Research and assessment of asphalt layers bonding/Asfaltines dangos ir pagrindo sluoksniu sukibimo tyrimai ir vertinimas/Asfalta segas slanu saistes izpete un novertejums/ Asfaldikihtide seotuse uuring ja hindamine.
Vaitkus, Audrius ; Zilioniene, Daiva ; Paulauskaite, Sabina 等
1. Introduction
The bonding of asphalt layers has direct reliance on road pavement
structures strength and durability. The bonding of asphalt layers is
affected by the size of aggregates, type of materials, binder (bitumen)
of adjacent layers, also by the type of bitumen emulsion, used for the
bonding between asphalt layers, and construction technology of asphalt
layers (Hu et al. 2011; Raab et al. 2009). In Lithuania, when laying
asphalt pavement from two or more layers, the under layer shall be
evenly coated with bitumen emulsion the type and amounts of which depend
on the class of pavement structure, properties of the under layer and
type of asphalt layer to be laid. In other countries to ensure the bond
of asphalt layers the bitumen emulsions of various types are widely used
(Harvey et al. 1999; Hu et al. 2011; Plug et al. 2010). Due to
insufficient bonding between asphalt layers the upper asphalt layer
under the effect of shear force can slip in respect of the lower asphalt
layer, and the lower asphalt layer can slip in respect of asphalt base.
In that case the corrugations, rutting and cracking occur within the
whole pavement structure. The mentioned defects are most frequently
formed at the acceleration/deceleration and turning zones. Due to
insufficient bonding of asphalt layers the life cycle of asphalt
pavement becomes shorter.
The problem of insufficient bonding between asphalt layers is
topical for many countries. Already in 1980, the Environmental Dept of
Northern Ireland identified asphalt pavement defects on the newly laid
road, and they were caused by insufficient bonding of asphalt layers (Hu
et al. 2011; Shaat 1992). Lepert et al. (1992) gave the results of
SETRA/DTC research, carried out in 1986, concluding that insufficient
bonding of asphalt layers caused 5% of the defects on the road network
of France. Sutano (2004) investigated the reasons why on the newly
reconstructed road of Indonesia the horizontal deformations and
corrugations occur at the acceleration and acceleration zones. Charmot
et al. (2005) has identified large areas of the slippage of upper
asphalt layer, which occurred two months after the overlay project on
one of the Nevada State (USA) roads.
The research in the Washington State (USA) indicated that in 10% of
the tested asphalt samples, taken from the roads of this State, the
upper and lower asphalt layers were separated (Muench, Moonmaw 2008).
Because of this problem the asphalt layers were slipped in respect of
each other and the corrugations, ruts and cracks were evident.
The problem of insufficient bonding of asphalt layers was also
analysed in Switzerland. On one of the newly constructed highways the
areas of insufficiently bonded base layers were identified. The problem
of insufficient bonding of asphalt layers not only occurs between the
upper and lower asphalt layers but also between the base layers (Raab,
Partl 2004a).
The problems of the slippage of upper layers were investigated and
analysed in some Japanese airports. On the airport runways the slippage
of upper layer was observed caused by insufficient bonding with the
lower layer (Hachiya, Sato 1997). The problem of the slippage of asphalt
layers due to insufficient bonding was also analysed and assessed in
Newark airport of the New Jersey State (USA) (Bognacki et al. 2007). On
some airport runways the slippage of upper asphalt layer in respect to
the lower asphalt layer was identified.
The ruts, corrugations, slippage of asphalt layers and longitudinal
cracks within the whole pavement structure, caused by insufficient
asphalt layers bonding, increase maintenance costs (due to repairs) and
shorten the life cycle of the pavement. Many European countries, also
USA, Canada and others, carry out investigations on the significance of
bonding between the upper and lower asphalt layers, and the deeper
layers for the life cycle and durability of asphalt pavement. Such
countries as USA, Switzerland, Germany and Slovenia have already
approved methods for the determination of the bonding strength of
layers. Lithuania according to Automobiliu keliu dangos konstrukcijos
asfalto sluoksniu irengimo taisykles IT ASFALTAS 08 [The Installation
Rules of the Road Pavement Asphalt Layers "IT ASFALTAS 08"]
also regulates the bonding strength between the upper and lower layers
and between the lower and base layers. However, not in all cases this
requirement carries an obligatory character and the customer takes the
final solution on its necessity.
The bonding of asphalt layers is affected by many factors. They
altogether determine the strength and durability of asphalt pavement.
Due to the gradually increasing traffic volume and traffic loads the
higher and higher requirements are raised for asphalt pavements. In
order to achieve the highest possible strength and durability of asphalt
pavements a large attention is paid to the research in the physical and
mechanical properties of individual asphalt layers and their mixtures
(Bulevicius et al. 2010; Cygas et al. 2011; Motiejunas et al. 2010).
