Application of finite element method in pile wall modeling.
Prskalo, Maja ; Colak, Anela
Abstract: The method used in this paper to protect a construction
pit by a pile wall is based on checking the stability of the pile wall
in the program GE05--FEM (Finite Element Method), which gives values of
stresses and strains in soil Since safety factors obtained by the
program were small, indicating structural instability, it is necessary
to additionally support the structure by struts. The adopted solutions
obtained in Sheeting Check (GEO 5) are based on Eurocode 7, specifically
using the design approach DA1, combination 1 and combination 2, adopting
adequate partial coefficients
Key words: construction pit, pile wall, finite element method,
Eurocode 7
1. INTRODUCTION
The common geotechnical practice is to use modern numerical
methods, such as the finite element method, differential method, and
boundary element method. These methods model the soil-structure
interaction and analyze stress-strain states in the foundation soil and
structure in all construction stages. Unlike usual analytical methods,
which directly calculate dimensions of support structures (such as
anchors, struts etc.), numerical methods require support structures to
be predefined (Logar, 2009).
2. PREVIOUS RESEARCH
Various theoretical and numerical procedures are developed to
obtain approximate solutions of real distribution of stresses in a
structure-soil interface. A practically reasonable approximation of the
actual state is achieved by developing numerical procedures and
thoroughly investigating deformation properties of soil (Veric, 2000).
GEO5 is a set of programs designed for solving geotechnical
problems and each of the programs is intended for solving a different
geotechnical problem. The programs are based on the analytical
calculation method and finite element method (FEM), Figure 1. By using
the finite element method, the FEM program evaluates stresses and
strains in soil around a structure and stability of the structure.
Finite element method computations of the FEM program established that
our sheet-pile wall was unstable without support, i.e. without a strut.
For that reason, further computations were carried out using the
Sheeting Check program, with a strut placed 3.0 in depth and sized based
on acting forces. Sheeting Check allows wall stability testing and
provides moments and forces acting on the pile wall.
3. NUMERICAL METHODS
With these calculations, we obtain ultimate states of bearing
capacity in terms of characteristic values of parameters of soil and
structure and characteristic geometry of elements of the structure,
anchor and strut, which are considered as linear elastic elements with
regard to actual characteristic stiffness.
Sizing is performed based on values of forces obtained according to EC7, with application of partial factors.
The geotechnical Eurocode (Eurocode 7, 1997) consists of two parts:
* EN 1997-1 Geotechnical design--Part 1 : General rules
* EN 1997-2 Geotechnical design--Part 2: Ground investigation and
testing.
The entire structure and stiffness of structural elements must be
predefined for calculation according to the finite element method.
Diaphragm should be calculated as elastic linear elements with constant
stiffness. For the C25/30 quality concrete, 30 GPa is adopted as the
value of modulus of elasticity. The volume weight of concrete is
[gamma]=25 kN/m3.
Structural calculation is generally carried out in the following
steps:
* selection of characteristic values of material parameters,
* selection of the depth to which piles are driven,
* stress-strain analysis of the structure using the finite element
method and sizing of elements of the protective structure,
* calculation of active pressures and equivalent forces acting on
the pile wall.
4. EXAMPLES OF NUMERICAL MODELING
Calculations of stability and strains of a pile wall solution 40 cm
in thickness were carried out by geostatic analyses. After that, sizing
of piles and strut elements was performed. We selected the piles 400 mm
in diameter and 11 and 12 m in length, with the axis-to-axis distance of
70 cm. Considering the presence of groundwater above the design
excavation bottom, a low-permeability barrier was used as the design
solution to protect the construction pit. Grouting decreased
permeability of the medium and made the whole barrier low-permeable.
Temporary struts were also placed as an extra protection measure because
the pile wall alone did not provide sufficient safety.
[FIGURE 1 OMITTED]
[FIGURE 2 OMITTED]
Struts were placed horizontally to support strut beams along the
pile wall. Metal HEB profiles, sized according to acting forces, were
used as struts and strut beams. One of the solutions obtained using the
finite element method in the FEM program is shown in Figure 2.
