Expert system for automated offering following a feature based approach.
Duerr, Holger ; Teich, Tobias ; Anh, Tran Ngoc 等
1. INTRODUCTION
The following procedures included in the three steps given below
are focused in a research project, which lead to this paper:
* Feature based design (FBD) of components and manufacturing
elements by means of a feature database--Computer Aided Design (CAD)
* Feature based main planning and specification of the
manufacturing equipment--Computer Aided Manufacturing (CAM)
* Offering based on calculated machining times and pre-calculated
production costs
This contribution is focused on making the offers in an integrated
automated way. Thus, we could demonstrate that offering can be executed
automatically and with sufficient accuracy of results. Within this
context, the results obtained by main planning of the technological
sequence are absolutely sufficient at the offering stage. When
determining costs with this methodology, production time is calculated
in a feature oriented way, and the characteristics of machine cost per
hour are taken into consideration.
2. FEATURE BASED OFFERING
2.1 Overall concept
The general feasibility of the product is verified according to geometric, technological and physical properties. To do this, queries
with corresponding information about individual technical elements of
the product are sent to the database of the resource model. In this
step, it can be determined whether the resources necessary to
manufacture the individual geometrical shapes within particular
constraints are existent. As a result, we obtain a set of manufacturing
steps for the product. These steps are the basis for determining the
manufacturing times and costs.
2.2 Feature-based design of the product's requirements
"Features" denotes the following: Features are regarded
as objects used to represent work pieces, and these objects have
functional, geometric and technological properties. They can also
include specific application-oriented data, such as times and costs
(Ehrenspiel & Kiewert 2007).
According to our methodology, the following steps must be followed
for feature representation:
* Define a work piece coordinate system
* Represent global information
* Decompose work piece geometry by feature classes (base-,
transition-, manufacturing- and machining shapes)
* Allocate dimensional relations to features
* Allocate technological requirements
* Generate feature catalogue as a means of communication among
designing engineers and production planners.
The feature classes should be defined in a manner as closely
related to the product as possible. Differentiating feature classes
first of all makes it possible to simplify representation of location.
The base shape features represent the work piece's initial shape.
Manufacturing- and Machining features are understood as surface
modifications to base shape features. Transition shape features are edge
modifications of marginal contours. From the perspective of costs, they
are irrelevant to the estimating process. For application of the feature
description model, STEP (Standard for the exchange of product model
data) is used. This ISO-Standard is segmented into different AP
(Application Protocol). For our requirements AP 224 is suitable and is
used for description of the demanded product. In Chapter 2.3, we
introduce modeling of the manufacturing resources and rough process
planning as another prerequisite for determining manufacturing times and
costs.
2.3 Competency-based modeling of the manufacturing resources and
rough process planning
The individual SMEs' competencies include human resources (engineering services, qualifications and levels of experience, know-how
etc.), manufacturing resources (machinery, equipment and related items)
and technologies ( manufacturing methods, etc.) (Durr et al. 2001; Hanel
et al. 2006; Lassig et al. 2006). Competency-based descriptions of
resources make it possible to balance product requirements and
manufacturing capacities with each other, in order to generate
technologically relevant process variants (Teich et al., 2008).
The technologically feasible process variants are generated as a
result of feature-based balancing of product requirements (demand
vector) with available resources (offer vector). This means, that for
each feature of the customer's demand, a machine is assigned
automical.
This process information is the basis for the concept used to
calculate the manufacturing costs outlined in chapter 2.4.
2.4 Determining manufacturing times and costs
The determination of manufacturing time and costs is divided into
two steps. For the accurate time determination, our model relies on the
on the REFA time diagram (REFA 1997), which is briefly introduced in
figure 1.
[FIGURE 1 OMITTED]
Machining time [t.sub.h] is calculated based on features with
sufficient accuracy. Time is computed according to the known equations
for each manufacturing technology. The determination of manufacturing
costs is the second step in the automated offering model introduced in
this paper. Costs can be determined using different calculation methods
like global estimating of allowances, direct cost calculation or
estimating the machine costs per hour.