However, it should be emphasized that not only the materials of
different asphalt layers but also the bonding between them is a very
important factor seeking to prolong pavement performance and to prevent
the occurrence of defects (Hu et al. 2011; Raab et al. 2004b).
2. The principles of bonding between asphalt layers
Sufficient bonding between asphalt layers ensures the required
bearing capacity, strength and durability of asphalt pavement (Raab et
al. 2009). Under sufficient bonding the asphalt layers function as a
monolithic structure and the largest stresses from vertical load are
concentrated at the bottom of the structure. When the bonding is
insufficient each asphalt layer functions separately and such pavement
is able to carry lower loads compared to the pavement the layers of
which are sufficiently bonded.
The bonding between asphalt layers is conditioned by friction,
bonding and interlocking of the layers. Asphalt layers can be (Frohmut,
Ascher 2007) (Fig. 1):
--fully bonded--in that case they work as a monolithic layer. On
their bonding plane large shear stresses occur and no deformations
(displacements) are developed. However, this is a theoretical model
since in practice the bonding plane of asphalt layers is always
represented by smaller or larger deformations;
--partially bonded (interlocked)--depending on the strength of
interlocking the shear stresses and deformations (displacements) of
various sizes are developed at the interlayer. In case of strong
interlocking large shear stresses and small deformations (displacements)
occur, in case of weak --on the contrary, small shear stresses and large
displacements. An intermediate variant is also possible. Besides
interlocking, the bonding is influenced by the layers friction, though,
the effect of friction is getting lower with the increasing bonding
area;
--fully slipped--between the layers only friction and bonding occur
due to the load and the self-weight of layers. Very small shear stresses
and very large deformations (displacements) are developed.
According to Dr Metelmann (ADLER Baustoff und Umwelt LABOR GmbH,
2004. Anforderungen an den Asphalteinbau, Schichtenverbund und
Lebensdauer von Asphaltkonstruktionen) the bearing capacity of asphalt
pavement, depending on the bonding of asphalt layers in a three-layer
structure, is distributed as follows: all three layers are bonded--100%,
there is no bonding between the upper and lower layers -70%, there is no
bonding between the lower and base layers--40% and there is no bonding
between all three layers -3%.
[FIGURE 1 OMITTED]
At the joining of two asphalt layers (interlayer) horizontal load
generates the shear and tensile stresses. The shear stresses occur in
the wheel and pavement contact zone between asphalt layers.
Insufficient bonding between asphalt layers are determined by the
following factors (West et al. 2005): the non-use of materials to
improve bonding (bitumen, bitumen emulsion), improper use of materials
to improve bonding, the use of improper asphalt mixtures to ensure a
proper bonding between asphalt layers (it is of significant importance
at the acceleration/deceleration and turning zones), the use of asphalt
mixtures with a large content of sand filler, the improper application
of technology to prepare the under layer surface or the non-compliance
with the technology (insufficient cleaning when preparing the layer,
dust, water, the uneven and (or) in too small contents spreading of
bitumen or bitumen emulsion).
3. Methods for the determination of asphalt layers bonding and
requirements for bonding values
The bonding strength between asphalt layers could be determined by
various testing methods. In recent years many European countries, as
well as USA and Canada, have validated methods and devices used to
perform the testing of bonding strength between asphalt layers. (Raab et
al. 2009).
To determine the bonding strength between asphalt layers most
frequently the shear tests are carried out, more seldom the pull-off of
torque tests (Fig. 2). The shear tests are performed by applying normal
stresses in the sample or without their application, the pull-off tests
are direct or indirect (Frohmut, Ascher 2007; Raab et al. 2009).
The shear tests, performed without applying normal stresses in the
sample, are also called direct, and the shear tests performed with
normal stresses --the simple. The most world widely used are various
modifications of the direct shear test. Those are static tests without
the application of normal stresses in the sample during which the force
with constant displacement is transferred to only one of the layers
parallel to the shear plane. Another layer remains fixed. A cylindrical
sample (asphalt core, Marshall sample or similar) is fixed in a
perpendicular direction to the cross-section, i.e. laid. The obligatory
parameters for the direct shear test are testing temperature, loading
speed, dimensions of samples, gap between fixation and shearing rings.
In many countries the tests are essentially similar only using different
testing parameters and the slightly modified shearing rings, and the
bond between the layers is usually assessed according to the measured
destructive shear force and shear flow (Frohmut, Ascher 2007; Raab et
al. 2009).
[FIGURE 2 OMITTED]
The bonding force between asphalt layers by a direct tensile test
is world widely determined by the same principle only under different
conditions, i.e. by laboratory and field tests. The edges of 50 mm, 100
mm or 150 mm diameter samples are glued with special glue to steel or
aluminium testing disks and are tracked in an axial direction with
constant force one from each other until their destruction. In this way,
at the selected temperature, for example 15 [degrees]C, the max force is
determined at which the sample fails. It should be mentioned that the
failure zone of the sample is not always identical to the interlayer
plane. The indirect tensile test of asphalt layers is carried out by the
method of wedge-shaped crack. The bonding point of separate layers of
rectangular or cylindrical samples is pressed by a special wedge, fixed
in the wheels, until the sample fails (Frohmut, Ascher 2007).
