Analysis of modern three-span suspension bridges with stiff in bending cables/Siuolaikinio triju tarpatramiu kabamojo standzialynio tilto skaiciavimas/Moderna trislaidumu iekarta tilta ar stingiem kabeliem analize/Kaasaegsete kolmeavaliste jaikade kaablitega rippsildade analuus.
Juozapaitis, Algirdas ; Kliukas, Romualdas ; Sandovic, Giedre 等
1. Introduction
Suspension bridges, due to their excellent technical performance,
are widely used for centuries. Efficiency of these composed-structure
bridges is highlighted (distinguished) by the availability to overlap
record spans (Ryall et al. 2000; Troyano 2003; Song, Wang 2010).
Comparison of these bridges with conventional standard bridges shows the
substitution of bending loads with tension loads transferred to the main
carrying element--suspension cable (Gimsing, Georgakis 2012; Gopper et
al. 2005; Katchurin et al. 1971). Cables of modern suspension bridges
are designed using exceptionally strong steel wires. Bending stiffness
of these cables is virtually close to zero. At the same time, the cables
shall be coated with special anticorrosion protection and are rather
complex in terms of construction due to their anchorage and intermediate
connections (Dani?nas, Urbonas 2013; Gimsing, Georgakis 2012; Nakamura,
Suzumura 2009; Xu, Chen 2013; Ryall et al. 2000; Yanaka, Kitagawa 2002).
Such factors induce appreciation of bridge construction and operation.
The main disadvantage of suspension bridges, i.e., the excessive
deformability, is familiar to the designers of suspension bridges or
structures (Horokhov et al. 2006; Jennings 1987; Kiisa et al. 2012). It
is preconditioned not by flexible deformations of carrying suspension
elements (cables) but by kinematic displacements under the impact of
asymmetric or local loads (Kulbach 2007; Sandovi? et al. 2011).
Generally, the initial shape of the suspension bridge could be
stabilized using suspended stiffening girder. This stabilization method
could not be deemed as extremely effective due to the high altitude of
the girder cross-section and, accordingly, the mass required under
particular bridge operation conditions (Grigorjeva et al. 2010; Lewis
2012; Wollman 2001). Various additional structural means enabling
minimization of displacements of kinematic origin could be used as well
(Jennings 1987; Katchurin et al. 1971; Strasky 2005). Some of them are
complicated or ineffective from technical--economical point of view.
Recently, the required rigidity of suspension bridge (minimization
of kinematic displacements) is ensured by the application of the
so-called "rigid" cables instead of conventional flexible
cables (Grigorjeva et al. 2010; Juozapaitis et al. 2006, 2010). These
cables are corrosion-resistant and made of standard hot-rolled or welded
steel cross sections and their factory and fabricated connections are
simple and firm. It simplifies both fabrication and installation of such
elements (Gorokhov et al. 2013).
There are numerous publications presenting the analysis of the
behavior of standard suspension bridges with absolutely flexible
suspension cable (Cobo del Arco, Aparicio 2001; Clemente et al. 2000;
Gimsing, Georgakis 2012; Katchurin et al. 1971; Kim, Thai 2010; Wollman
2001). In particular, the articles describing the analysis of suspension
bridge flexible cables in terms of local bending stresses having
occurred at certain sections shall be mentioned (Caballero, Pose 2010;
Chen et al. 2011; Furst et al. 2001; Gimsing, Georgakis 2012; Prato,
Ceballos 2003; Strasky 2005).
It shall be noted that analysis methods applied for these
innovative three-span suspension bridges with "rigid" cables
are still under development. There are only few individual publications
describing the behaviour of single-span suspension bridge (Grigorjeva et
al. 2010; Juozapaitis et al. 2010). Between them a simplified
engineering method could be mentioned for the analysis of internal
forces and displacements of suspension bridge with "rigid"
cables (Grigorjeva et al. 2010). However, the methodology could not be
deemed as completely accurate. Recently, the internal forces and
displacements of suspension bridge with "rigid" cables are
calculated applying digital techniques (Nevaril, Kytyr 2001; Kala 2012).
Still, the above-mentioned techniques could not provide unexceptional
results of the analysis of modern suspension bridges with
"rigid" cables. Undoubtedly, the analysis of modern suspension
three-span bridges with stiff in bending cables shall be developed.
The article describes the behaviour of suspension multi-span bridge
with "rigid" cables under the impact of symmetric loads,
provides formulas to be applied for calculation of internal forces and
displacements of the aforementioned bridge considering the non-linear
behavior, and deals with analysis method considering the erection
sequence of "rigid" cables.
