Analysis of productivity based on production line balancing.
Taucean, Ilie Mihai ; Tamasila, Matei ; Cociu, Nicolae 等
1. INTRODUCTION
Productivity is the measure on production efficiency. While
productivity is the amount of output produced relative to the amount of
resources that go into the production, efficiency is the value of output
relative to the cost of inputs used. Productivity improves when the
quantity of output increases relative to the quantity of input.
Labour productivity is generally held to be the same as the
"average product of labour" (average output per worker or per
worker-hour, in physical or price/value terms).
Productivity, in production, is the relationship between output of
goods and services and the inputs of resources used in the production
process. A change in productivity is characterized by a shift of the
production function and a change to the output/input relation (Saari,
2005):
Productivity = Output/Input (1)
2. PRODUCTION LINE BALANCING. CASE STUDY
Production line balancing supposes preparing following steps
(Guerra, 2009):
* breakdown of technological processes in operation, phases,
transitions;
* determination of phases succession and predecessors (precedence
rules);
* repartition of each phase to an workplace/workstation or worker
in order of their execution;
* the concomitant execution of operations at all workplace and with
a rhythm of the tact time.
Tact time is the time or pace necessary for a product component to
be produce at one workplace of the production line and is the maximum
time from all operations/phases time (Co, 2009). In table 1 we have an
example, from our case study, of line balancing with a tact time of 5
minutes.
The problem here is to determine the optimum tact time for a
maximum productivity and for a production volume that is effective for a
given enterprise. For this we can use the breakeven points (the volume
of production), between which the enterprise is profitable.
In our case study, the values of these two points are given by the
enterprise and are 23000 and 40000 products per year. These correspond
to a tact time from 3 to 5.1 minutes, as can be seen in the table 2,
based on the following equations:
Q = Tt/t [products/year] (2)
N = Cycle time [jobs] (3)
Loading = No of jobs * t [min/job] (4)
Loading rate = (5) Loading/Cycle time [%] (5)
W = Q/N [pcs/job * year] (6)
Where: Tt is the time available in a year (in our case is 118560
minutes/year); Q is the volume of the production per year; W is the
productivity; N is the number of jobs/workplace or workstations; t is
the tact time. The minimum tact time in our case is 1.1 minutes, which
is maximum of all phase's time. The total cycle time for production
line is 25.75 minutes.
In table 2 are presented the theoretical values of: number of jobs,
loading per job, loading rate, quantity and productivity for each phase,
this is when we do not consider the real duration of each phase. For the
real values of productivity for our study case, we have the results
presented in table 3, with the differences calculated from the
theoretical values.
In figure 1, 2 and 3 we present, dependent on tact time, the
variations of productivity (theoretical and real from the study case),
volume of production (quantity of products produced) and the loading
rate (theoretical and real from the study case).
We can see from the figures that the real values are lower that the
theoretical ones, but the differences are generally not high (one job or
a maximum of 23% for loading rate). The maximum of productivity is for
tact time of 4 minutes, with 7 workplaces and a loading rate of 82.61%.
[FIGURE 1 OMITTED]
[FIGURE 2 OMITTED]
[FIGURE 3 OMITTED]
3. CONCLUSIONS
With all this information on a dashboard (Co, 2006), production
managers can decide the optimum way of line balancing, for a maximum of
productivity, or for a maximum of workplace loading, minimum of workers,
maximum of quantity needed (maybe more important for a certain period of
time).
The next step will be the benchmarking of this productivity with
key competitors on the market, to see if enterprise is competitive
(Porter, 1990). But the limitations here is the fact that every
competitor has unique/specific type and organization of production
process and the comparison is difficult and maybe with irrelevant results.