Using the non-destructive test methods to detect the bonding
condition between asphalt layers the piezoelectric acceleration
detectors are used to measure and record vibrations induced by the
impulse (from the falling weight) to the pavement surface. The curves of
vibrations of sufficient and insufficient bonding differ, and thus the
bonding between asphalt layers is detected without destructing the
pavement.
A plenty of tests are worldwide used to determine the bonding
strength between asphalt layers (Bondt 1999; Canestrari, Santagata 2005;
Frohmut, Ascher 2007; Kruntcheva et. al. 2004; Raab et al. 2009;
Recasens et. al. 2003; Sholar et. al. 2004; Tashman et al. 2006):
--shear tests: direct shear test (without normal
stresses)--Leutner, Layer-Parallel Direct Shear, LBC, de Bondt, NCAT,
FDOT, Iowa, Rommanoshi, Al-Qadi, Asher, Superpave shear tester (SST) or
simple shear test (by inducing normal stresses in the sample)--MCS,
ASTRA, SST;
--tensile tests: direct tensile test--UTEP Pull-Of Test, MTQ;
indirect tensile test--Tschegg;
--torque tests--Attacker and Torque bond test;
--non-destructive tests--load impulse test; Falling weight
deflectometer (FWD) test.
In Europe, the bonding strength between asphalt layers is mostly
measured by testing cylindrical core samples with the diameter of 100 mm
or 150 mm taken from the asphalt pavement. Using the modified direct
shear device (Layer parallel direct shear LPDS) the bonding between
asphalt layers can be also measured for prismatic samples. The test
of bonding strength is usually performed at a 20-25 [degrees]C
temperature.
The Leutner shear test is widely used in many countries, and in
Switzerland, Austria and Germany has been accepted as a national
standard to detect the bonding strength of asphalt layers. European
countries, using the Leutner method, have slightly modified its
principle scheme and adapted to their needs. The test is performed on a
150 mm or 100 mm diameter cylindrical sample composed of two layers. One
tested part (lower layer) is fixed by mechanical clamping and another
part (upper layer) is provided with the static load at a constant 50
mm/min speed. Between the fixing plate and force transfer plate a 1 mm
gap is left. The test is performed at a temperature of 20 [degrees]C
(Leutner 1979).
The direct bonding strength of asphalt pavement layers can be
determined by the peel test. In Germany, this test is aimed at
determining the bonding between thin asphalt layers and is performed
according to the Forschungsgesellschaft fur Srassen--und Verkehrswesen
"Technische Prufvorschriften fur asphalt, TP Asphalt-StB Teil
81"2009 [Research Society for Srasse and Transportation
"Technical Test for Asphalt, Asphalt-StB part TP 81st" 2009].
During the test the edges of samples (cores) are glued by special glue
to the steel or aluminium testing disks and are tracked in axial
direction with constant force one from each other until their
destruction. At the selected temperature the largest destructive force
is detected. It should be mentioned that the failure zone is not always
identical to the interlayer bonding plane. The test can be performed in
the laboratory or on-site.
The bonding condition between asphalt layers could be assessed by
using the falling weight deflectometer. This device induces the load
impulse, simulating traffic loading, and pavement deflections are
recorded by the piezoelectric acceleration detectors. Knowing the
properties of pavement materials and based on the back-calculation
method the bonding between the layers are determined. For this purpose
the parameters, influencing the layers bonding, are changed until the
calculated surface deformations coincide with those measured. This
method does not enable to determine the direct bonding parameters
between asphalt layers (bonding strength or shear flow). Due to an
extremely large amount of parameters, influencing calculation results,
the use of this method for the determination of asphalt layers bonding
is rated as poor (Frohmut, Ascher 2007).
In Germany, the min values of the bonding strength between asphalt
layers, regulated by the document ZTV Asphalt-StB 07 are: between the
upper and lower asphalt layers not less than 15 kN and between other
layers or partial layers not less than 12 kN.
ZTV Asphalt-StB 07 does not regulate the values of shear flow, and
the recommended limit values for the shear flow are given in ZTV M-V and
Arbit No. 60 (Table 1).
4. Experimental research
The first stage of experimental research on the bonding of asphalt
layers was carried out at the Road Scientific Laboratory of the Vilnius
Gediminas Technical University Road Research Institute in September and
October 2010. The samples were taken from the streets of Vilnius City.
The research consisted of the taking of asphalt samples (cores) from the
selected streets and roads and the laboratory testing of bonding between
asphalt layers in the samples (cores) that were taken. The samples were
taken in five locations (Table 2), at the outer track of the first
traffic lane. In all sampling locations, under the lower asphalt layer
(in Savanoriu pr. and Kalvariju g. between the upper and lower asphalt
layers) a geosynthetic material was laid or a special asphalt mix.