2. Analysis of suspension three-span bridge with "rigid"
cable
According to the provided, the initial shape of suspension bridges
could be stabilized and displacements minimized by applying the
so-called "rigid" cables with calculated bending stiffness
([E.sub.c][J.sub.c] [not equal] 0) instead of flexible ones. These
"rigid" cables are made of conventional structural steel
sections or complex welded steel cross sections (Grigorjeva et al. 2010;
Juozapaitis et al. 2010). Value of the cable bending strength
[E.sub.c][J.sub.c] shall be selected in accordance with the imposed
loads and operational requirements. It shall be noted that
cross-sectional area of this "rigid" cable is approximately
equal to the cross-sectional area of a flexible cable, and its
application does not increase the mass of carrying structures. On the
contrary, while comparing it with classical bridge (with flexible
cable), total demand for steel could be reduced due to the
"rigid" cable resistance to the impact of asymmetric loads and
"unloading" of the suspended stiffening girder. Thus the cross
section of the girder could be reduced.
One more characteristic property of rigid cable shall be noted.
There are two variants of cable installation. The first one when the
cable is provided with bending stiffness ([E.sub.c][J.sub.c] [not equal
to] 0) in case of both dead load g and temporary load p. The second
method foresees minimization of initial loads applying the bending
stiffness after the bridge erection, i.e. only under the impact of live
loads. This article describes a second method of bridge erection.
The structure of new suspension bridge (with "rigid"
cable) is analogous to that of conventional bridge. Stiffening girders,
pylons and hangers connecting bearing cables and stiffening girders
shall be erected for this type of bridge. Analysis of these new
suspension bridges shall be made applying the same assumptions (Gimsing,
Georgakis 2012; Katchurin et al. 1971; Wollman 2001). First of all, it
is assumed that the height of a stiffening girder remains constant along
the entire bridge ([h.sub.b] = const). Secondly, it is assumed that the
distance between hangers could ensure random distribution of loads
imposed on the cable. Thirdly, it is assumed that the hangers are
absolutely rigid, i.e. the elongation of hangers is disregarded.
Fourthly, it is assumed that rigid cable under the dead load takes the
shape of parabola. This assumption could be used for the second method
of "rigid" cable formation without any exceptions. Still, it
shall be noted that in case of first erection method the
"rigid" cable could be provided both with square parabola
shape and other shape foreseen and described by the designer.
2.1. Initial shape of suspension bridge
Structural and estimated diagrams of considered suspended
three-span bridge with "rigid" cables, stiffening girders,
connection hangers, and pylons are provided in Fig. 1. Stiffening
girders are split, i.e. flexibly connected at the level of intermediate
supports (Fig. 1c). Certainly, high bending loads could be prevented by
applying flexible connection of "rigid" cables and the upper
part of pylons.
According to the aforesaid, the second method of "rigid"
cable formation shall be analyzed, i.e., bearing cable during its
installation will adopt the entire dead load as an absolutely flexible
cable, and after the completion of bridge erection it will behave as
"rigid" cable ([E.sub.c][J.sub.c] [not equal to] 0). In this
case, the bridge loading history will be obvious: the overall dead load
g will be imposed on flexible cable, and live loads p will be
distributed among the stiffening girder ([p.sub.b]) and
"rigid" cable ([p.sub.b]).
Deformation diagram of suspension multi-span bridge under the loads
g and p is shown in Figs 1b, 1c. The bridge shall be conditionally
divided into individual structural elements --cables (1, b) and
stiffening girders (1, c). Mid span (main span) ([l.sub.m]) and side
spans ([l.sub.a]) of the bridge shall be analyzed individually.
[FIGURE 1 OMITTED]
2.1.1. Mid span
Supports of the mid span cable shall be installed at the same
level. The initial shape of flexible cable under the dead load g,
considering the erection sequence, shall be expressed by the following
equilibrium equation:
[H.sub.m0][z.sub.m0]([x.sub.m]) = [M.sub.mg]([x.sub.m]), (1)
where [H.sub.m0]--horizontal component of cable tension under the
load g; [M.sub.mg]([x.sub.m]) =
0.125[gl.sup.2.sub.m](4[x.sub.m]/[l.sub.m] -
4[x.sup.2.sub.m]/[l.sup.2.sub.m])-- moment caused by the dead load g in
the analogous girder, i.e., girder with the equal length of the span;
[z.sub.m0]([x.sub.m]))--initial curve of the cable (square parabola).
Cable straining force at the center of the mid span ([x.sub.m] =
0.5[l.sub.m]) shall be calculated as follows:
[H.sub.m0] = [gl.sup.2.sub.m]/8[f.sub.m0], (2)
where [f.sub.m0]--initial sag of flexible cable.
It shall be repeated that in case of the second suspension bridge
erection sequence, stiffening girders (both of mid span and side spans)
will not adopt the dead load, and the bending moments will be equal to
zero ([M.sub.bg] = 0).
