Energy management applications for recovering the heat from waste water.
Todoran, Radu Matei
1. INTRODUCTION
Our method is to recover the heat of the waste water from city
sewage. The yearly average temperature of the waste water in the sewage
is up to 12-13 degrees and the water can be used to recover a ratio of
their heat and to transfer it to buildings. On the other hand, the waste
waters' temperature is transferred to the environment and this is
leading to (especially when the waste water is dumped into lakes or
rivers) a significant alteration of the temperature of the recipient
environment, affecting the ecosystems. In industrial areas, especially
where there is heat generating processes the impact over the environment
is more significant because the heated water is dumped directly into the
environment or into the sewage.
The recherche we are presenting is highly applicative and does not
theoretical citations.
The method is to put on the bottom of the sewage pipe the heat
exchangers. The heat exchangers (see figure 1) will be submerged under
the waste water and thus will be able to capture a part of the waste
water heat using water-water heat pumps. We must emphasise that during
the summer the
system can act as cooling system, due to its reversing features,
only with small adjustments.
As advantages of the system we have to mention:
1. it is easy to adapt to any pipe shape section
2. it is easy to et up and is expandable
3. is not interfering the normal sewage works
4. long lifespan (over 50 years)
The data we have gathered after using this method are encouraging
and are recommend it as an alternative to other systems, in order to
stop the waste of energy:
a. waste water energy extracted--1-4 KWh/ m
b. investment cost--800-1800 euro/KW
c. CO2 annual saving--60-70%
d. heating cost saving--40-60%
e. amortization--4-10 years
[FIGURE 1 OMITTED]
2. EQUIPMENT TECHNICAL DATA AND WORKING PRINCIPLES
Therm Liner system is using the existing heating equipments of a
building, thus being connected directly to the building heating system
and provides 50 to 60 degrees hot water. The system features the
following modules:
a. existing heating network of a building
b. heating pump, replacing existing heating source
c. recirculation pump for transporting the heat exchange liquid
from the heat pump to heat exchanger and back
d. the heat exchanger placed in the sewage The working principle is
presented in figure 2.
The heat exchanger is made of 800 mm long sections of stainless
steel that can be put together easy using a Lego type system. There
shape and transversal section are custom made using the diameter and
shape of the pipe where is going to be placed. The objective is to have
a lower flow resistance and to ensure a higher heat exchange surface.
The dimensioning of the total length of the heat exchanger modules
is made based on the following data:
a. waste water flow (a minimum of 15 litres/second is recommended)
b. diameter of pipe (a minimum of 500 mm is recommended)
c. pipe gradient
d. waste water yearly average temperature.
Considering the above mentioned features, one can see that a
cluster of heat exchangers with a certain length can actually chill the
waste water too much. This conclusion will be entered in our computing
in order not to deactivate the bacteria performing the biological stage
in the treatment plant.
[FIGURE 2 OMITTED]
3. THERM LINER SYSTEM APPLIED TO A SCHOOL CAMPUS IN SEBES CITY
ROMANIA PROJECT TO BE FINANCED WITH EUROPEAN FUNDS.
The project was designed by the Uhrig team, the patent owners,
together with a group of specialists from the 1 Decembrie 1918
University in Alba Iulia.
For the given situation, two of the necessary prerequisites were
missing, namely the pipe diameter was below 500 mm and the pipe gradient
was below 1/1000. Considering this, we have decided to replace the
existing pipe over a distance of 70 meters with a new pipe featuring a
higher diameter (700 mm) and to assemble the heat exchanger into this
section. Due to the very small speed of the waste water flow, because of
the small gradient, our solution was to put a pneumatic controlled
mobile dam in front of the heat exchanger. The role of the dam is to
release the water 5 to 7 times a day in order to flood the heat
exchanger, thus washing and avoiding waste accumulation and, also, to
ensure a constant flow in the pipe be fixing it to a certain height.
The school campus comprise of four buildings as follows:
a. C1--building for primary school
b. C2--building for secondary school
c. C3--building for kindergarten
d. C4--sport hall
Foreseen solution:
a. waste water heat recovering system
b. water-water heat pump for heating the four buildings
c. heating network with static radiators for school and
kindergarten
Sewage characteristics
a. form--ovoid
b. dimensions--500x700 mm
c. gradient--1/1000
d. dry weather flow--68 l/s (minimum), 140 l/s (average)
e. waste water temperature--12 degrees minimum
f. available length--100 meters
g. heat transfer surface, fully submerged--0,58 sqm./m
h. microbiological deposit layer influence--40% Heat exchange
characteristics:
a. total length--80 meters
b. minimum extraction capacity--114 KW
c. heat pump power--31 KW
d. heating capacity--145 KW
e. heating pump performance factor--4,7
Economic features
Natural gas reduction--219750 KWh
CO2 reduction--48931 kg/year
Amortization with no incentives--4 years
4. Conclusions
We must emphasis that this project is finished in terms of design
and is ready to be submitted for financing. Also, worth mentioning that
our project is modern, reliable and efficient by featuring:
a. the use of renewable energy with the help of the most modern
heating source--the heat pump
b. lack of CO2 emissions, thus is contributing to the actions of
reducing the global warming
c. we are making a mixing of high capacity by capturing the
residual heat from sewage with low costs for investing and operating
d. comparing with a classic heating gas system, our system reduces
the heating costs with 55%
e. the project provides a long lifespan and reliability for the
beneficiary
f. the amortization period is short
g. the system is reversible, thus being able to provide cool air
with minimum of supplemental investment
h. the system allows other combination--it can be used as heating
system or as worm water supplier for other heating systems.
4. REFERENES
All, Heat Engineering Multilingual Dictionary, Ed. Tehnica,
Bucharest, 1997
Constantinescu, Dan, Heat Engineering, Ed. Agir, Bucharest, 2008
Damian, V., Dragan, M, Environmental policies in Energetic, Ed.
Academica, Galati, 2005
Mihaila, Cornel, Heat Engineering Issues, Ed. Tehnica si
pedagogica, Bucharest, 1975
Uhrig, Technical book for implementing Therm Liner, Geisingen,
26.02.2009
usage unit Therm Liner Classic
power KW 145 145
Year usage for heating h 3950 3950
Cold weather heating KWh 73250 293000
energy conventional
Cold weather heating KWh 219750
energy Therm Liner
Heat exchanger cost euro 248805
Drying cost euro 9520
Heat pump cost euro 35105
Conventional system cost euro 41412
Installation cost euro 32904 36282
Total cost euro 325524 77694
Annual savings in comparison
features unit base
Annual operating cost euro
Electricity cost euro 35
Gas cost euro 345
Electricity charge ct/K 12
Wh
Gas charge ct/K 31
Wh
Total annual operating euro
cost
Annual economy euro
%
features Therm classic
Liner
Annual operating cost 952 952
Electricity cost 35 35
Gas cost 345
Electricity charge 6201
Gas charge 22708 90830
Total annual operating 29896 92162
cost
Annual economy 62266
68