Taking of asphalt samples (cores) to be tested was carried out
according to the standard LST EN 12697-27:2002 "Bituminiai
misiniai. Karstojo asfalto misinio bandymo metodai. 27 dalis. Eminiu
emimas" [Bituminous Mixtures--Test Methods for Hot Mix
Asphalt--Part 27: Sampling], and the bonding condition of asphalt layers
was determined according to the document TP Asphalt-StB Teil 80
Technische Prufvorschriften fur Asphalt [Technical Regulations for
Asphalt Testing, Part 80]). This was based on the fact that the IT
ASFALTAS 08 points out namely to this document for the determination of
the bonding of asphalt layers.
In the laboratory the bonding of asphalt layers was determined for
those layers between which the geosynthetic material (geogrid) was laid,
i.e. between the lower layer and the layers of the old asphalt pavement
(in most cases) or between the upper and lower asphalt layers, also
between the layers where no geogrid was laid to compare the bonding
strength between the layers. The bonding strength between the upper or
lower asphalt layer and the underlying layer, laid from the special
stress-absorbing asphalt mixture VIASAF 0/5, was also determined.
Prior to the shear test of asphalt layers each of the asphalt
samples (cores) was marked with the traffic direction, since the shear
of asphalt layers was made parallel to the driving direction. The
bonding test was performed according to the principle scheme of the
Leutner shear test. The asphalt cores of 150 mm diameter were tested.
For the transfer of shear load and for the recording of destructive
force and shear flow the standard Marshall press, generating a static
load, was used. The shear was made by a special shearing mould (Fig. 2)
which was fixed in the Marshall press. During the test the lower layer
was fixed by mechanical clamping and the upper layer was provided with
the static load at a constant 50 mm/min speed. Before the test, asphalt
cores were stored at a 20 [degrees]C temperature for 24 hours, then the
diameter of samples and the thicknesses of the sheared layers were
measured and the joining boundary of asphalt layers was marked with a
special marker to ensure a more precise fixing of the sample. Totally, 2
or 3 asphalt cores were tested (depending on the sampling location).
After the test the remains of adjoining layers were recorded.
The second stage of experimental research on the bonding of asphalt
layers was carried out at the Road Scientific Laboratory of the Vilnius
Gediminas Technical
University Road Research Institute from October 2010 to January
2011. The bonding tests were performed using methodology identical to
the first research stage. First of all, on different roads of Lithuania
the asphalt samples (cores) were taken, then the shear test of the upper
asphalt layer was performed (Table 3). The asphalt cores were taken at
the first track and also in-between the tracks to compare the bonding
strength between the layers. Two asphalt cores were taken from each
location.
[FIGURE 3 OMITTED]
5. Analysis and assessment of research results
The first stage of laboratory tests of the bonding between asphalt
layers in the samples found that the max shear force in asphalt layers
varies depending on the geosynthetic material used (Fig. 3).
In all cases, for the samples without geogrid at the interlayer a
larger max shear force was determined compared to the samples the
interlayer of which was equipped with geosynthetic material. It was
found that the max shear force in the samples without geogrid (between
the lower and the old asphalt pavement layers), taken from the Plytines
g., was 85% higher than in the samples taken from the same street but
having the geogrid Pavegrid G100/100 (between the lower and the old
asphalt pavement layers). The similar results were also obtained in
Kalvariju g. where the bonding strength of the samples without geogrid
(between the lower and the old asphalt pavement layers) was 38% higher
compared to the samples with the geogrid Pavegrid G100/100 (between the
upper and lower asphalt pavement layers). The histogram of Fig. 3 shows
that the max shear force in the samples without geogrid (between the
lower and the old asphalt pavement layers), taken from the Eisiski?
road, is about 30% higher than in the samples with the geogrid HaTelit C
40/17 (between the lower and the old asphalt pavement layers) and even
2.7 times higher than in the samples with the geogrid Armatex RSM 50/70.
It should be mentioned that the bonding strength in the samples with the
geogrid Armatex RSM 50/70 between the lower and the old asphalt pavement
layers is 20% lower than it is required by the article 86 of ?T ASFALTAS
08 (9.6 kN < 12.0 kN). The bonding strength in all other samples
(with and without the geogrid between the upper and lower layers and
between the lower and the old asphalt pavement layers) is higher than
the required. The testing showed that the bonding between a pavement
layer from the special asphalt mixture VIASAF 0/5 and the lower or upper
asphalt layers is relatively large and in all tested cases reached more
than 22.0 kN.
The shear flow (deformation) of asphalt layers varies subject to
the geosynthetic material used (Fig. 4). It could be noticed that the
shear flow in the samples with the geogrid Pavegrid G100/1 00 is lower
than that in the samples without geogrid, and in the samples with the
geogrid HaTelit C 40/17 and Armatex RSM 50/70 to the contrary--higher.
