Simulation-based model for optimizing highways resurfacing operations/Imitacinis keliu dangu rekonstrukcijos darbu optimizavimo modelis/Autocelu seguma atjaunosanas optimizacijas imitejosais modelis/Maantee ulekatte paigaldamise simulatsioonil pohinev optimiseerimismudel.
Marzouk, Mohamed ; Fouad, Marwa
1. Introduction
Highway maintenance, especially pavement rehabilitation or
resurfacing, requires lane closures. Given the very substantial cost of
maintenance and the very substantial traffic disruption and safety
hazards associated with highway maintenance work, it is desirable to
plan and manage the work in ways that minimize the combined cost of
maintenance, traffic disruptions and accidents. Work zone delays due to
highway maintenance have been increasing in reconstruction and
maintenance work zone. Highway construction projects are classified as
infrastructure construction projects characterized by long duration,
large budget, and complexity. Resurfacing of highways is executed in
different environmental conditions which raise uncertainties that
influence the production rates of construction resources. These
different conditions includes unusual or complex works, equipment
breakdown, unfavorable weather conditions, and unexpected site
conditions. Several simulation systems have been designed specifically
for construction (Halpin, Riggs 1992; Martinez 1996). These systems use
some form of network based on Activity Cycle Diagrams to represent the
essentials of a model, and employ clock advance and event generation
mechanisms based on Activity Scanning or Three-Phase Activity Scanning.
These systems are designed for both simple (e.g., CYClic Operations
NEtwork (CYCLONE)) and very advanced (e.g., STate and ResOurce Based
Simulation of COnstruction ProcEsses (STROBOSCOPE)) modeling.
Work zones often cause traffic congestion on high volume roads. As
traffic volumes increase so does work zone-related traffic congestion
and so does the public demand for road agencies to decrease both their
number and duration. Negative impacts on road users are minimized by
bundling interventions on several interconnected road sections instead
of treating each road section separately. Negative impacts on road users
are quantified in user costs. The optimum work zone is the one that
results in the minimum overall agency and user costs. The minimization
of these costs is often the goal of corridor planning. In order to
achieve this goal the interventions on each asset type (pavement,
bridges, tunnels, hardware, etc.) must be bundled into optimum packages.
Hajdin and Lindenmann (2007) presented a method that enables road
agencies to determine optimum work zones and intervention packages. The
method allows the consideration of both budget constraints and distance
constraints, including maximum permissible work zone length or minimum
distance between work zones. The mathematical formulation of this
optimization problem is a binary.
Pavements on two-lane two-way highways are usually resurfaced by
closing one lane at a time. Vehicles then travel in the remaining lane
along the work zone, alternating directions within each control cycle.
Several alternatives are evaluated, defined by the number of closed
lanes and fractions of traffic diverted to alternate routes. Chen et al.
(2005) presented an algorithm, referred to as Simulated Annealing for
Uniform Alternatives with a Single Detour (SAUASD), to find the best
single alternative within a resurfacing project. SAUASD is developed to
search through possible mixed alternatives and their diverted fractions,
to minimize total cost, further including agency cost (resurfacing cost
and idling cost) and user cost (user delay cost and accident cost).
Thus, traffic management plans are developed with uniform or mixed
alternatives within a two-lane highway resurfacing project. Several
research efforts have been made in highway maintenance and lane closures
(Jiang et al. 2009; Lee 2009; Lukas, Borrmann 2011; Meng, Weng 2010;
Meng, Weng 2013; Wang et al. 2002; Weng, Meng 2013; Yang et al. 2009).
This paper presents a framework that is dedicated for determining the
optimum length of highway resurfacing work zone. A numerical example is
worked out to demonstrate the essential features of the proposed
framework.
2. Proposed framework
The proposed framework Resurfacing Sim helps contractors in
planning of highway resurfacing operation. The developed framework
performs planning of highways resurfacing operation and selects optimum
length of work zone based on minimum total cost and total duration.
These two functions are performed by two main components--simulation and
optimization modules. Fig. 1 depicts a schematic diagram for the
proposed framework that shows the interaction between its two
components.
3. Simulation module
The developed simulation module captures the sequence of tasks
involved in the resurfacing operation and the relationships between
these tasks. The procedure of designing and building a simulation model
are summarized in six steps as described below.
1. Break-down the operation into main processes and tasks. For each
task, type of resources (i.e., materials, labor, and/or equipment)
involved in its execution is identified.
2. Indicated each type of tasks, either: Normal or Combi depending
on its need of resources.
