local Climatological
Data (QCLCD) and Local Climatological Data (LCD). These services allow
for selection of specific climatic elements from stations around
Connecticut. In total, 19 stations across Connecticut were identified
with daily weather data going back a minimum of 10 years. Based on the
collected data, specific weather indices were calculated as shown in
Table 1. A weighted surface interpolation was applied to weather indices
from surrounding weather stations to each individual segment. This was
done by locating the three closest weather stations to the
segment's midpoint and interpolating the index value from all
three, giving the closest weather station the most weight. Two overall
climatic indices, each with three levels, were created in order to
assess the impact of cold and hot temperatures in the analysis. Table 1
shows the indices used with regard to both climates. It should be noted
that climatic indices were determined for each segment individually
taking into consideration only the period since the last resurfacing
project.
[FIGURE 2 OMITTED]
[FIGURE 3 OMITTED]
[FIGURE 4 OMITTED]
[FIGURE 5 OMITTED]
All indices have been arranged so that the higher the level is, the
more significantly the region is considered either cold or hot.
Histograms were then created of the averaged levels for both hot and
cold climate index averages for all segments. For example, if a segment
was in Level 1 for Absolute Min Temp., Level 2 for No. of Days <
-18[degrees]C, and Level 1 for Avg. Winter Temp., its overall cold
climate average index would be 1.33 which is an average of those three
levels. Once the histograms were completed for each climate, two groups
were created based off the histogram to distinguish segments which
experienced more significant climatic impact. After creating the two
groups from the histograms, it was seen that the western part of the
state experienced less cold weather and more hot weather, whereas the
central part of the state experienced colder and less hot climates. It
should be also mentioned that other weather-related composite indices
can be created, e.g. the number of passes through zero 0[degrees]C.
3. Current PCI
A vital step for any PMS is to construct a way to index the
condition of all pavements within the network. In this case, a PCI was
created incorporating the three pavement performance indicators used in
the study: longitudinal and transverse cracking as well as IRI. For both
longitudinal and transverse cracking, ASTM D6433-11 "Standard
Practice for Roads and Parking Lots Pavement Condition Index
Surveys" was employed to calculate the number of deduct points to
use based on cracking density in meters using the medium severity level.
Since IRI is not a distress and therefore not listed in the ASTM
D6433-11 standard, deduct points were computed using a correlation
equation developed in the study by Park et al. (2007). Once deduct
points were computed for all three indicators, they were summed and used
with the ASTM D6433-11 total deduct point chart for n = 3, which outputs
a single PCI deduction value based on the considered distresses. This
procedure was repeated for all 4070 segments and a resultant histogram
of the PCI for all segments considered in this network is shown in Fig.
5. It should be mentioned that these values represent the baseline
network condition as of 2010.
4. Categorical family grouping and model assignment
All 4070 segments were categorized into families which shared
attributes. Since each segment will deteriorate differently over time,
this step is done to determine a different decay coefficient for each
family type. Pavement families were created throughout the entire
network based on five attributes and since each attribute had two
levels, 32 families were created ([2.sup.5] = 32). Table 2 shows five
attributes and their levels. Interpolated climatic index averages were
used for both cold and hot climates as shown in Table 1. It should be
mentioned that selected attributes and resultant families represent only
one of many possible approaches. While several other assignments were
also checked it was found that presented 32 families produced the most
balanced dataset that lead to reliable PCI prediction equations for all
families.
After assigning each pavement segment to a family, plots of
pavement age vs. PCI were created. The minimum number of segments
assigned to a family was 18 and the maximum was 462. Using the
least-squares approach the following exponential decay function was
created to fit each family separately:
PCI = 100 x [e.sup.-age/[alpha]], (1)
where [alpha]--decay parameter varying for each family (ranged from
16.57 to 46.21); age--time since the last reconstruction project, in
years.