It was found that the shear flow in the samples with the geogrid
Pavegrid G100/100 (between the lower and the old asphalt pavement
layers), taken from the Plytines g., was 35% lower than in the samples
without geogrid, and the shear flow in the samples taken from the
Kalvariju g. with the identical geogrid between the upper and lower
layers was 20% lower than in the samples without geogrid.
[FIGURE 4 OMITTED]
Meanwhile, the shear flow in the samples with the geogrid HaTelit C
40/17 and Armatex RSM 50/70 (between the lower and the old asphalt
pavement layers) was about 40% higher compared to the samples without
geogrid. The relatively high shear flow (> 5 mm) was determined
between a layer from the special asphalt mixture VIASAF 0/5 and the
lower or upper asphalt layers compared to the other tested samples.
The analysis of results of the 1st research stage enables to assume
that the use of geosynthetic materials at the interlayer reduces the
bonding strength between asphalt layers. Also, the bonding strength
between asphalt layers depends on the type of geosynthetic material. The
use of geosynthetic material, and especially of the special
stress-absorbing asphalt layer, increases the shear flow at the asphalt
pavement interlayers.
[FIGURE 5 OMITTED]
[FIGURE 6 OMITTED]
The analysis of results of the second research stage showed that
the samples from 83% of the sampling locations (25 from 30) had the max
shear force higher than 15 kN (Fig. 5). The max shear force in the
samples of the remaining 4 locations was < 25% lower than the
required (15 kN), and the shear force the samples of 1 location was 2
times lower than the required. The highest shear force was determined in
the samples taken from the road No. 102. The samples were taken in the
track, the upper asphalt layer was laid from the mixture SMA 11 S.
Meanwhile, the lowest shear force was determined in the samples taken
from the road No. 153. The samples were taken at the track, the upper
asphalt layer was laid from the mixture AC 11 VS. It could be noticed
that the samples from 50% of the sampling locations had the max shear
force higher than 20 kN.
Fig. 5 shows that the bonding strength in the samples, taken from
the road No. 102, is higher than 30 kN. The upper asphalt layer of this
road was laid from the mixture SMA 11 S. The relatively high shear force
was also determined in the samples taken from the road No. A14 (in all
cases > 22 kN), here the upper asphalt layer was also laid from the
mixture SMA 11 S. When analysing the bonding strength between the upper
and the lower layers of the pavement of road No. 130, it should be
mentioned that in 4 from 5 sampling locations the samples had no
required 15 kN shear force. It was determined that the bonding strength
was on average 16% lower than the required. The insufficient bonding
between asphalt layers was also determined in the samples taken in 1.6
km of the road No. 153, and in the samples taken in 15.7 km of the road
No. 143. The results of the bonding strength in the samples, taken in
the 1st track and in-between the tracks, suggest no concrete
assumptions. During the testing no significant difference was detected
between the shear force in the samples, taken in the track, and in those
taken in-between the tracks of the same road.
The analysis of results of the shear flow of the upper and lower
asphalt layers showed that the shear flow varies irrespective of the
sampling location. The histogram of Fig. 6 shows that in the samples
taken from 63% of locations (19 from 30) the shear flow varied from 2.0
mm to 4.0 mm. The results of the remaining 11 sampling locations were as
follows: the shear flow in the samples taken from 4 locations was
slightly lower than 2 mm, in the other 7--higher than 4 mm. It could be
noticed that the shear flow in the samples taken from the roads the
upper layer of which was laid from the mixture SMA 11 S (the roads No.
102 and No. A14) was slightly higher compared to the shear flow in the
samples taken from other roads. The research showed that the shear flow
varies irrespective of the fact if the samples were taken in the track
or in-between the tracks.
The analysis of results of the bonding strength between asphalt
layers in the samples, taken from different roads of Lithuania, showed
that the samples from 83% of the sampling locations (25 from 30) had the
max shear force higher than 15 kN, and in the samples taken from 63% of
locations (19 from 30) the shear flow varied from 2.0 mm to 4.0 mm. In
most cases, the bonding between the lower and upper asphalt layers on
different roads of Lithuania corresponds to the current requirements,
thus, it could be assumed that the asphalt underlayer has been prepared
properly. It should be also mentioned that the highest bonding values
between the upper and lower asphalt layers were recorded in those cases
where the upper layer was laid from the asphalt mixture SMA 11 S. In
those cases, the bonding strength value, required by the IT ASFALTAS 08,
is exceeded even up to two times. The higher shear flow was observed
where the upper asphalt layer was laid from the asphalt mixture SMA 11
S.
6. Conclusions and recommendations
In the result of analysis and assessment of theoretical principles
of the bonding between asphalt layers, research methods, worldwide
experience and of the results of experimental research, carried out in
Lithuania, the following conclusions and recommendations are given.