3. Representing the sequence and relationships between tasks by
using Arcs to map the network.
4. Add more control logical conditions by created control
statements.
5. Using simulation language to code the simulation network and
control statements.
6. Verify the simulation model and test it.
3.1. Modeling of converting traffic flow
Converting traffic flow involves three main processes:
I--laying safety control devices;
II--breaking concrete platform and median;
III--removing waste materials from work zone.
Fig. 2 depicts the elements of the network that capture the
converting traffic flow. Table 1 and Table 2 list the resources, input
parameters, and tasks which are involved in converting traffic flow.
3.2. Modeling reconstruction of semi-rigid paving
Reconstruction of semi-rigid paving involves seven main processes:
I--breaking concrete slab;
II--removing broken concrete;
III--excavating old base layer;
IV--removing old base layer;
V--laying new base layer;
VI--constructing new reinforced concrete slab, and
VII--constructing median.
[FIGURE 1 OMITTED]
[FIGURE 2 OMITTED]
[FIGURE 3 OMITTED]
Table 3 and Table 4 list the resources, input parameters, and tasks
which are involved in reconstruction of semi-rigid paving. Fig. 3
depicts the element of the network that captures the reconstruction of
semi-rigid paving. Similarly, tasks are performed like the manner that
is descripted in converting traffic flow.
3.3. Modeling reconstruction flexible paving and finishing
Reconstruction flexible paving and finishing involves seven main
processes:
I--removing old paving;
II--laying new paving;
III--installing electrical work;
IV--making drainage hole;
V--fixing sign and signal;
VI--repairing joint,
VII--finishing.
Tables 5 and 6 list the resources, input parameters, and tasks
which are involved in reconstruction of flexible paving and finishing.
4. Optimization module
Optimization module utilizes Genetic Algorithms (GAs) (Coley 1999;
Goldberg 1989; Holland 1992) which have been used as a powerful tool for
optimization based on heuristic search techniques following random
sampling. To carry out optimization utilizing Genetic Algorithms, a
population is created and subjected to different GAs' operations
including crossover and mutation. Crossover is utilized to combine
parent chromosomes to produce children chromosomes. Crossover
probability value ranges from zero to one. Usually is given a rate that
ranges from 0.6 to 1. On the other hand, mutation is the process of
altering some genes in a chromosome to ensure the entire state-space is
searched. Mutation leads the population out of local minima. Small
mutation rate (less than 0.1) is usually used (Elbeltagi et al. 2005).
In the presence of multi- and conflicting objectives, a set of optimal
solutions, instead of one optimal solution, are obtained. Multi optimal
solutions exist since there is no one solution is considered as optimal
for multiple conflicting objectives (Deb 2001). This module based on a
biased sharing Non-Dominated Sorting Genetic Algorithm NSGA. The idea
behind NSGA is that a ranking selection method is used to emphasize the
non-dominant points with the aid of sharing function method to maintain
diversity in the population.
4.1. Single-objective optimization
The objective of the work zone optimization problem is to minimize
the total cost for work zone activities. The objective function for work
zone activities is expressed as per Eq (1):
Minimize [C.sub.T] = [C.sub.M] + [C.sub.U], (1)
where: [C.sub.T]--total cost; [C.sub.M]--maintenance cost;
[C.sub.U]--user cost.
Variables that affect maintenance cost ([C.sub.M]) include work
zone length, fixed setup cost, and average maintenance cost per unit
length. Whereas, user cost is affected by work zone length, traffic
volumes, speed, etc. Both [C.sub.M] and [C.sub.U] are functions of work
zone length since [C.sub.M] and [C.sub.U] are significantly influenced
by work zone size. Chien et al. (2002), Chien and Schonfeld (2001)
concluded longer zones tend to increase the user delays, but the
maintenance activities can be performed more efficiently with fewer
repeated setups. Since work zones lengths and maintenance duration
affect maintenance and user cost, it is important to tradeoff between
maintenance cost and user cost in order to minimize total cost.
Maintenance cost usually includes labor cost, equipment cost, material
cost and traffic management cost. The first step in estimating
maintenance cost is to determine construction quantities/unit prices.
Unit prices can be determined from highway agencies historical data on
previously bid jobs of comparable scale (Walls, Smith 1998). In this
study, the cost of maintaining for length L is assumed to be a linear as
per Eq (2):
[C.sub.M] = [Z.sub.1] + [Z.sub.2] L, (2)
where [Z.sub.1]--the fixed cost for setting up a work zone;
[Z.sub.2]--the average additional maintenance cost per work zone unit
length.