2.1.2. Side spans
Supports of the side span cable shall be installed at different
levels (Fig. 1). These inclined cables under the impact of the dead load
g, considering the erection sequence, will be flexible as well. If the
inclined cables are analyzed applying the global reference system, their
initial shape could be approximately expressed by the analogous
equation:
[H.sub.a0][z.sub.a0]([x.sub.a]) = [M.sub.ag]([x.sub.a]), (3)
where [H.sub.a0]--horizontal component of cable tension under the
load g; [M.sub.ag](x) =
0.125[gl.sup.2.sub.a](4[x.sub.a]/[l.sub.a]--4[x.sup.2.sub.a]/[l.sup.2.sub.a]--moment caused by the dead load g in the analogous girder of a side
span; [z.sub.a0]([x.sub.a])--initial curve of the side span cable.
It shall be highlighted that [z.sub.a0]([x.sub.a]) shall be
calculated from the line connecting the top and the bottom supports
(Fig. 1b). This means that the initial straining force of side cable at
the center of the span ([x.sub.a] = 0.5[l.sub.a]) shall be calculated as
follows:
[H.sub.a0] = [gl.sup.2.sub.a]/[8.sub.a0], (4)
where: [f.sub.a0]--initial sag of flexible cable, calculated from
the line connecting the top and the bottom supports.
Initial tension of the side cable [H.sub.a0] is horizontally
directed (Fig. 1b).
2.2. Selection of geometrical parameters of suspension bridge
The structure of suspension three-span bridge is more complex in
comparison to the single-span suspension bridge. This type of bridge
structure requires the selection of appropriate geometrical parameters
of individual structural span elements in order to eliminate occurrence
of additional vertical and horizontal displacements in case of a dead
load. In other words, it is essential to ensure the appropriate balance
of the entire structural system. For this reason the upper part of
pylons shall meet the following condition:
[H.sub.a0] = [gl.sup.2.sub.a]/8[f.sub.a0] = [H.sub.m0] =
[gl.sup.2.sub.m]/8[f.sub.m0]. (5)
Under the given lengths of main and side spans [l.sub.m] and
[l.sub.a], the following dependency (relation) of the initial sag of mid
and side cables could be discovered:
[f.sub.m0] = [f.sub.a0] [[l.sup.2.sub,m]/[l.sup.2.sub.a]. (6)
Bridge engineering practice describes the most frequent length of
side spans as the half of the mid one ([l.sub.a] = 0.5[l.sub.m]). In
this case [f.sub.a0] = 0.25[f.sub.m0].
Lately, the so-called asymmetric multi-span bridges with side spans
of different length are being used, i.e. [l.sub.a1] [not equal to]
[l.sub.a2]. In this case, instead of Eq (6), the following generalized
expression should be used:
[f.sub.m0] = [f.sub.a0.1] [[l.sup.2.sub.m]/[l.sup.2.sub.a1]] =
[f.sub.a0.2] [[l.sup.2.sub.m]/[l.sup.2.sub.a2]]. (7)
It shall be noted that the described conditions will be correct if
in case of initial shape (when the overall length of a bridge is
subjected to the dead load (g = const), the cables are flexible
([E.sub.ca][J.sub.ca] = 0 and [E.sub.cm][J.sub.cm] = 0) and the pylons
rest flexibly on the foundation.
2.3. Analysis of suspension bridge under temporary load
The following analysis of suspension three-span bridge will be
discussed. Symmetric load in case of equal temporary load value of all
spans ([v.sub.a] = [v.sub.m] = v) will be investigated. Deformed diagram
of this bridge under both dead g and temporary v loads is provided in
Figs 1b, 1c. Let's refresh the fact that in course of bridge
behavior analysis the second erection variant shall be applied. The
initial equilibrium state of these "flexible" cables under the
g load shall be described by (1), (2) and (3), (4) equations. Prior the
impact of permanent load particular bending stiffness shall be set for
all cables applying appropriate structural means, i.e. cable will become
the so-called "rigid". The case will be analyzed when the
bending stiffness of mid and side cables is equal ([E.sub.ca][J.sub.ca]
= [E.sub.cm][J.sub.cm] = [E.sub.c][J.sub.c] [not equal to] 0). It means
that the temporary load imposed on the above cables ([v.sub.c]) will
induce additional axial forces H and bending moments [m.sub.c](x).
Stiffening girders will take remaining part of the above loads
[v.sub.b].