1. Sufficient bonding between asphalt layers ensures the
functioning of asphalt pavement as of the monolithic structure, and the
largest stresses from vertical loads are concentrated at the bottom of
the monolithic structure. In case of insufficient bonding between
asphalt layers the largest stresses occur at the bottom of each layer.
Such pavement structure can carry lower loads compared to that having
sufficient bonding between asphalt layers.
2. Due to insufficient bonding of asphalt layers, deformations
developed within asphalt pavement (tearing, corrugations, slippage of
layers, longitudinal cracks) worsen the driving conditions, reduce
pavement life cycle between repairs, increases pavement maintenance
costs. Due to insufficient bonding of asphalt layers the plastic
pavement deformations occur--ruts, and pavement durability can decrease
to 7 or 8 years.
3. Experimental research has indicated that the bonding strength
between asphalt layers decreases from 20% to 50% when the geogrid is
laid between asphalt layers.
4. The use of stress-absorbing asphalt layer between asphalt
pavement layers allows achieving the relatively high bonding between
asphalt layers. Experimental research showed that the bonding of asphalt
layer, constructed from this mixture, and the lower or upper asphalt
layers in all tested cases is higher than 22.0 kN under the relatively
high shear flow > 5 mm.
5. It was determined by the testing of asphalt pavement samples,
taken from different roads of Lithuania, that the bonding between the
upper and lower asphalt layers in most cases (83%) corresponds to the
requirements of IT ASFALTAS 08 and is higher than 15 kN. The bonding
values higher than 20 kN were detected at 50% of all studied locations.
The assumption could be made that the attainment of the required bonding
values between asphalt layers of the studied roads depend on a proper
preparation of underlayer, protection against pollution and the use of
optimum amount of bitumen emulsion.
6. During experimental research no difference was detected in the
bonding strength of asphalt layers depending on the sampling
location--in the track or in-between the tracks of the same road.
7. The bonding values for asphalt pavement layers, regulated by the
normative documents of Lithuania IT ASFALTAS 08 and IT APM 10, ensure
sufficient bonding of layers in respect of road pavement strength and
durability. However, it is recommended to supplement those normative
documents with the requirement when accepting works to control the
bonding strength of asphalt layers and the volume of control tests, also
to supplement the IT ASFALTAS 08 with the requirements for the control
of the bonding of asphalt layers when for the interlayers of asphalt
pavement the geosynthetic materials are used. In that case, the control
tests on the bonding between asphalt layers shall be obligatory for each
object.
8. For the determination of the bonding between asphalt layers the
shear test is recommended (without applying normal stresses). For the
determination of bonding between thin layers and the underlayer it is
recommended to use the peel test (direct tension). The German testing
methodologies are recommended to be used.
doi: 10.3846/bjrbe.2011.27
References
Bognacki, J. C.; Frisvold, A.; Bennert, T. 2007. Investigation of
Asphalt Pavement Slippage Failures on Runway 4r-22l, Newark
International Airport, 2007 FAA Worldwide Airport Technology Transfer
Conference, Atlantic City, New Jersey, USA.
Bondt de, A. H. 1999. Anti-Reflective Cracking Design of
(Reinforced) Asphaltic Overlays. PhD thesis. Delft University of
Technology.
Bulevicius, M.; Petkevicius, K.; Zilioniene, D.; Drozdova, K. 2010.
Testing of Physical-Mechanical Properties of Coarse Aggregate, Used for
Producing Asphalt Mixtures, and Analysis of Test Results, in Proc. of
the 10th International Conference "Modern Building Materials,
Structures and Techniques": selected papers, vol. 2. Ed. by
Vainiunas, P.; Zavadskas, E. K. May 19-21, 2010, Lithuania. Vilnius:
Technika, 1094-1098.
Canestrari, F.; Santagata, E. 2005. Temperature Effects on the
Shear Behaviour of Tack Coat Emulsions Used in Flexible Pavements,
International Journal of Pavement Engineering 6(1): 39-46.
doi:10.1080/10298430500068720
Charmot, S.; Romero, P.; Dunning, M. 2005. Forensic Analysis of
Slippage Cracking, TRB 84th Annual Meeting, Washington DC, USA.
Cygas, D.; Mucinis, D.; Sivilevicius, H.; Abukauskas, N. 2011.
Dependence of the Recycled Asphalt Mixture Physical and Mechanical
Properties on the Grade and Amount of Rejuvenating Bitumen, The Baltic
Journal of Road and Bridge Engineering 6(2): 124-134.
doi:10.3846/bjrbe.2011.17
Frohmut, W.; Ascher, D. 2007. Untersuchungen zur Wirksamkeit des
Haftverbundes und dessen Auswirkungen auf die Lebensdauer von
Asphaltbefestigungen, [Studies on the Effectiveness of the Adhesive Bond
and Its Impact on the Life of Asphalt Pavements] Schlussbericht zum
AiF-Projekt [Final Report on Project AiF] No. 13589 BR/1, Technische
Universitat Dresden.
