Economic engineering study regarding Aeolian installation manufacturing system using CPM and pert methods.
Vartolomei, Mihaela ; Milos, Teodor ; Vartolomei, Mihael 等
1. INTRODUCTION
Solar energy is the first energy source used by humans. It
represents essential element in mankind's development and there is
no way to be life on Earth without sun energy (Lazarescu, 2003). The
total solar energy intercepted by the Earth is 178 x [10.sup.9]MW, by
15.000 times more than mankind's current necessity. Medium density
of radiant flux on horizontal area is between 250 W/[m.sup.2], in Sahara
and 100W/[m.sup.2], in Central Europe (Ambros et al, 1999). The
Partnership Project this paper has started is called "Energetic
Supply for a Local Community Using Draughts". It will choose the
optimum solution for Aeolian turbine which will be manufactured by a
partner of the project. The peculiar of the project is the possibility
to choose the configuration of the turbine palette with the calibration
and simulation of the flow with the peculiar soft existent in the
University. In this paper, our attention is fixed on planning and
designing period of the Aeolian investment.
Non-fossil energy sources or energy renewable sources (ERS)
represents the environment resources, that are continuously regenerating
or in a certain periodicity and their consumption don't lead to a
possible depletion. These kinds of ERS are constantly renewed or
restored and include: sun (solar), internal heat of the earth
(geothermal energy), wind (wind power), vegetation (biomass), falling
water, tides, and wave motion (hydropower). A clear feature of ERS is
their independent existence by any man's consistently activity
(Ambros et al., 1999).
2. INVESTMENT DESIGNING PROCESS USING CRITICAL PATH METHODS (CPM)
2.1 CPM Principles
In this paper we call "work" the whole process of work
and manufacturing activities targeted towards execution and setting the
Aeolian investment.
The work has more activities. An activity represents the sum of
rather homogeneous operations, which participate to the achievement of a
part of the work.
The program is referring to tidy up activities executions, so that
the work frames in planned terms, without surpass resources allocated.
Every activity is formed by a throng of events (event is the physical
stage an activity can be at a certain moment). Any activity is bordered
upon two events: starting one and ending one. If the investment's
work (W) has n activities then:
A=([a.sub.1], [a.sub.2], ..., [a.sub.i]); i=1...n (1)
Where: A=throng of activities [a.sub.i]=activity i
In this investment situation, we had identified 7 activities, from
[a.sub.1] to [a.sub.7] (table 1). Furthermore, it is necessary to
introduce a succession relation between these activities. Thus, the
investment activities and events' graph (networks system of
oriented arcs, bordered by knots) is showed in figure 1. The arcs
represent the activities and the knots represent the start-end events.
Looking figure 1, we can notice that there are more paths from event 1
to event 7: [P.sub.12357], [P.sub.12457] and [P.sub.1267] (so called
full paths), the longest full path is called critic path:
[P.sub.12357]=180+30+360+60=630 days
[P.sub.12457]=180+30+300+60=570 days
[P.sub.1267]=180+360+0=540 days
[P.sub.cr]=max ([P.sub.12357], [P.sub.12457], [P.sub.1267])=
[P.sub.12357]=630 days
[P.sub.12357] is the critical path ([P.sub.cr]) because it has the
longest length. Thus, the uncritical path has time reserves (represents
the difference between maximum terms till activity execution is accepted
and possible minimum terms). There are four terms: minimum term of
activity start ([t.sub.i]), maximum term of activity start ([T.sub.i]),
minimum term of activity end ([t.sub.j]) and maximum term of activity
end ([T.sub.j]).
The minimum and maximum terms are established using optimality
principle (relation 2 and 3).
[FIGURE 1 OMITTED]
[t.sub.1]=max[P.sub.li] and [t.sub.j]=max[P.sub.lj] (2)
[T.sub.i]=[P.sub.cr]-max[P.sub.in] and
[T.sub.j]=[P.sub.cr]-max[P.sub.jn] (3)
Where n represents the final event of the work
Using minimum and maximum term of the events we can calculate time
reserve for each activity. So we have:
[t.sub.1]=0; [t.sub.2]=max[P.sub.12]= [P.sub.12]=180 days;
[t.sub.3]=max[P.sub.13]= [P.sub.123]=180+30=210 days;
[t.sub.4]=max[P.sub.14]= [P.sub.124]=180+30=210 days
[t.sub.5]=max[P.sub.15]=max ([P.sub.1235]; [P.sub.1245])=max(180+30+360;
180+30+ +300)=max(570;510)=570 days [t.sub.6]=max[P.sub.16]=
[P.sub.126]=180+360=540 days [t.sub.7]=max[P.sub.17]= [P.sub.15]+
[P.sub.57]=570+60=630 days [T.sub.7]=[P.sub.cr]-0=630 days
[T.sub.6]=[P.sub.cr]-[P.sub.67]=630-0=630 days [T.sub.5]=
[P.sub.cr]-[P.sub.57]=630-60=570 days
[T.sub.4]=[T.sub.5]-[P.sub.45]=570-300=270 days
[T.sub.3]=[T.sub.5]-[P.sub.35=570-360=210 days
[T.sub.2]=min([T.sub.3]-[P.sub.23; [T.sub.4]-[P.sub.24];
[T.sub.6]-[P.sub.26]) = min (310-30; 270-30; 630-360) = min (180; 240;
270) = 180 days [T.sub.1]=[T.sub.2]-[P.sub.12]=180-180=0 days
2.2 PERT Principle
The essential difference between CPM and PERT (Program Evaluation
and Review Technique Methods) is the execution period evaluation: CPM
the period is evaluated in a certain number of days, PERT the period is
appreciated in three situations: optimistic (the shortest,
"a"), pessimistic (the longest, "l") and probable
("b"). The average value is calculated with relation 4
(Dogaru, 2004):
[[bar.d].sub.ij] = a + 4b + l/6 (4)
[square root of [[sigma].sup.2]] = l--a/6 (5)
z = [d.sub.p]--[[bar.d].sub.n]/[[sigma].sup.2] (6)
Where: [[square root of [[sigma].sup.2]]--represents Average
Squared Deviation
[[sigma].sup.2]--represents Dispersion
z--represents probability factor
[d.sub.p]--represents planned duration of investment
[[bar.d].sub.n]--investment average duration
If planned term of investment execution is 366 days, the
probability factor is 0.127 (using relation 6).