2.3.1. Analysis of the main span of suspension bridge
"Rigid" cables and stiffening girders of the entire
bridge under the temporary load v will be deformed (Fig. 1). Suspension
cable will receive the dead load and a part of a temporary load
(g+[v.sub.c]), and the stiffening girder--sharing part of a temporary
load ([v.sub.b]). The above mentioned third assumption enables the
following even displacement condition of stiffening girder and
"rigid" cable [w.sub.bm]([x.sub.m]) = [w.sub.cm]([x.sub.m]) =
[w.sub.m]([x.sub.m]). According to the above mentioned condition, the
equilibrium equation of stiffening girder will be as follows:
-[E.sub.b][J.sub.b][w.sub.m]"([x.sub.m]) +
[M.sub.b,m]([x.sub.m]) = 0, (8)
where [E.sub.b][J.sub.b]--bending stiffness of stiffening girder;
[M.sub.b,m]([x.sub.m]) =
0.12[v.sub.b][l.sup.2.sub.m](4[x.sub.m]/[l.sub.m] -
4[x.sup.2.sub.m]/[l.sup.2.sub.m])--imposed live loads ([v.sub.b])
imposed bending moment.
Deformation state of "rigid" cable tension will be more
complicated. It will be subjected to bending moment as well.
Consequently, the equilibrium equation of the abovementioned cable will
be as follows:
[H.sub.m] [[z.sub.m0] ([x.sub.m]) + [w.sub.m] ([x.sub.m])] +
[m.sub.cm] ([x.sub.m]) + [M.sub.c,m] ([x.sub.m]) = 0, (9)
where [m.sub.cm]([x.sub.m]) =
-[E.sub.c][J.sub.c][w.sub.m]"([x.sub.m])--bending moment of
"rigid" cable; [M.sub.c,m]([x.sub.m])--moment caused by dead
load g and temporary load [v.sub.c] inside the analogous girder.
Taking into consideration that the estimated general load imposed
on the bridge structures is equal to g + v = g + [v.sub.c] + [v.sub.c],
and based on the third assumption the following equilibrium equation
could be made:
[MATHEMATICAL EXPRESSION NOT REPRODUCIBLE IN ASCII] (10)
Eq (10) is similar to the equilibrium equation of standard single
span bridge with flexible cable (Juozapaitis et al. 2010; Wollman 2001).
In this case the overall strength of calculated bridge will increase due
to the member [E.sub.cm][J.sub.cm], i.e. due to the bending stiffness of
a cable. It could be stated that displacements of new suspension bridge
with "rigid" cables under the equal initial conditions will be
lower than displacements of a suspension bridge with flexible cable
(Juozapaitis et al. 2010). Eq (10) could be rewritten as follows:
[MATHEMATICAL EXPRESSION NOT REPRODUCIBLE IN ASCII] (11)
where [k.sub.m.sup.2] = [H.sub.m]/[E.sub.bm][J.sub.bm] +
[E.sub.cm][J.sub.cm]--total flexibility factor of the entire system.
In order to find simpler solution and minimize the volume of
iterative calculation the following concept of fictive displacement of
"rigid" cable shall be used (Juozapaitis et al. 2010; Moskalev
1981):
[w.sub.fic,m]([x.sub.m]) =
[z.sub.fic,m]([x.sub.m])--[z.sub.0m]([x.sub.m]), (12)
where [z.sub.fic](x) = [M.sub.m]([x.sub.m])/[H.sub.m]--fictive
curve complying with the curve of deformed axle of absolute flexible
cable with the equal tension force (Moskalev 1981).
In this case (11) the equation will be as follows:
[w.sub.m]"([x.sub.m]) - [k.sup.2.sub.m][w.sub.m]([x.sub.m]) =
-[k.sup.2.sub.m][w.sub.fic,m]([x.sub.m]). (13)
Solution of this equation, considering the ultimate condition will
be as follows:
[w.sub.x]([x.sub.m]) =
[[DELTA].sub.fic,m][4[x.sub.m]/[l.sub.m]--4[x.sup.2.sub.m]/[l.sup.2.sub.m] + [8/[k.sup.2.sub.m]] [beta]], (14)
where [[DELTA].sub.fic,m] = [z.sub.fic,m]([x.sup.*.sub.m]) -
[z.sub.0m]([x.sup.*.sub.m])--fictive displacement of "rigid"
cable at the middle of the span ([x.sup.*.sub.m] = 0.5[l.sub.m]);
[[beta].sub.m] = ch[k.sub.m][x.sub.m] - [1 -
ch[k.sub.m][l.sub.m]/sh[k.sub.m][l.sub.m]] sh[k.sub.m][x.sub.m] - 1.
Analysis of this solution (14) shows its analogy to the formula
applied for the displacement of "rigid" cable
([E.sub.c][J.sub.c] [not equal to] 0) (Juozapaitis et al. 2006). It
shall be stated that the new suspension bridge could be calculated as a
single "rigid" cable replacing its flexibility factor with the
total flexibility factor of the entire system (Eq (11)). It could be
stated that behaviour of new suspension bridge is described by the
interaction of cable with stiffening girder. Level of initial bridge
shape stabilization applying bending stiffness is described by the
flexibility factor of the entire structural system. It is essential to
highlight the fact that in case of the same general bridge strength and
varying values of girder bending stiffness [E.sub.bm][J.sub.bm] and
cable bending stiffness [E.sub.cm][J.sub.cm], the ratio of values shall
ensure minimum tension forces inside bridge structures. It means that
deformation behaviour of the entire bridge could be regulated in
accordance with the ultimate shape conditions.