Hachiya, T.; Sato, K. 1997. Effect of Tack Coat on Bonding
Characteristics at Interface Between Asphalt Concrete Layers, in Proc.
of the 8th International Conference on Asphalt Pavements. Seattle, USA.
349-362.
Harvey, J. T.; Hoover, T.; Coetzee, N. F.; Nokes, W. A.; Rust, F.
C. 1999. Caltrans Accelerated Pavement Test (CAL/APT) Program--Results
from Tests on Asphalt Pavements 1994-1998, in Proc. of the 7th
Conference on Asphalt Pavements for Southern Africa, CAPSA '99,
Victory Falls, Zimbabwe.
Hu, X.; Walubita, F. L. 2011. Effects of Layer Interfacial Bonding
Conditions on the Mechanistic Responses in Asphalt Pavements, Journal of
Transportation Engineering 137(1): 28-36.
doi:10.1061/(ASCE)TE.1943-5436.0000184
Kruntcheva, M. R. 2004. Feasibility of Assessing Bond Condition of
Asphalt Concrete Layers with Dynamic Nondestructive Testing, ASCE
Journal of Transportation Engineering 130(4): 510-518.
doi:10.1061/(ASCE)0733-947X(2004)130:4(510)
Lepert, P.; Poilane, J. P.; Villard-Bats, M. 1992. Evaluation of
Various Field Measurement Techniques for the Assessment of Pavement
Interface Condition, in Proc. of the 7th International Conference on
Asphalt Pavements. Nottingham, UK, vol. 3. 224-237.
Leutner, R. 1979. Untersuchungen des Schichtenverbunds beim
bituminosen Oberbau Investigation of the Adhesion of Bituminius
Pavements [Investigations of the bituminous layers composite
superstructure Investigation of the Adhesion of Bituminius Pavements],
Bitumen 3: 84-91.
Mirn Recasens, R.; Perez Jimenez, F.; Borr?s Gonz?lez, J. M. 2003.
Evaluation of the Effect of Tack Coats. LCB Shear Test, in Proc. of the
6th RILEM Symposium PTEBM'03. Ed. by Partl, M. N. April 14-16,
2003, Zurich, Switzerland. Bagneux: RILEM Publications, p. 550-556.
Motiejunas, A.; Paliukaite, M.; Vaitkus, A.; Cygas, D.;
Laurinavicius, A. 2010. Research on the Dependence of Asphalt Pavement
Stifness upon the Temperature of Pavement Layers, The Baltic Journal of
Road and Bridge Engineering 4(1): 50-54. doi:10.3846/bjrbe.2010.07
Muench, S. T.; Moonmaw, T. 2008. De-Bonding of Hot Mix Asphalt
Pavements in Washington State: an Initial Investigation, Final Technical
Report TNW 2008.
Plug, C. P; Bondt de, A. H.; Hydra, R. 2010. Optimum Bonding of
Tthin Asphalt Overlays on Porous Asphalt. Research &
Development--Conference Papers, the 5th World Congress on Emulsions,
Lyon, France.
Raab, C.; Partl, M. N. 2004. Efect of Tack Coats on Interlayer
Shear Bond of Pavements, in Proc. of the 8th Conference of Asphalt
Pavements for Southern Africa (CAPSA04), September 12-16, 2004, Sun
City, South Africa. Document Transformation Technologies cc, 847-855 b.
Raab, C.; Partl, M. N. 2004. Interlayer Shear Performance:
Experience with Different Pavement Structures, 3rd Eurasphalt &
Eurobitume Congress Vienna 2004--Paper 081a.
Raab, C.; Partl, M. N.; Halim, A. E. 2009. Evaluation of Interlayer
Shear Bond Devices for Asphalt Pavements, The Baltic Journal of Road and
Bridge Engineering 4(4): 186-195. doi:10.3846/1822-427X.2009.4.186-195
Shaat, A. A.; 1992. Investigation of Slippage of Bituminuos Layer
in Overlaid Pavement in Northern Ireland. Consultancy Report Submitted
for the DOE in Northern Ireland, Belfast, UK.
Sholar, G. A.; Page, G. C.; Musselman, J. A.; Upshaw, P. B.;
Moseley, H. L. 2004. Preliminary Investigation of a Test Method to
Evaluate Bond Strength of Bituminous Tack Coats, Journal of the
Association of Asphalt Pavement Technologists 73: 771-806.
Sutano, M. H. 2004. Analisis kekuatan rekat lapisan perekat (tack
coat) sebagai perekat antara lapisan permukaan hot rolled sheet (HRS)
dengan lapisan pondasi asphalt treated base (ATB), Master Thesis,
Institut Teknologi Sepuluh November, Surabaya, Indonesia.
Tashman, L.; Nam, K.; Papagiannakis, T. 2006. Evaluation of the
Influence of Tack Coat Construction Factors on the Bond Strength Between
Pavement Layers, Report No. WCAT 06002, Washington Center for Asphalt
Technology.