It is always necessary to choose a suitable model of soil with
adequately described changes that occur when excavating a construction
pit. To model such problems, it is generally appropriate to use a
non-linear model of soil with consolidation (e.g. the Hardening Soil
Model) because of non-uniform pressures. For simplicity of the example,
an ideal elasto-plastic Mohr-Coulomb model of soil, with characteristics
equal to those applied in the analytical calculation, is selected here.
Some computer programs for design based on the finite element method
also allow numerical calculations of groundwater flows in stationary and
non-stationary conditions. Effects of moments and transverse forces on
the pile wall were calculated according to the design approach 1,
combinations 1 and 2, with values of partial safety factors shown in
Table 1.
The value of active pressure acting on the pile structure is taken
as a continuous load on the strut beam. This solution is conservative
because it assumes that the strut beam takes the full equivalent force
of active pressure, fully disregarding rigidity of the pile wall, but it
is on the safe side and justified in view of possible consequences of
oversizing. Values of active pressure forces are applied as a continuous
load and we obtained the maximum values of moment and transverse forces,
horizontal displacement and pressures on the diaphragm under effects of
the active pressure, Table 2, Figures 3, 4.
[FIGURE 3 OMITTED]
[FIGURE 4 OMITTED]
5. CONCLUSION
To ensure safe work during construction of the foundation and
basement, the construction pit situated close to urban environment (two
structures, roads and underground installations) was protected according
to design elements and investigation results.
Sizing of the pile wall was carried out on the basis of the forces
computed using the software suite (GEO5, 2010). Results of calculations
based on the finite element method gave the values of maximum moment,
maximum transverse force, and maximum horizontal displacement of the
diaphragm according to Eurocode 7, design approach 1, combinations 1 and
2, with previously defined parameters of the support structure, and they
serve as a basis for further pile wall stability calculations.
6. REFERENCES
Eurocode 7, (1997). Part 1 (BS EN 1997-1) Geotechnical design
-General rules and Part 2 (prEN 1997-2) Ground investigation and testing
Logar, J. & Pulko, B. (2009). Prirocnik za projektiranje
gradbenih konstrukcij po evrokod standardih (Guide for design of
engineering structures according to Eurocode standards), Evrokod 7:
Geotehnicko projektiranje, Univerza v Ljubljani, Fakulteta za
gradbenistvo in geodezijo, ISBN: 978-961-6724-03-6, Ljubljana
Prskalo, M. (2011). Zbirka rijegenih zadataka iz Mehanike tla s
primjenom EC 7 (Book of solved problems in soil mechanics with
application of EC7), Faculty of Civil Engineering, University of Mostar
Veric, F. (2000). Savitljive temeljne konstrukcije (Flexible
foundation structures), Authorized lectures, Faculty of Civil
Engineering, University of Zagreb, Institute for Geotechnics
*** GEO 5 (2010) FEM, SHEETING CHECK, Software, version 5.10.32.0,
www.finesoftware.eu
Tab. 1. Values of partial safety factors for support
structures--design approach PP1 (Prskalo, 2011)
Design
approach
DA 1 Effects
Combination [[gamma].sub.G] = 1.35
1 [[gamma].sub.Q] = 1.5
Combination [[gamma].sub.G] = 1.35
2 [[gamma].sub.Q] = 1.5
Design
approach Soil
DA 1 parameters
Combination [[gamma].sub.[phi]] = [[gamma].sub.c] 1.0
1 [[gamma].sub.cu] = 1.0
Combination [[gamma].sub.[phi]] = [[gamma].sub.c] 1.0
2 [[gamma].sub.cu] 1.0
Design
approach Soil resistance
DA 1 RI
Combination [[gamma].sub.R;e] = [[gamma].sub.R;v] 1.0
1 [[gamma].sub.R;h] = 1.0
Combination [[gamma].sub.R;e] = [[gamma].sub.R;v] 1.0
2 [[gamma].sub.R;h] = 1.0
Tab. 2. Results of calculation according to the finite element
method
Horizontal
displacement
of the
Design [M.sub.max] [Q.sub.max] diaphragm
approach DAI (kNm/m) (kN/m) [U.sub.max] (mm)
Combination 1 202.64 167.94 10.5
Combination 2 150.69 127.50 9.1