Then using Laplace function and interpolation methods we obtain the
probability of 54.09% that indicate a proper programming (under 25% it
means very short term and above 60% indicates many time reserves, so it
will be redacted).
2.3 PERT/time
After program finalizing in its optimum variant, we'll
elaborate Gantt graphic.
2.4 PERT/cost
A very important facility of this method is that prolonging
execution dates of some activities, in the framework of time reserves,
it is possible to obtain cost reduction linked by the work deployment
(Buglea, 2002). This is why this model is known in scientific literature
as cost-time function optimization. In some condition, the investment
execution period can be shorted, but this supposes cost increase
(urgency cost). But also, an exaggerated prolonging can produce
certainly cost increases (figure 2) (Popa, 2005).
[FIGURE 2 OMITTED]
2.5 Work launching and execution
After the convenient variant is chosen, and after all terms was
established, we go to the investment launching process, redrawing Gantt
graphic depending by chosen variant, needed resources and mean for
achieve any activity in established terms, passing, step by step Gantt
graphic. Any modification in the system leads to the program
re-optimization.
3. CONCLUSIONS
In planning and designing process of our project Aeolian investment
in good conditions, we use Critical Path Methods. First we ordered
different activities so that the final results to correspond with the
main target of the project, from terms and resources allocation points
of view (Anton et al., 2007). The designing process supplies data about
economic and technical optimum and the planning process bunches economic
and technical optimum with social optimum.
4. REFERENCES
Ambros, T.; Arion, V.; Gutu, A.; Sobor, I.; Todos, P.; Ungureanu,
D. (1999). Energy Renewable Sources, Tehnica-Info Publishing House,
Chisinau, ISBN 9975-91079-3
Anton, L.E.; Baya, A.; Milos, T.; Stuparu, A. (2007), Experimental
Hydrodynamics, "Orizonturi Universitare" Publishing House,
ISBN 978-973-638-330-4.
Buglea, A. (2002). Investments and Their Financing, West University
Publishing, Timisoara, ISBN 973-8433-13-4
Dogaru, V. (2004) Statistics in Economy, Eurostampa Publishing
House, Timisoara, ISBN 973-687-269-6
Lazarescu, S. (2003). Energetic Concepts and Wind Energy
Utilization, Orizonturi Universitare Publishing House, Timisoara, ISBN
973-638-039-4
Popa, A. (2005). Investments Efficiency, Sitech Craiova, ISBN
973-746-059-6
Tab. 1. Investment activities and execution time.
Activity Start-end Activity name Activity Symbol
symbol events time (in of right
days) preceding
activity
[a.sub.1] 1,2 Execution 180 --
project
elaboration
[a.sub.2] 2,3 Work space 30
organization
[a.sub.3] 3,5 Building 360 a2
execution
[a.sub.4] 2,4 Equipments 30 a1
contraction
4,5 Equipment 300 a4
acquisition
[a.sub.6] 5,7 Equipment 60 a3
assembling
[a.sub.7] 2,6 Prepare for 360
manufacturing
Tab. 2. Average Squared Deviation and Dispersion
Act. Activity duration [square [square
symb root of root of
[[sigma] [[sigma]
a b 1 [d.sub.n] .sub.2]] .sub.2]]
1 2 3 4 5 6 7
[a.sub.1] 160 175 220 180 10 100
[a.sub.2] 20 30 40 30 3.33 11
[a.sub.3] 300 360 420 360 20 400
[a.sub.4] 20 30 40 30 3.33 11
[a.sub.5] 250 290 390 300 23.33 544
[a.sub.6] 40 60 80 60 6.67 44
[a.sub.7] 300 360 420 360 20 400
Tot. 520 625 760 630 x 555