It should be noted that the decay function could have been
represented by other algebraic function, i.e. polynomial, logarithmic,
linear etc. While considering an appropriate function several factors
were taken into account, such as the number of segments per family, age
range within each family, and the number of function parameters. Power
function was found to be the most robust and appropriate for this study,
but it should be only considered as an example application.
5. Pavement management approach and implementation
The management approach used in this paper was to keep as many
pavement segments above certain PCI thresholds as possible. In the case
of segments which were well below this threshold level at the baseline
year, i.e. beginning of 20-year simulation, they were set to deteriorate
until they reached the reconstruction level. This is a reasonable modern
day approach since many departments face significant budgetary
constraints. If the entire budget is spent attempting to fix the poor
condition roads, only a handful of roads will be fixed and all the
pavements which are in fair condition will deteriorate further in the
short-term future. This typically leads to an increase of poor condition
roads over time and puts the department in a significant budgetary
backlog.
The treatments used in the paper are common maintenance procedures
identified in the relevant literature. The life expectancy of the
treatments depends on two primary characteristics: condition of the
pavement being treated, and traffic volume. The life extension (L.E.)
for treatments is split based on the pavement condition being good,
fair, or poor. The values obtained for typical life expectancy and cost
per one-mile (1600 m) and 9 m wide pavement section were selected from
the literature review and are shown in Table 3 (Gao et al. 2012;
Geoffroy 1996; Peshkin et al. 2004; Smith, Peshkin 2011). Since the
pavement will deteriorate at a faster rate after each treatment is
applied, a reduction value was created for each treatment to increase
the alpha parameter depending on the quality of treatment (see Eq (1)).
This reduction in alpha parameter was empirically assumed but it can be
verified with a larger database of pavement maintenance activities.
[FIGURE 6 OMITTED]
In order to simplify the maintenance approach for such a large
network, six treatment sequences were created based on common practices
and treatment constraints. Each segment was assigned to a specific
treatment sequence based on the baseline PCI value and traffic volume.
Once the sequence was established, all steps were performed sequentially
each time the PCI reached the starting trigger shown in Table 4. Fig. 5
shows a sample plot of a segment in the network which falls under
Sequence #3 (Table 4), and Scenario #2 to keep the PCI above 60.
Comparatively, if nothing was done to the segment, it can be seen that
it would reach the reconstruction PCI threshold of 35 merely 17 years
into its life. Table 4 displays the six different treatment sequences
along with their selection constraints using treatment options in Table
3.
[FIGURE 7 OMITTED]
In order to determine which sequence to use, both PCI and traffic
were used as primary decision makers, as shown in the flowchart in Fig.
8.
6. Pavement management scenarios
Four different management scenarios were used in this study in
order to demonstrate the changes in pavement condition over time, as
well as associated costs. The fours scenarios were: "Do Nothing for
20 years", PCI threshold at 60, PCI threshold at 70, and PCI
threshold at 80. These scenarios were used to determine the advantages
and disadvantages of keeping the pavement condition of the network at a
high level and obtaining the most significant lifetime extensions from
the treatments. All four scenarios were tested for a simulation period
of 20 years. Since a treatment L.E. is not a "fixed" number
and it depends on many factors, this study used a stochastic approach.
Random lifetime extensions were computed in each simulation iteration
based on the appropriate L.E. range from Table 3. In total, 25
iterations of the entire network of 4070 segments were done for each of
the four scenarios. In order to compare the difference in pavement
conditions between the scenarios, the following PCI brackets were
assumed:
--good condition, pavement segments with PCI > 70;
--fair condition, pavement segments with 50 [less than or equal to]
PCI [less than or equal to] 70;
--poor condition, pavement segments with PCI < 50.
[FIGURE 8 OMITTED]
The estimated cost was calculated depending on the simulation year
in which the treatment occurs in order to incorporate the future cost
correctly. This was done for all segments and the total annual cost for
maintaining the network at the threshold level was calculated. Next, the
pavement condition throughout the simulation period was observed after
incorporating the treatments done each year.