4. REFERENCES
Co, H.C. (2006). Operational Management, Available from:
www.csupomona.edu, Accessed on: 2010-06-16
Co, H.C. (2009). Assembly Line Balancing, Available from:
www.csupomona.edu/~hco/POM, Accessed on: 2010-06-16
Guerra, F. (2010). Work performance measurement in the start of a
new assembly line to achieve production target, Available from:
http://dimgruppi.ing.unibs.it/impianti/pubblicazioni.html, Accessed on:
2010-06-16
Michael, P. (1990). The Competitive Advantage of Nations, The Free
Press, ISBN 9780029253618, New York
Saari S. (2006). Productivity. Theory and Measurement in Business,
Proceedings of European Productivity Conference, Hannula, M. (Ed.), pp.
92-103, Espoo, Finland
Tab. 1. Example of line balancing with a tact time of 5 min
Phase Precedence T T accum. Loading Jobs
no phase min/pcs] min/pcs] [%] no.
1 -- 0.93 0.93 93.80% I
2 1 0.85 1.78
3 2 0.91 2.69
4 3 1.10 3.79
5 4 0.90 4.69
6 5 0.95 0.95 90.80% II
7 6 0.90 1.85
8 7 0.95 2.80
9 8 0.79 3.59
10 9 0.95 4.54
11 10 0.80 0.80 92.80% III
12 11 1.00 1.80
13 12 1.02 2.82
14 13 1.02 3.84
15 14 0.80 4.64
16 15 1.02 1.02 90.80% IV
17 16 0.78 1.80
18 17 1.02 2.82
19 18 1.01 3.83
20 19 0.71 4.54
21 20 0.90 0.90 96.80% V
22 21 1.02 1.92
23 22 1.00 2.92
24 23 1.02 3.94
25 24 0.90 4.84
26 25 1.00 1.00 50.00% VI
27 26 0.90 1.90
28 27 0.60 2.50
Tab. 2. Theoretical productivity based on tact time
t No of Load Loading Q W
[min/pcs] jobs min/job] rate [%] pcs/year] pcs/job]
3.0 9 27 95.40 39520 4392
3.1 9 27.9 92.30 38246 4250
3.2 9 28.8 89.40 37050 4117
3.3 8 26.4 97.50 35928 4491
3.4 8 27.2 94.70 34871 4359
3.5 8 28.0 92.00 33875 4235
3.6 8 28.8 89.40 32934 4117
3.7 7 25.9 99.40 32044 4578
3.8 7 26.6 96.80 31200 4458
3.9 7 27.3 94.30 30400 4343
4.0 7 28.0 92.00 29640 4235
4.1 7 28.7 89.70 28918 4132
4.2 7 29.4 87.60 28229 4033
4.3 6 25.8 99.80 27573 4596
4.4 6 26.4 97.50 26946 4491
4.5 6 27.0 95.40 26347 4392
4.6 6 27.6 93.30 25774 4296
4.7 6 28.2 91.30 25226 4205
4.8 6 28.8 89.40 24701 4117
4.9 6 29.4 87.60 24196 4033
5.0 6 30.0 85.80 23712 3952
5.1 6 30.6 84.20 23248 3875
Tab. 3. Real productivity based on tact time
[DELTA]
t No of [DELTA] No Loading W [DELTA] W
min/pcs] jobs of jobs rate [%] [pcs/job] [pcs/job]
3 10 1 -9.54% 3952 -440
3.1 10 1 -9.23% 3825 -425
3.2 10 1 -8.94% 3705 -412
3.3 10 2 -19.51% 3593 -898
3.4 9 1 -10.52% 3875 -484
3.5 9 1 -10.21% 3764 -471
3.6 9 1 -9.93% 3660 -457
3.7 8 1 -10.10% 4006 -572
3.8 8 1 -12.10% 3900 -558
3.9 8 1 -20.19% 3800 -543
4 7 0 -9.35% 4235 0
4.1 7 0 -9.13% 4132 0
4.2 7 0 -8.92% 4033 0
4.3 7 1 -22.97% 3939 -657
4.4 7 1 -22.44% 3850 -641
4.5 7 1 -13.62% 3764 -628
4.6 7 1 -13.33% 3682 -614
4.7 6 0 0.00% 4205 0
4.8 6 0 0.00% 4117 0
4.9 6 0 0.00% 4033 0
5 6 0 0.00% 3952 0
5.1 6 0 0.00% 3875 0