In order to determine displacements of "rigid" cable
[w.sub.m]([x.sub.m]), and bending moment [m.sub.cm]([x.sub.m]) it is
required to calculate appropriate fictive displacements
[[DELTA].sub.fic,m] and cable tension force [H.sub.m]. The
abovementioned values are correlated by the following dependency:
[H.sub.m] = (g + [v.sub.c])[l.sup.2.sub.m]/8([f.sub.m0] +
[DELTA][f.sub.fic,m]. (15)
In order to determine [DELTA][f.sub.fic,m] and [H.sub.m], it is
required to apply additional equation describing the relation
(dependency) of the initial length of the cable ([s.sub.0]), its
flexible elongation ([DELTA][s.sub.el]), and length after the
deformation (s):
s = [s.sub.0] + [DELTA][s.sub.el]. (16)
Analysis of the mid span requires the evaluation of possible
horizontal displacement of the pylon upper part [DELTA]l (Fig. 1b).
Initial length of the cable, considering its shape, shall be
calculated applying the following expression [s.sub.0m] = [l.sub.m] +
8[f.sup.2.sub.m0]/3[l.sub.m]. In case of temporary load of symmetrically
stressed ([v.sub.c]) length of a "rigid" cable after the
deformation (considering pylon displacements [DELTA]l), will be equal
to:
[s.sub.m] = [l.sub.m] - [[DELTA]l + 8[([f.sub.m0] +
[DELTA][f.sub.fic,m]).sup.2]/3[(.sub.lm] -
[DELTA]l)][phi]([k.sub.m][l.sub.m])l, (17)
where [phi]([k.sub.m][l.sub.m])--function evaluating the impact of
cable bending stiffness on its deformation.
It shall be noted that application of a "rigid" cable
length after the deformation fictive bending concept expression (17) is
identical to the formula applied for calculation of a flexible cable
length (Moskalev 1981). It simplifies iterative analysis. Provided
formulas show that decreased bending stiffness of a "rigid"
cable [E.sub.c][J.sub.c], values of fictive bending
[[DELTA].sup.f.sub.fic,m] approximate the values of a flexible cable
bending, if [E.sub.c][J.sub.c] [right arrow] 0, the value of fictive
bending of rigid cable will be equal to the value of flexible cable
fictive bending.
It shall be noted that horizontal displacement of cable supports
(the upper part of pylons) [DELTA]l will increase both vertical
displacements and additional bending moments inside the
"rigid" cable and stiffening girder.
It is essential to apply structural means intended for minimization
of cable support (the upper part of pylons) displacements.
Iterative calculation shall be performed applying the following
sequence. First of all, values of the initial main indeterminates
[DELTA][f.sub.fic,m] and [H.sub.m] shall be accepted for flexible cable.
Then, flexibility factor of the entire system [k.sub.m] and function
[phi]([k.sub.m][l.sub.m]) shall be calculated. Further, calculation
shall be carried out applying gradual approximating with the help of Eqs
(15)-(17). Conversion condition could be expressed as follows:
[DELTA][s.sub.el,m] - [DELTA][s.sub.gm] [less than or equal to]
[epsilon], (18)
where [DELTA][s.sub.gm] = [s.sub.m] - [s.sub.0m].
It shall be noted that calculation has been complicated by the
indeterminate horizontal displacement of supports [DELTA]l, which could
be determined after the calculation of parallel side spans.
Final values [DELTA][f.sub.fic,m] and [H.sub.m] shall be used for
calculation of "rigid" cable and stiffening girder
displacements [w.sub.m]([x.sub.m]) their bending moments
[m.sub.cm]([x.sub.m]) and [m.sub.bm]([x.sub.m]). It shall be highlighted
that fictive displacement enables minimization of iterative number and
simplifies the calculation itself.
2.3.2. Analysis of a side span of suspension bridge
Behaviour of side spans of suspension bridge is identical to the
behaviour of the mid span structure. The distinctive feature includes
the fact that the "rigid" cable of the side span is inclined
(Fig. 1). Improved analysis of inclined "rigid" cables (local
reference system) is more complex. Consequently, in order to simplify
calculation this inclined cable will be analyzed by applying the global
reference system, and the accuracy of calculation will be enhanced by
applying the cable flexibility [k.sub.a][l.sub.a] adjustment coefficient
[[eta].sub.a] = [cos.sup.-2][phi].