To achieve sufficient accuracy when calculating the production
cost, we chose the paradigm based on machine cost per hour. The function
of machine cost per hour includes the addition of overhead costs proportional to the used machine time. Machine costs per hour [k.sub.hM]
are calculated using the ratio of the total of machine-related
manufacturing overhead cost types per annum [K.sub.Mach]. to possible
annual machine time [T.sub.N] at the planned degree of utilization:
[k.sub.hM] = [K.sub.Mach.]/[T.sub.N] ([member of]/h]) (1)
The Machine-dependent manufacturing overhead cost (Mach.-depend.
FGK) of a batch corresponds to machine costs per hour [k.sub.hM]
multiplied by manufacturing time [T.sub.Fz].
[MATHEMATICAL EXPRESSION NOT REPRODUCIBLE IN ASCII] (2)
The machine dependent production overhead costs are calculated
automatically based on the feature description applied to each, demand
and supply. The cost of production can then be determined by the scheme
shown in table 1, including direct costs for production material, labor
and special costs of production as well as overhead costs for material
and production.
3. CONCLUSION
The project focuses on integrated and automated estimating based on
feature modeling and competency-based resource description in virtual
production networks. The authors were able to verify that it is possible
to draft estimates using a method that is both automated and
sufficiently accurate. Generating a rough plan of the technological
sequence is entirely sufficient at the estimate stage. Cost calculation
is centered on feature-oriented calculation of production time and uses
characteristics of machine costs per hour. Implementation of the entire
concept on a computer was demonstrated with selected manufacturing
examples.
4. REFERENCES
Durr, H.; Mehnert, J. & Teich, T. (2001) Integration of
decentral Developing and Process Planning Competence into the model of
Extended Value Chain Management, Proceedings of DAAAM, International
Symposium: Intelligent Manufacturing & Automation, 24.-27. October,
S. 125, Jena, ISBN-Nr.: 3-901509-19-4
Ehrlenspiel, K.; Kiewert, A. & Lindemann, U. (2007)
Kostengunstig Entwickeln und Konstruiere, Springer, Heidelberg
Hanel, T.; Shatyan, A. & Durr, H.(2006) Development and
evaluation of competence profiles in non-hierarchical production
networks, Proceedings of FAMP06, Flexible Automation & Intelligent
Manufacturing, Limerick, June 26th-28th, Ireland, ISBN--Nr.: 1874653933
Lassig, J.; Heinrich, S. & Durr, H. (2006) Supply Chain
Executive Monitor for Controlling and Failure Management in Supply
Chains, DAAAM International Scientific Book 2006, S. 395-408, Published
by DAAAM International, ISBN 3-901509-47-X, ISSN 1726-9687, Vienna,
Austria
Mehnert, J. & Durr, H. (2004) Generation and Evaluation of
technological Search Patterns for the target-exact Addressing of
potential Suppliers Proceedings of FAM'04 Flexible Automation &
Intelligent Manufacturing, Toronto, Canada, July 2004, ISBN--Nr.:
0-662-37218-2
REFA (1997) Worterbuch der Arbeitswissenschaft, Verband fur
Arbeitsstudien und Betriebsorganisation (Hrsg.), Carl Hanser Verlag,
Munchen
Teich, T.; Zimmermann, M.; Unger, K. & Militzer, J. (2008)
Functional Characterization of Resources for Automatic Request Handling,
Proceedings of the Fifteenth International Working Seminar on Production
Economics, Innsbruck (Austria), March 3th-7th, vol. 4, pp. 213-225
Table 1: Basic methodology of cost calculation for estimating
Selling price
Prime costs
Cost of production (model for
feature-oriented estimating)
Material costs Manufacturing costs
Production material Direct labor costs
Material overhead cost Machine-dependent production
(allowance proportional to overhead costs (feature-oriented)
production material)
Residual production overhead costs
(allowance proportional to direct
labor costs)
Special direct costs of production
Administration- and sales overhead costs (allowance
proportional to production costs)
Special direct selling costs
Profit margin (as a percentage of prime costs)