West, R. C.; Zhang, J.; Moore, J. 2005. Evaluation of Bond Strength
Between Pavement Layers, NCAT Report 05-08. Received 26 January 2009;
accepted 21 March 2011
Table 1. The recommended values for the shear flow of asphalt
layers
Name of document ZTV M-V Arbit No. 60
Underlayer Shear flow, mm
Between the upper and 2.0-4.0 2.0-5.0
lower asphalt layers
Between the lower and 1.5-3.0 1.0-4.5
base layers
Table 2. Sampling locations in the Vilnius City
Sampling location Number of
asphalt samples
(cores), units
The Vilnius City STA 28+15 leftside 2
Western
By-pass, Oslo g. STA 37+12 right side 2
Savanoriu pr. 7.0 m from the road 3
sign (Kaunas 92,
Klaipeda 303) in
Kaunas direction,
right side
Plytines Numbered in schemes 3
street, behind included into the
the turn to the testing protocols
Plytines
cartodrome, in
Dvarcionys direction No. 1-2322 and 1-2323 3
Kalvariju g., from 21.0 m from the 1st 2
Zvalgu g. in entrance to the
petrol station
Alausa, left side
Ozo g. direction 3.0 m in front of 2
the entrance to the
petrol station
Alausa, right side
Eisiskiu road Numbered in schemes 3
included into the 3
testing protocols
No. 1-2324, 1-2325, 3
1-2326, 1-2327
3
Type of geosynthetic
material or special
asphalt mix in the
interlayer
The Vilnius City VIASAF 0/5
Western
By-pass, Oslo g. (under the lower layer)
Savanoriu pr. VIASAF 0/5
(under the upper layer)
Plytines Pavegrid G100/100
street, behind (under the lower layer)
the turn to the
Plytines
cartodrome, in
Dvarcionys direction --
Kalvariju g., from --
Zvalgu g. in
Ozo g. direction Pavegrid G100/100
(between the upper and lower
layers)
Eisiskiu road HATelit C 40/17
(under the lower layer)
Armatex RSM 50/50
(under the lower layer)
--
Table 3. Sampling locations
The mix
of asphalt
upper
Sampling location layer
Road No. 153 1.6 km, left in the track AC 11 VS
Joniskis-Zagare side, 2.2 m
from the road
axis
1.4 km, right in the track
side, 2.2 m
from the road
axis
1.1 km, right in-between the
side, 1.6 m tracks
from the road
axis
Road No. 143 17.0 km, left in the track AC 11 VN
Jonava-Zasliai- side, 2.4 m
Kalniniai- from the road
Mijaugonys axis
16.0 km, left in-between the
side, 1.4 m tracks
from the road
axis
15.7 km, right in the track
side, 2,2 m
from the road
axis
15.7 km, right in the track AC 11 VS
side, 2,2 m
from the road
axis
15.7 km, right in-between the
side, 2.2 m tracks
from the road
axis
Road No. 130 34.0 km, left in the track AC 11 VS
Kaunas-Prienai- side, 2.6 m
Alytus from the road
axis
33.9 km, left in-between the
side, 1.7 m tracks
from the road
axis
22.95 km, left in the track
side, 2.7 m
from the road
axis
22.85 km, left in-between the
side, 1.7 m tracks
from the road
axis
Road No. 128 26.0 km, in the in the track AC 11 VS
Valkininkai track, 2,6 m
railway from the road
station-Daugai- axis
Alytus
26.05 km, left in the track
side, 2,7 m
from the road
axis
25.95 km, left in-between the
side, 1.9 m tracks
from the road
axis
Road No. 102 48.06 km, left in the track SMA 11 S
Vilnius- side, 2.4 m
svencionys- from the road
Zarasai axis
48.11 km, left in-between the
side, 1.5 m tracks
from the road
axis
48.16 km, left in the track
side, 2.3 m
from the road
axis
Road No. 2828 1.0 km, left in the track AC 11 VN
Alanta- side, 1.8 m
Naujasodis- from the road
Svobiskelis axis
1.05 km, left in-between the
side, 1.2 m tracks
from the road
axis
1.1 km, left in the track
side, 1.8 m
from the road
axis
Road No. A4 48.0 km, right in the track AC 11 VS
Vilnius- side, 2.3 m
Varena- from the road
Gardinas axis
48.1 km, right in-between the
side, 1.7 m tracks
from the road
axis
48.25 km, right in the track
side, 2.3 m
from the road
axis
Road No. A14 12.0 km, right in the track SMA 11 S
Vilnius-Utena side, 7.1 m
from the road
axis
12.3 km, right in-between the
side, 6.3 m tracks
from the road
axis
13.0 km, right in the track
side, 7.1 m
from the road
axis
14.4 km, left in the track
side, 2.1 m
from the road
axis
14.2 km, left in-between the
side, 2.9 m tracks
from the road
axis
14.17 km, left in the track
side, 2.1 m
from the road
axis