Further, behaviour of the right span structures of suspension
bridge will be discussed. Deformed diagram of individual structures is
shown in Figs 1a, 1b. Suspension cable the same as mid span structure
will be subjected to the dead load and sharing part of temporary load (g
+ [v.sub.c]), and stiffening girder to sharing part of temporary load
([v.sub.b]). Equilibrium condition of the side span stiffening girder
will be as follows:
-[E.sub.b][J.sub.b][w.sub.a]([x.sub.a]) + [M.sub.b,a]([x.sub.a]) =
0, (19)
where [w.sub.a]"([x.sub.a])--the second expression of a
described span stiffening girder displacement; [M.sub.b,a]([x.sub.a]) =
0.125[v.sub.b][l.sup.2.sub.a]((4[x.sub.a]/la) - (
4[x.sup.2.sub.a]/[l.sup.2.sub.a]))--moment caused by the temporary load
([v.sub.b]).
Equilibrium equation of the inclined "rigid" cable:
[H.sub.a][[z.sub.a0]{[x.sub.a]) +
[w.sub.a]([x.sub.a])]-[E.sub.c][J.sub.c][w.sub.a]([x.sub.a]) +
[M.sub.c,a]([x.sub.a]) = 0, (20)
where [E.sub.c][J.sub.c][w.sub.a]"([x.sub.a])--banding moment
inside the inclined "rigid" cable;
[M.sub.c,a]([x.sub.a])--moment caused by the dead load g and temporary
load [v.sub.c] inside the analogous span girder.
After the translation of Eq (20) and application of fictive bending
concept, the solution analogous to the mid span solution could be drawn:
[MATHEMATICAL EXPRESSION NOT REPRODUCIBLE IN ASCII] (21)
where
[MATHEMATICAL EXPRESSION NOT REPRODUCIBLE IN ASCII]
[DELTA][f.sub.fic,a] ([x.sup.*.sub.a]) -
[z.sub.0a]([x.sup.*.sub.a])--fictive displacement of "rigid"
cable at the center of the span ([x.sup.*.sub.a] = 0.5[l.sub.a]), shall
be calculated starting from the straight line connecting the upper and
the bottom supports (Fig. 1b).
Horizontal element of inclined "rigid" cable tension
force shall be calculated as follows:
[H.sub.a] = (g + [v.sub.c])[l.sup.2.sub.a]/8([f.sub.a0] +
[DELTA][f.sub.fic,a]). (22)
Iterative calculation shall be performed applying the
abovementioned equation:
[s.sub.a] = [s.sub.0a] + [DELTA][s.sub.el,a], (23)
Initial length of the inclined cable under the square parabola
shape shall be calculated applying global reference system and
previously drawn equation:
[s.sub.0a] = [l.sub.a]/cos[phi] + 8[f.sup.2.sub.a0]/3[l.sub.a]
[cos.sup.3][phi]. (24)
Length of the inclined "rigid" cable after the
deformation, considering the displacements of its supports [DELTA]l,
will be equal to:
[MATHEMATICAL EXPRESSION NOT REPRODUCIBLE IN ASCII] (25)
where [phi]([k.sub.a][l.sub.a]h)--function, describing the impact
of inclined "rigid" cable bending stiffness on the
deformation.
Iterative calculation of the side suspension bridge span structure
shall be performed applying the sequence analogous to the sequence used
for main span. If accepted values of values of the initial main
indeterminates [DELTA][f.sub.fic,a] and [H.sub.a] shall be used for
gradual approximating with the help of Eqs (22)-(25). Conversion
condition is analogous to the mid span condition and could be expressed
as follows [DELTA][s.sub.el,a] - [DELTA][s.sub.ga] [less than or equal
to] [epsilon]. It shall be noted that the determination of the
displacement of side span inclined cable, stiffening girder and internal
forces the following horizontal displacements of supports shall be known
[DELTA]l. For this purpose the additional iteration of the second level
shall be drawn, it foresees equilibrium condition of the mid and side
span tension force and suspension bridge cable deformation equation.
Analysis could be simplified by preliminary calculation of cable
kinematic displacement performed at the very beginning of iteration.
3. Concluding remarks
The work describes the modern suspension three-span bridge with
stiff in bending cables, the initial shape of which is stabilized by
so-called "rigid" cables. Initial and operation stages of that
bridge are being described in terms of erection sequence of its
"rigid" cables. Analysis formulas of internal forces and
displacements of individual components are provided in terms of
horizontal displacements of supports. Analysis of inclined
"rigid" cable applying global reference system has been
described as well. It has been noted that calculation expressions used
for modern threes-pan suspension bridge describe the general cases used
for calculations of the above bridges, i.e., ignoring the impact of
stiffening girders could help to determine appropriate formulas for
individual "rigid" cables. In case of "rigid" cable
transformation into the flexible one--expressions for the calculation of
standard suspension bridge could be delivered. It has been determined
that modern suspension bridge enables the adjustment of structural
tension force deformation state by changing the ratio between the cable
and stiffening girder bending stiffness. Application of the cable's
fictive displacement concept could be used in order to significantly
simplify the iterative calculation of the total system.