The average maintenance cost per lane-km is calculated by dividing
Eq (2) by the zone length L. The components of user cost are user delay
cost and accident cost. The user delay can be classified into queuing
delay and moving delay (Cassidy, Bertini 1999; Chien, Schonfeld 2001;
Schonfeld, Chien 1999). The user delay cost is determined by multiplying
the user delay by the value of user time (Wall 1998). The accident cost
is related to the historical accident rate, delay, work zone
configuration, and average cost per accident. Chien and Schonfeld (2001)
determined accident cost from the number of accidents per 100 mln
vehicle hours multiplied by the product of the user delay and average
cost per accident and then divided by work zone length. The user delay
cost consists of the queuing delay costs due to a one-way traffic
control and the moving delay costs through work zones. The queuing delay
cost [C.sub.q] per maintained lane-km is the total delay per cycle Y in
both directions multiplied by the number of cycles N per maintained
lane-km and the users' value of time v in L.E/vh as per Eq (3):
[C.sub.q] = Y[N.sub.v], (3)
where Y--summation of the delays (e.g., [Y.sub.1] and [Y.sub.2])
incurred by traffic flows from directions 1 and 2 per cycle. [Y.sub.1]
and [Y.sub.2] are derived using deterministic queuing analysis.
The moving delay cost of the traffic flow [Q.sub.1] and [Q.sub.2],
denoted as [C.sub.v], is the cost increment due to the work zone. It is
equal to the flow ([Q.sub.1] + [Q.sub.2]) multiplied by:
1) the average maintenance duration per km ([Z.sub.3]/L +
[Z.sub.4]);
2) the travel time difference over zone length with the work zone
(L/v) and without the work zone (L/[v.sub.0]);
3) the value of time, v.
As such, the delay cost is calculated as per Eq (4):
[C.sub.v] = ([Q.sub.1] + [Q.sub.2]) ([Z.sub.3]/L + [Z.sub.4])(L/v -
L/[v.sub.0])v, (4)
where [v.sub.0]--the speed on the original road without any work
zone, km/h.
The user delay cost ([C.sub.U] is the summation of queue delay cost
([C.sub.q]) and moving delay cost ([C.sub.v]) as per Eq (5):
[C.sub.U] = [C.sub.q] + [C.sub.v]. (5)
The accident cost incurred by the traffic passing the work zone is
determined from the number of accidents per 100 mln vehicle hours
([n.sub.a]) and the average cost per accident ([v.sub.a]) as per Eq (6):
[Ca.sub.q] = ([[C.sub.q]/v] +
[[C.sub.v]/v])([[n.sub.a][v.sub.a]]/[10.sup.8]) (6)
Optimization variables are any entities within studied system,
where any change in this entity would affect the objective function.
Based on interviews with expert engineers and extensive analysis of
resurfacing operation, 6 optimization variables have been identified:
1. Hourly Flow Rate in Direction 1: Number of vehicle in the same
direction with work zone.
2. Hourly flow rate in Direction 2: Number of vehicle in opposite
direction against work zone.
3. Average maintenance time per lane-km: the required duration for
maintenance for each lane per kilometer
4. Work zone length: the optimum length for work zone that
decreases delay in traffic time and decrease accidents.
5. Average work zone speed: speed of vehicle at work zone.
6. Average headway: the time of the distance between two vehicles
as shown in Fig. 4.
A fitness function is a particular type of objective function that
prescribes the optimality of a solution (i.e., a chromosome) in genetic
algorithms so that that particular chromosome is ranked against all the
other chromosomes. Optimal chromosomes, or at least chromosomes which
are more optimal, are allowed to breed and mix their datasets by any of
several techniques, producing a new generation.
4.2. Multi-objective optimization algorithm
The objective of the work zone multi optimization problem is to
minimize the total cost as in single optimization that explained before
and minimize total duration for work zone activities. The objective
function for work zone activities is expressed as per Eq (7):
Minimize [C.sub.T] = [C.sub.M] + [C.sub.U], (7)
Minimize [D.sub.T] = [z.sub.3] + [z.sub.4] L, (8)
where [C.sub.T]--the total cost; [C.sub.M]--the maintenance cost;
[C.sub.U] the user cost; [z.sub.3]--setup time; [z.sub.4]--average
maintenance time per lane-km; L--work zone length in km.