Scenario #1--Do Nothing
This scenario was done initially to assess what would happen if
nothing was done to the pavement network for the next 20 years. This is
a management approach for considering the worst case scenario and the
resulting outcomes to both the pavement condition as well as the overall
costs. The condition change of the segments over time is shown in Fig.
9. Nearly all segments would be in poor condition at the end of
simulation period and they would require the most significant, and
costly treatment. For this scenario, treatments were selected based
solely on PCI and ADT of segments after 20 years of simulation. Nearly
all segments needed to be reconstructed and were assigned to either
Full-depth Cold in Place Recycling or Reconstruction (Sequence #5 and #6
from Table 4).
[FIGURE 9 OMITTED]
Scenario #2--Keep PCI above 60
The next scenario was to simulate the next 20 years by keeping the
PCI above 60. This was done by using PCI = 60 in the constraint
equations in Table 4 and assigned specific treatment scenarios for each
segment in the network based off this threshold. Once treatment
scenarios were assigned, the simulation began for 20 years and once the
PCI fell below 60, the following step in the sequence was triggered. In
this scenario, random values from the L.E. Fair column were used from
Table 3 for the 25 iterations. Fig. 7 shows the different treatment
steps in the sequence being triggered once the pavement falls below the
threshold. Fig. 9 shows the pavement condition over time for this
scenario using the same condition grouping of good, fair, and poor as
discussed in the previous scenario. The vast improvement between this
scenario and the previous is evident with only minimal segments
achieving a poor condition over time and most maintaining at least fair
condition.
Scenario #3--Keep PCI above 70
The biggest difference between this scenario and the previous of
keeping PCI above 60 is the improvement of lifetime extension of
treatments. Since the PCI threshold is increased to 70, the treatments
will occur on pavements which are considered to be in relatively good
condition. For this scenario L.E. good extensions from Table 3 were
used. Also, the alpha value reductions shown in Table 3 were cut in half
assuming that the decay rate will not increase as much when treating a
good condition pavement. Fig. 9 shows the pavement condition for this
scenario. There is a noticeable increase in the number of good condition
segments compared to the previous scenario.
Scenario #4--Keep PCI above 80
The last scenario done was to analyse how keeping the PCI above 80
would affect the costs and condition of the network. Although the
reality of keeping the condition of a network at such a high level is
unlikely due to limitations in resources, it is done to allow for
comparative analysis. This scenario also uses the lifetime extensions in
the L.E. good column of Table 3, however generates a random number from
the top half of the range. For example, chip sealing has an extension
between 6 and 10 years in the L.E. good column, but only the top half of
the range was used for this scenario making the range between 8 and 10
years. Alpha reductions were treated the same as Scenario #3. It is seen
in Fig. 9 that the condition of the network when simulated for 20 years
consists of nearly all good condition segments.
7. Pavement management cost analysis
In order to fully assess the different scenarios, a cost analysis
must be done to put valuation with respect to the pavement condition. It
can be seen from the previous section that naturally a highway
department would prefer to use Scenario #4 to keep the PCI threshold
high and the network in good condition assuming availability of
resources. For each scenario presented in the previous section the cost
of the treatments was recorded based on the year in which they occurred.
The inflation rate of 2.7% was used to adjust the cost to future years.
Fig. 10 shows the comparison in annual costs for the Scenarios 2, 3, and
4. Scenario 1 was not included in this Fig. because it only has a single
cost at year 20.