Caption: Fig. 1. Structural and estimated diagrams of considered
suspended bridge
doi: 10.3846/bjrbe.2013.26
References
Caballero, A.; Pose, M. 2010. Local Bending Stresses in Stay Cables
with an Elastic Guide, Structural Engineering International 20(3):
254-259. http://dx.doi.org/10.2749/101686610792016745
Chen, Z. W.; Xu, Y. L.; Xia, Y.; Li, Q.; Wong, K. Y. 2011. Fatigue
Analysis of Long-Span Suspension Bridges under Multiple Loading: Case
Study, Engineering Structures 33(12): 3246-3256.
http://dx.doi.org/10.1016/j.engstruct.2011.08.027
Cobo del Arco, D.; Aparicio, A. C. 2001. Preliminary Static
Analysis of Suspension Bridges, Engineering Structures 23(9): 1096-1103.
http://dx.doi.org/10.1016/S0141-0296(01)00009-8
Clemente, P.; Nicolosi, G.; Raithel, A. 2000. Preliminary Design of
Very Long-Span Suspension Bridges, Engineering Structures 22(12):
1699-1706. http://dx.doi.org/10.1016/S0141-0296(99)00112-1
Furst, A.; Marti, P.; Ganz, H. 2001. Bending of Stay Cables,
Structural Engineering International 11(1): 42-46(5).
Gimsing, N. J.; Georgakis, Ch. T. 2012. Cable Supported Bridges:
Concept and Design. 3rd edition. John Wiley & Sons, 590 p. ISBN
0470666285.
Gorokhov, Y.; Mushchanov, V.; Pryadko, I. 2013. Reliability
Provision of Rod Shells of Steady Roofs over Stadium Stands at Stage of
Design Work, in Proc. of the 11th International Conference on Modern
Building Materials, Structures and Techniques. Procedia Engineering 57:
353-363. http://dx.doi.org/10.1016/j.proeng.2013.04.047
Gopper, K.; Kratz, A.; Pfoser, P. 2005. Entwurf und Konstruktion
einer S-formigen Fussgangerbrucke in Bochum Stahlbau 74(20): 126-133 (in
German).
Grigorjeva, T.; Juozapaitis, A.; Kamaitis, Z. 2010. Static Analysis
and Simplified Design of Suspension Bridges Having Various Rigidity of
Cables, Journal of Civil Engineering and Management 16(3): 363-371.
http://dx.doi.org/10.3846/jcem.2010.41
Hao Wang; Ai-qun Li; Jian Li. 2002. Progressive Finite Element
Model Calibration of a Long-Span Suspension Bridge Based on Ambient
Vibration and Static Measurements, Engineering Structures 32(9):
2546-2556. http://dx.doi.org/10.1016/j.engstruct.2010.04.028
Horokhov, Y.; Mushchanov, V.; Kasimov, V. 2006. New Approaches to
Analysis and Design of a Stationary Covering above the Stadium Tribunes,
Journal of Civil Engineering and Management 12(4): 293-302.
Jennings, A. 1987. Deflection Theory Analysis of Different Cable
Profiles for Suspension Bridges, Engineering Structures 9(2): 84-94.
http://dx.doi.org/10.1016/0141-0296(87)90002-2
Juozapaitis, A.; Idnurm, S.; Kaklauskas, G.; Idnurm, J.; Gribniak,
V. 2010. Non-Linear Analysis of Suspension Bridges with Flexible and
Rigid Cables, Journal of Civil Engineering and Management 16(1):
149-154. http://dx.doi.org/10.3846/jcem.2010.14
Juozapaitis, A.; Vainiunas, P.; Kaklauskas, G. 2006. A New Steel
Structural System of a Suspension Pedestrian Bridge, Journal of
Constructional Steel Research 62(12): 1257-1263.
http://dx.doi.org/10.1016/j.jcsr.2006.04.023
Kala, Z. 2012. Geometrically Non-Linear Finite Element Reliability
Analysis of Steel Plane Frames with Initial Imperfections, Journal of
Civil Engineering and Management 18(1): 81-90.
http://dx.doi.org/10.3846/13923730.2012.655306
Katchurin, V.; Bragin, A.; Erunov, B. 1971. Design of Suspension
and Cable-Stayed Bridges. Transport, 280 p.
Kiisa, M.; Idnurm, J.; Idnurm, S. 2012. Discrete Analysis of
Elastic Cables, The Baltic Journal of Road and Bridge Engineering 7(2):
98-103. http://dx.doi.org/10.3846/bjrbe.2012.14
Kim, S. E.; Thai, H.-T. 2010. Nonlinear Inelastic Dynamic Analysis
of Suspension Bridges, Engineering Structures 32(12): 38453856.
http://dx.doi.org/10.1016/j.engstruct.2010.08.027
Kulbach, V. 2007. Cable Structures. Design and Analysis. Tallin,
Estonian Academy Publisher. 224 p.