[FIGURE 4 OMITTED]
The same optimization variables of single-objective optimization
are considered in multi-objective optimization. Pareto optimality is
used to determine the set of optimal solutions. A solution is
Pareto-optimal if no other solution improves one objective function
without a simultaneous deterioration of at least one of the other
objectives. A set of such solutions is called the Pareto-optimal front.
5. Numerical example
In order to demonstrate the use of the developed framework in
optimization resurfacing operation of highways for an actual project
example is considered. The example involves a highway (named El-Mehwer)
with a length of 15 km that connects El-Giza Governorate to 6 October
Governorate in Egypt. The values of the considered parameters are listed
in Table 7. The boundaries of optimization parameters are listed in
Table 8. Several experiments have been carried out to test the
performance of the optimization module against different values of
crossover threshold (CO), mutation threshold (m), and number of
generations (G). Table 9 lists the outputs, obtained from the
sensitivity analysis. Fig. 5 shows the change in Total cost at different
mutation and crossover thresholds. The results reveal that solutions are
too sensitive to both crossover and mutation values. For this road, best
solutions for minimum cost are obtained at CO = 0.5 and m = 0.1.
The same example is solved to demonstrate the use of
multi-objective algorithm. Several experiments have been carried out to
test the performance of optimization with respect to project total cost
(LE) and project duration (Dur.) in months against different values of
crossover threshold (CO), mutation threshold (m), considering population
size of 30 chromosomes as per Fig. 6.
[FIGURE 5 OMITTED]
[FIGURE 6 OMITTED]
6. Summary
Repairing highway project is one of the complex projects that are
characterized by repetitive operations, difficult construction
environment, and different construction tools. Such characteristics lead
to uncertainties with respect to estimated duration and repairing cost.
This paper presented a framework that is used for planning of highways
resurfacing using computer simulation and optimization. The proposed
framework is capable to plan required repairing of highways. It aids in
the selection of work zone length that achieves minimum total cost and
total duration. The simulation module is implemented using the Microsoft
Visual basic 6.0 programming language and it utilizes STROBOSCOPE
(general purpose simulation language) as simulation engine. Simulation
module sends the estimated duration for each zone to calculate the total
duration and total cost for repairing highway operation. The total cost
is calculated by summing up the direct cost of resurfacing,
indirect/overheads cost, and the cost of the impact of work zone on
road, which are moving delay cost, queuing delay, and accident cost. Two
genetic algorithms optimization were considered; single-objective
optimization and multi-objective optimization. To demonstrate the
functionality of the proposed framework, a numerical example was worked
out. Sensitivity analysis was performed to test the performance of
optimization with respect to project total cost (LE) and project
duration (Dur.) in months against different values of crossover
threshold (CO ranges from 0.1 to 0.6), mutation threshold (m ranges from
0.02 to 0.2), considering population size of 30 chromosomes.
Caption: Fig. 1. Schematic diagram of proposed framework
Caption: Fig. 2. Converting traffic flow simulation network
Caption: Fig. 3. Reconstruction of semi-rigid paving simulation
network
Caption: Fig. 4. Average headway (H)
Caption: Fig. 5. Total Cost vs. No. of generations: a--different
mutation thresholds (CO = 0.5); b--different crossover thresholds (m =
0.02)
Caption: Fig. 6. Sensitivity analysis results: a--CO = 0.6; b--CO =
0.4; c--CO = 0.2; d--CO = 0.1
doi:10.3846/bjrbe.2014.08
Received 2 August 2011; accepted 23 February 2012
References
Cassidy, M. J.; Bertini, R. L. 1999. Some Traffic Features at
Freeway Bottlenecks, Transportation Research Part B-Methodological
33(1): 25-42. http://dx.doi.org/10.1016/S0191-2615(98)00023-X
Chen, C.-H.; Schonfeld, P.; Paracha, J. 2005. Work Zone
Optimization for Two-Lane Highway Resurfacing Projects with an Alternate
Route, Journal of the Transportation Research Board 1911: 51-66.
http://dx.doi.org/10.3141/1911-06
Chien, S.; Schonfeld, P. 2001. Optimal Work Zone Lengths for
Four-Lane Highways, Journal Transportation Engineering 127(2): 124-131.
http://dx.doi.org/10.1061/(ASCE)0733-947X(2001)127:2(124)
Chien, S.; Tang, Y.; Schonfeld, P. 2002. Optimizing Work Zones for
Two-Lane Highway Maintenance Projects, Journal Transportation
Engineering 128(2): 145-155.
http://dx.doi.org/10.1061/(ASCE)0733-947X(2002)128:2(145)
Coley, D. A. 1999. An Introduction to Genetic Algorithms for
Scientists and Engineers. World Scientific. ISBN 9810236026. 244 p.