[FIGURE 10 OMITTED]
[FIGURE 11 OMITTED]
Initially the highest costs are associated with Scenario #4 (PCI
> 80), since most segments in the network need to be initially
treated to go above the threshold value. Afterwards however, the costs
associated with this scenario outperform both Scenario #2 and 3 since
the extension of the treatments last longer and the number of required
treatments decrease. Scenario #3 also follows a similar trend but to a
much lesser extent. Although the initial costs are much higher than
Scenario #2, it doesn't provide reduced costs later on in
simulation years like Scenario #4 does. However, since it maintains a
higher level of condition than Scenario #1, it should still be
considered a better alternative. Unlike the others, Scenario #1 starts
off with very low costs for treatments, since most segments are above
this threshold and waiting to trigger for their first treatment. Since
the L.E. for the treatments is less the other scenarios, the demand for
more treatments occurs at a higher frequency resulting in higher costs
as the simulation periods increases.
To further investigate the lifetime costs, a comparison was done to
evaluate the differences between the Net Present Value (NPV) costs for
all four scenarios again with error bars representing three standard
deviations from the 25 iterative runs, shown in Fig. 11. Scenario #1 has
the most expensive NPV associated with it since the pavement decays and
the most expensive treatments are required after 20 years. Scenarios 2,
3, and 4 all have fairly similar values, however there is an appealing
trend showing a decrease in cost when a higher PCI threshold is used.
This is primarily due to longer life extensions which may end up
avoiding the later and more expensive steps in the treatment sequences.
8. Conclusions
1. Scenario #1 for doing nothing for 20 years shows the importance
in maintaining road networks frequently, as nearly all segments in the
network deteriorated to poor condition in this time. The cost associated
with repairing the network after nothing was done after 20 years far
surpassed the other scenarios.
2. Scenario #2 had low costs initially since many segments were
above the pavement condition index threshold of 60. However the life
extension of treatments was lower since the treatments were being done
on fair condition pavements and resulted in more frequent repairs and
higher costs than both Scenario #3 and Scenario #4.
3. Both Scenario #3 and Scenario #4 kept the condition of the
network at remarkable high levels; however, the cost analysis supported
the use of Scenario #4. If a highway department has enough capital and
resources to support the high initial costs and extensive workload of
these scenarios, they would be rewarded with longer treatment
extensions, less frequent applications, and less cost in future years.
4. Scenario #1 Do Nothing is about two times more expensive
according to Net Present Value than Scenario #4.
5. It should be noted that the elements of pavement management
system presented in this paper were created with significant assumptions
that could affect above observations. In the mature system most of these
assumptions should be verified based on the historical data of
maintenance activities. The main purpose of the paper is to demonstrate
the pavement management process and stochastic approach to the life
extension of treatments and their implication on the net present values
of different scenarios.
Caption: Fig. 1. Implementation steps of the PMS
Caption: Fig. 2. Study flowchart
Caption: Fig. 3. Distribution of 4070 segment lengths
Caption: Fig. 4. Network dataset elimination
Caption: Fig. 5. Baseline pavement condition of network (as of
2010)
Caption: Fig. 6. Alpha parameter and the number of segments per
family
Caption: Fig. 7. Sample segment treatment sequence (sequence
threshold: PCI = 60, reconstruction threshold: PCI = 35)
Caption: Fig. 8. Sequence decision flowchart
Caption: Fig. 9. PCI condition simulations
Caption: Fig. 10. Annual costs for Scenarios #2, #3, and #4
Caption: Fig. 11. Net present value for all scenarios
doi:10.3846/bjrbe.2014.01
Received 28 October 2013; accepted 3 February 2014
Acknowledgements
Authors would like to thank the ConnDOT for providing the raw data
necessary for this study. However, the ConnDOT or any other government
or private organization did not support this study in any other way, and
all findings are solely based on authors' observations. Also,
authors would like to thank Dr. Mo Y. Shahin for his invaluable
contributions to the area of pavement management.
References
Abaza, K.; Ashur, S. 1999. Optimum Decision Policy for Management
of Pavement Maintenance and Rehabilitation, Transportation Research
Record 1655: 8-15. http://dx.doi.org/10.3141/1655-02
Braga, A.; Cygas, D. 2002. Adaptation of Pavement Deterioration
Models to Lithuanian Automobile Roads, Journal of Civil Engineering and
Management 8(3): 214-220.
http://dx.doi.org/10.1080/13923730.2002.10531279
Camahan, J. V.; Davis, W. J.; Shahin, M. Y.; Keane, P. L.; Wu, M.