Lewis, W. J. 2012. A Mathematical Model for Assessment of Material
Requirements for Cable Supported Bridges: Implications for Conceptual
Design, Engineering Structures 42: 266-277.
http://dx.doi.org/10.1016/j.engstruct.2012.04.018
Moskalev, N. S. 1981. Suspension Structures. Moskva: Stroyizdat.
335 p.
Nakamura, Sh.; Suzumura, K. 2009. Hydrogen Embrittlement and
Corrosion Fatigue of Corroded Bridge Wires, Journal of Constructional
Steel Research 65(2): 269-277.
http://dx.doi.org/10.1016/j.jcsr.2008.03.022
Nevaril, A.; Kytyr, J. 2001. FEM Analysis of Bridge-Type Cable
System, in Proc. of IABSE Conference Cable Supported. Bridges
--Challenging Technical Limits. June 12-14, 2001, Seoul, Korea. IABSE
Reports 84: 154-155. http://dx.doi.org/10.2749/222137801796349989
Yanaka, Y.; Kitagawa, M. 2002. Maintenance of Steel Bridges on
Honshu-Shikoku Crossing, Journal of Constructional Steel Research 58(1):
131-150. http://dx.doi.org/10.1016/S0143-974X(01)00031-1
Prato, C. A.; Ceballos, M. A. 2003. Dynamic Bending Stresses Near
the Ends of Parallel Bundle Stay Cables, Structural Engineering
International 13(1): 64-68. http://dx.doi.org/10.2749/101686603777965008
Daniunas, A.; Urbonas, K. 2013. Influence of the Column Web Panel
Behaviour on the Characteristics of a Beam-to-Column Joint, Journal of
Civil Engineering and Management, 19(2): 318-324.
http://dx.doi.org/10.3846/13923730.2013.776628
Ryall, M.; Parke, G.; Harding, J. 2000. The Manual of Bridges
Engineering. London: Tomas Telford Ltd. 1012 p. ISBN 0727727745.
Sandovic, G.; Juozapaitis, A.; Kliukas, R. 2011. Simplified
Engineering Method of Suspension Two-Span Pedestrian Steel Bridges with
Flexible and Rigid Cables under Action of Asymmetrical Loads, The Baltic
Journal of Road and Bridge Engineering 6(4): 267-273.
http://dx.doi.org/10.3846/bjrbe.2011.34
Song, H.; Wang, X. 2010. Zhoushan Xihoumen Bridge with the World
Record Span Length of Steel Box Girder, China, Structural Engineering
International 20(3): 312-316.
http://dx.doi.org/10.2749/101686610792016871
Strasky, J. 2005. Stress-Ribbon and Supported Cable Pedestrian
Bridges. London: Thomas Telford Ltd. 232 p. ISBN 072773282X.
http://dx.doi.org/10.1680/sracspb.32828
Troyano, L. F. 2003. Bridge Engineering: a Global Perspective.
London: Tomas Telford Ltd. 775 p. ISBN 0727732153.
http://dx.doi.org/10.1680/beagp.32156
Wollman, G. P. 2001. Preliminary Analysis of Suspension Bridges,
Journal of Bridge Engineering 6(4): 227-233.
http://dx.doi.org/10.1061/(ASCE)1084-0702(2001)6:4(227)
Wyatt, T. A. 2004. Effect of Localised Loading on Suspension.
Bridges, Bridge Engineering 157(BE2): 55-63.
http://dx.doi.org/10.1680/bren.2004.157.2.55
Xu, J.; Chen, W. 2013. Behavior of Wires in Parallel Wire Stayed
Cable under General Corrosion Effects, Journal of Constructional Steel
Research 85: 40-47. http://dx.doi.org/10.1016/j.jcsr.2013.02.010
Received 2 May 2013; accepted 5 August 2013
Algirdas Juozapaitis (1) [mail], Romualdas Kliukas (2), Giedre
Sandovic (3), Ona Lukosevicience (4), Tomas Merkevicius (5)
(1, 3, 5) Dept of Bridges and Special Structures, Vilnius Gediminas
Technical University, Sauletekio al. 11, 10223 Vilnius, Lithuania
(2, 4) Dept of Strength of Materials, Vilnius Gediminas Technical
University, Sauletekio al. 11, 10223 Vilnius, Lithuania
E-mails: (1) algirdas.juozapaitis@vgtu.lt; (2)
romualdas.kliukas@vgtu.lt; (3) giedre.sandovic@vgtu.lt; (4)
ona.lukoseviciene@vgtu.lt; (5) tomas.merkevicius@vgtu.lt