Deb, K. 2001. Multi-Objective Optimization Using Evolutionary
Algorithms. 1st edition. Wiley, New York. ISBN 047187339X. 518 p.
Elbeltagi, E.; Hegazy, T.; Grierson, D. 2005. Comparison among Five
Evolutionary-Based Optimization Algorithms, Journal of Advanced
Engineering Informatics 19(1): 43-53.
http://dx.doi.org/10.1016/j.aei.2005.01.004
Goldberg, D. E. 1989. Genetic Algorithms in Search, Optimization
and Machine Learning. 1st edition. Addison-Wesley, Reading, Mass. ISBN
0201157675. 432 p.
Hajdin, R.; Lindenmann, H. P. 2007. Algorithm for the Planning of
Optimum Highway Work Zones, Journal of Infrastructure Systems ASCE
13(3): 202-214. http://dx.doi.org/10.1061/(ASCE)1076-0342(2007)13:3(202)
Halpin, D. W.; Riggs, L. S. 1992. Planning and Analysis of
Construction Operations. John Wiley & Sons, Inc., New York, NY. ISBN
047155510X. 381 p.
Holland, J. H. 1992. Genetic Algorithms, Scientific American:
66-72. http://dx.doi.org/10.1038/scientificamerican0792-66
Jiang, Y.; Chen, H.; Li, S. 2009. Computation of User Costs at
Freeway Work Zones Using Weigh-in-Motion Traffic Data, International
Journal of Construction Education and Research 5(3): 197-219.
http://dx.doi.org/10.1080/15578770903152823
Lee, H. Y. 2009. Optimizing Schedule for Improving the Traffic
Impact of Work Zone on Roads, Automation in Construction 18(8):
http://dx.doi.org/10.1016/j.autcon.2009.05.004
Lukas, K.; Borrmann, A. 2011. Minimizing the Traffic Impact Caused
by Infrastructure Maintenance Using and Colony Optimization, in Proc. of
the 28th International Symposium on Automation and Robotics in
Construction (ISARC 2011). Seoul, Korea.
Martinez, J. C. 1996. Stroboscope State and Resource Based
Simulation of Construction Processes. PhD Thesis. University of
Michigan, USA.
Meng, Q.; Weng, J. 2013. Optimal Subwork Zone Length and Project
Start Time for Short-Term Daytime Work Zones from the Contractor's
Perspective, Transportation Research Part C: Emerging Technologies 29:
72-83. http://dx.doi.org/10.1016/j.trc.2013.01.001
Meng, Q.; Weng, J. 2010. Optimal Subwork Zone Operational Strategy
for Short-Term Work Zone Projects in Four-Lane Two-Way Freeways, Journal
of Advanced Transportation 47(2): 151-169.
http://dx.doi.org/10.1002/atr.153
Schonfeld, P.; Chien, S. 1999. Optimal Work Zone Lengths for
Two-Lane Highways, Journal of Transportation Engineering, ASCE 125(1):
21-29. http://dx.doi.org/10.1061/(ASCE)0733-947X(1999)125:1(21)
Wang, Y.; Cheu, R. L.; Fwa, T. F. 2002. Highway Maintenance
Scheduling Using Genetic Algorithm with Microscopic Traffic Simulation,
in Proc. of the 81st Annual Meeting of the Transportation Research
Board, in CD-ROM, paper No. 02-2174.
Walls, J.; Smith, M. R. 1998. Life Cycle Cost Analysis in Pavement
Design--in Search of Better Investment Decisions. Technical Report No.
FHWA-SA-98-079, Federal Highway Administration, Washington, D.C.