I. 1987. Optimal Maintenance Decisions for Pavement Management, Journal
of Transportation Engineering 113(5): 554-572.
http://dx.doi.org/10.1061/(ASCE)0733-947X(1987)113:5(554)
Gao, L.; Xie, C.; Zhang, Z. 2012. Network-Level Road Pavement
Maintenance and Rehabilitation Scheduling for Optimal Performance
Improvement and Budget Utilization, Computer-Aided Civil and
Infrastructure Engineering 27(4): 276-287.
http://dx.doi.org/10.1111/j.1467-8667.2011.00733.x
Geoffroy, D. N. 1996. Cost-Effective Preventive Pavement
Maintenance. NCHRP Synthesis of Highway Practice 223: Transportation
Research Board, National Research Council.
Harvey, M. O. 2012. Optimizing Road Maintenance. Discussion Paper
No. 2012-12, OECD, International Transport Forum.
Hicks, R. G.; Dunn, K.; Moulthrop, J. 1997. Framework for Selective
Effective Preventive Maintenance Treatments for Flexible Pavements,
Transportation Research Record 1597: 54-65.
http://dx.doi.org/10.3141/1597-01
Marzouk, K.; Awad, E.; El-Said, M. 2012. An Integrated Tool for
Optimizing Rehabilitation Programs of Highways Pavement, The Baltic
Journal of Road and Bridge Engineering 7(4): 297-304.
http://dx.doi.org/10.3846/bjrbe.2012.39
Manik, A.; Gopalakrishnan, K.; Singh, A.; Yan, S. 2008. Neural
Networks Surrogate Models for Simulating Payment Risk in Pavement
Construction, Journal of Civil Engineering and Management 14(4):
235-240. http://dx.doi.org/10.3846/1392-3730.2008.14.22
Mbwana, J. R.; Turnquist, M. A. 1996. Optimization Modeling for
Enhanced Network-Level Pavement Management System, Transportation
Research Record 1524: 76-85. http://dx.doi.org/10.3141/1524-09
Moya, M; Gallego, E.; Garcia, A. I.; Ayuga F. 2011. A Proposed
Methodology for the Management of Low-Volume Roads in Spain, The Baltic
Journal of Road and Bridge Engineering 6(3): 153-162.
http://dx.doi.org/10.3846/bjrbe.2011.20
Park, K.; Thomas, N.; Lee, W 2007. Applicability of the
International Roughness Index as a Predictor of Asphalt Pavement
Condition, Journal of Transportation Engineering 133(12): 706-709.
http://dx.doi.org/10.1061/(ASCE)0733-947X(2007)133:12(706)
Peshkin, D. G.; Hoerner T. E.; Zimmerman, K. A. 2004. Optimal
Timing of Pavement Preventive Maintenance Treatment Applications. NCHRP
Report 523. Transportation Research Board, National Research Council.
Saliminejad, S.; Gharaibeh, N. G. 2012. A Spatial-Bayesian
Technique for Imputing Pavement Network Repair Data, Computer-Aided
Civil and Infrastructure Engineering 27(8): 594-607.
http://dx.doi.org/10.1111/j.1467-8667.2012.00762.x
Shahin, M. Y.; Walther, J. A. 1990. Pavement Maintenance Management
for Roads and Streets Using the PAVER System. USACERL Technical Report
M-90-05.