Weng, J.; Meng, Q. 2013. Estimating Capacity and Traffic Delay in
Work Zones: An Overview, Transportation Research Part C: Emerging
Technologies 35: 34-45. http://dx.doi.org/10.1016/j.trc.2013.06.005
Yang, N.; Schonfeld, P.; Kang, M. W. 2009. A Hybrid Methodology for
Freeway Work-Zone Optimization with Time Constraints, Public Works
Management Policy 13(3): 253-264.
http://dx.doi.org/10.1177/1087724X08322843
Mohamed Marzouk (1) ([mail]), Marwa Fouad (2)
Dept of Structural Engineering, Cairo University, Giza 12613, Egypt
E-mails: (1) mm_marzouk@yahoo.com; (2)
eng.marwafouad_2006@yahoo.com
Table 1. Converting traffic flow resources
Type Resources
Labor crews Safety
Equipment Loader--Jack hummer--Trucks
Materials Area of work zone--Volume of waste materials
Table 2. Converting traffic flow tasks
Process Task Description
Laying safety control Safetydevices Distribute safety control
devices devices along work zone
length and after work
zone
Breaking concrete BrkenPlateform Break old platform and
platform and median median
Removing waste materials Load Load trucks with the
from work zone waste material
Haul Move to dump area
Dump Dump the waste in dump
area
Retune Return to site area
Table 3. Reconstruction of semi-rigid paving resources
Type Resources
Labor crews Base layer--Reinforced Bars--Formwork--Casting
median--Fixing median
Equipment Loader--Jack hummer--Trucks
Materials Volume of waste concrete--Volume of waste soil--Base
layer (crushed stone)--Blocks--Water
Table 4. Reconstruction of semi-rigid paving tasks
Process Task Description
Breaking concrete BrokenSlab Break old reinforced concrete
slab slab
Load Load trucks with the broken
concrete
Removing broken Haul Haul to dump area
concrete Dump Dump broken concrete in dump
area
Retune Return of trucks to site
Excavating old base Excavation1 Excavate base layer that is
layer under concrete slab
Removing old base Load2 Load trucks with old base
layer
layer Haul2 Haul to dump area
Dump2 Dump old base layer in dump
area
Retune2 Return of trucks to site
Laying new base Brlaybaselayer Lay new crushed stone layer as
layer a base layer for semi-rigid
paving
Constructing new Formwork Install slab framework
reinforced concrete Reinforcing Place slab reinforcing bars
slab PouringRC Cast of concrete
Curing Cure concrete
Constructing median CastingMedian Cast median blocks
FixingMedian Fix median blocks
Table 5. Reconstruction flexible paving and finishing resources
Type Resources
Labors crews Electric--Drain--Sign--Repairing joint--Painter
Equipment Scraper--Roller
Materials Electric work--Drain hole--Sign--Volume of old
asphalt--Volume of new asphalt--Volume of new asphalt
5 cm--Length of joint--paint
Table 6. Reconstruction flexible paving and finishing tasks
Process Task Description
Removing old paving RmovingoldAsph Removing old layer of
asphalt using scrapers
Laying new paving NewAsphalt1 Laying first layer of new
asphalt that bond between
base and top layers
NewAsphalt2 Laying second layer of new
asphalt that is the top
layer of paving
Installing electrical Electricwork1 Erected the light poles and
work road electrical work
Making drainage hole Draingehole Fixing road drainage holes
Fixing sign and Signandsignal Fixing the different types
signal of sign and electrical
signal that work as a guide
for drivers
Repairing joint Repairjoint Repairing the different
types of joints that exist
on road
Finishing Finishing Making lane limits and
drawings on road using
paint
Table 7. Example input parameters
Parameter Value
Fixed cost for setting up a work zone, ([Z.sub.1]) 80 L.E/Zone
Average additional maintenance cost per 160 L.E/Lane.mm
unit length ([Z.sub.2])
Setup time ([Z.sub.3]) 10 h/Zone
Value of user time (v) 12.7 L.E/veh.h
Speed on the original road ([V.sub.0]) 80 km/h
Number of accidents per 100 million 67
vehicle hours ([n.sub.a]) accident/100 mvh
Average cost per accident ([v.sub.a]) 17.6 L.E/h
Table 8. Limits of optimization parameters
Parameter Min value Max value
[Q.sub.1] 3 000 veh/h 5 000 veh/h
[Q.sub.2] 3 000 veh/h 5 000 veh/h
[Z.sub.4] 10 h/Lane.mm 20 hr/Lane.km
L 1 km 15 km
V 10 km/h 15 km/h
H 2 sec 10 sec
Table 9. Values of optimization parameters for optimum
solution (CO = 0.5 and m = 0.1)
Variable [Q.sub.1] [Q.sub.2] [Z.sub.4]
# Generation 100 50.12 51.27 10.21
# Generation 500 50.09 50.03 10.00
# Generation 1000 50.06 50.03 10.00
Variable L V H
# Generation 100 4.84 14.97 2.01
# Generation 500 4.77 12.70 2.01
# Generation 1000 4.76 12.70 2.01