Sivilevicius, H.; Petkevicius, K. 2002. Regularities of Defect
Development in the Asphalt Concrete Road Pavements, Journal of Civil
Engineering and Management 8(3): 206-213.
http://dx.doi.org/10.1080/13923730.2002.10531278
Smith, K.; Peshkin, D. 2011. Pavement Preservation on High-Traffic
Volume Roadways, Transportation Research Record 2235: 54-65.
http://dx.doi.org/10.3141/2235-07
Adam Zofka (1)([mail]), Ramandeep Josen (2), Migle Paliukaite (3),
Audrius Vaitkus (4), Tomasz Mechowski (5), Maciej Maliszewski (6)
(1,5,6) Road and Bridge Research Institute, ul. Instytutowa 1,
Warszawa, 03-302 Poland
(2) Fay, Spofford & Thorndike, Inc., 5 Burlington Woods Dr,
Burlington, MA 01803, USA
(3,4) Road Research Institute, Vilnius Gediminas Technical
University, Linkmenu str. 28, 08217 Vilnius, Lithuania
E-mails: (1) azofka@ibdim.edu.pl; (2) rjosen@fstinc.com; (3)
migle.paliukaite@vgtu.lt; (4) audrius.vaitkus@vgtu.lt; (5)
tmechowski@ibdim.edu.pl; (6) MMaliszewski@ibdim.edu.pl
Table 1. Index ranges used for interpolating cold and hot climate
regions
Cold Climate
Index Level 1 Level 2 Level 3
Absolute Min Temp. [degrees]C <-20, ...> (-23, -20) <..., -23>
No. of Days < -18[degrees]C <0, 4> (4, 10) <10, ...>
Avg. Winter Temp. [degrees]C <-5, ...> (-7, -5) <..., -7>
Hot Climate
Index Level 1 Level 2 Level 3
Absolute Max Temp. [degrees]C <..., 36> (36, 38) <38, ...>
No. of Days > 95[degrees]F <0, 5> (5, 10) <15, ...>
Avg. Summer Temp. [degrees]C <..., 26> (26, 28) <28, ...>
Table 2. Categorical binning of pavement families
Cold climate Hot climate Traffic volume,
index avg. index avg. vpd
Level 1 Average Average <80 000
Level 2 Colder Warmer >80 000
Total pavement Pavement type
thickness, cm
Level 1 <25 Flexible
Level 2 >25 Composite
Table 3. Pavement treatments with associated costs
Treatment L.E. good L.E. fair L.E. poor
Crack Seal/Fill 2 to 7 years 2 to 5 years 1 to 4 years
Chip Seal 6 to 10 years 4 to 6 years 2 to 4 years
Double Chip Seal 7 to 12 years 5 to 7 years 3 to 5 years
Microsurfacing 7 to 12 years 5 to 7 years 3 to 6 years
Thin Overlay 8 to 11 years 6 to 9 years 3 to 7 years
Thin Mill/ Overlay 10 to 13 years 9 to 11 years 8 to 10 years
Cold in place PCI to 85 PCI to 82.5 PCI to 80
recycling
Reconstruction PCI to 92.5 PCI to 90 PCI to 87.5
Treatment Cost/ mile Alpha
(1.6 km), $ reduction
Crack Seal/Fill 13 200 -3
Chip Seal 30 800 -2
Double Chip Seal 48 400 -1
Microsurfacing 52 800 -1
Thin Overlay 61 600 -1
Thin Mill/ Overlay 74 800 -0.5
Cold in place 96 800 -0.5
recycling
Reconstruction 110 000 -0.5
Table 4. Six treatment sequences
Sequence # Step 1 Step 2
1 Crack seal/Fill Chip seal
2 Crack seal/Fill Double chip seal
3 Crack seal/Fill Microsurfacing
4 Thin mill/ Overlay Crack seal/Fill
5 Cold in place recycling Crack seal/Fill
6 Reconstruction Crack seal/Fill
Sequence # Step 3 Starting triggers
1 Thin overlay At threshold value
2 Thin overlay At threshold value
3 Thin overlay At threshold value
4 Microsurfacing At threshold value -5
5 Microsurfacing At threshold value -20
6 Microsurfacing At threshold value -20