The alternative procedure of lot size determination in flexible manufacturing systems.
Vazan, Pavel ; Moravcik, Oliver
Abstract: The paper presents the way how to use simulation
optimization for determination of lot size in FMS. It provides the basic
methods and procedures. The simulation optimization can be alternative
procedure to classic analytical methods. This procedure involves more
factors that influence lot size, than analytical methods. Therefore it
is more accurate.
Key words: Batch production, lot size, simulation, simulation
optimization
1. INTRODUCTION
The lot size is the number of pieces which is processed at the same
time at one workplace with one-off (time) and at the same costs
investment for its set up. (Tomek, 1999) The lot size is one of the
directions of production which markedly influences production costs.
There are several known methods for determination of lot size in the
world. Many of them have attribute "optimal" directly in their
name but the problem of correct lot size determination remains the
problem. The authors will demonstrate the possibility of usage of
simulation optimization for calculation of lot size.
2. STATE-OF-THE-ART
There are mainly used analytical methods for determination of lot
size. These methods try to express lot size by mathematical relation in
dependence on time used to set up workplace and piece of time, for
example the method of so called capacitance of lot size. The lot size,
so called economically optimal lot size is often used. This lot size is
expressed by mathematical model. The solution of compromise between the
reduction of fixed costs per piece and increasing of lot size and on the
other side increasing of the storage costs (Gregor, 2000).
The other methods are based on empirically found variables with
many defects. There are used different approaches, e.g. optimal lot size
is defined in many possibilities and chosen is the one with its own
minimal costs. There is included e.g. optimal lot size according to Teplov or Bankovsky (Gregor, 2000).
Management attempts to set up the same lot size in the same
planning periods. The lot size is calculated as a part of annual
capacity suitable for relevant planning period. This is a simple
principle of periodical lot size.
In spite of the fact that classic calculation methods of lot size
have optimal size in their title, they usually consider only few factors
which influence lot size. That is why the attribute "optimal"
is applied only for strictly defined conditions. The necessary input
values set up costs or storage costs are in fact qualified
approximations but not exact values. These calculated optimal lot size
are at least approached to optimal values (Potoradi,1999).
Lot size is also influenced by other factors not only by considered
classic methods of calculation. Here belong: production type,
orientation of material flow, system flexibility, organization of
manufacturing process etc. Of course, these factors do not include
analytical methods (Habchi, 1995). During the determination of lot size
it is necessary to take into consideration also conceptions which are
used in planning and control of production. Systems coming out from MRP expect constant lot size through the production process. Conceptions
coming out from JIT philosophy consider lot size as one piece in ideal
case (Khan, 2002). But systems using OPT accept changeable lot size.
Contemporary approaches of determination of lot size are focused on
mathematical models that minimize costs. Such approach is used for
determination of so called Economic Manufacturing Quantity. The reason
of high costs is not solved. Many authors accept that the best method to
verify optimal lot size is simulation way (Gregor, 2000, Habchi, 1995)
Potoradi, 1999, Ramaswami, 2006). Software tools for simulation model
design of production system reached such level of development that the
simulation model design lasts few days. The simulation models of
production system have high accuracy and they allow to test the
behaviour of production system for chosen lot size. It is possible by
the simulation way to follow many factors that influence correct lot
size. The results of simulation experiments may totally follow the
chosen production goals. These goals are not only costs but also flow
times, work in process, usage of capacities, number of produced parts
etc. The simulation connected with simulation optimization may be
appropriate method for determination of optimal lot size in dynamically
changeable conditions of flexible manufacturing systems.
3. DESIGN OF SOLVING PROCEDURE
3.1 Methods
The authors propose to use the simulation optimization for
determination of lot size in production systems. The existence of the
simulation model is necessary assumption for the usage of the simulation
optimization. It means that simulation model of FMS have to be created.
The most appropriate simulation method is the discrete-event simulation
for manufacturing model building. Rapid expansion of simulation tools
for manufacturing allowed the usage of this procedure very effectively.
The model building takes a short time and the model is very detailed.
The authors use the Witness simulator.
Simulation optimization is defined as optimization of outputs from
simulation experiments. It is based on optimization of outputs from
discrete event simulation models (Fu, 2001).
Simulation optimization provides a structured approach to determine
optimal input parameter values, where optimal is measured by a function
of output variables associated with a simulation model. (Swisher, 2000)
The simulation optimization problem is defined as well as ordinary
optimization problem by primary methods. (Fu. 2001):
* input and output variables;
* objective function;
* constraints.
[FIGURE 1 OMITTED]
The value of objective function cannot be evaluated directly but it
must be estimated as output from simulation run. It means that
optimization via simulation is computationally very expensive. On the
other side the definition of objective function is very simple without
complicated mathematical formula.
The computational cost of simulation optimization causes that the
practical usage of simulation optimization without software support is
impossible. The software packages are solved as plug-in modules which
are added in the basic simulation platform. The approach to simulation
optimization is based on viewing the simulation model as a black box
function evaluator. Figure 1 shows this black-box approach to simulation
optimization. The optimizer chooses a set of values for the input
parameters and uses the responses generated by the simulation model to
make decisions regarding the selection of the next trial solution.
3.2. Procedure
The critical step of solving was the definition of objective
function. As it was mentioned, the lot size is influenced by more
factors not only by costs. The authors in the process of definition of
objective function went out of production goals. There were also
included number of finished parts, machine utilization and flow time in
objective function besides of the costs which represents the important
goals of production. The function for cost calculation involved not only
the set up costs and storage costs but also operation costs and
transport costs. The objective function calculates costs per unit.
All variables and functions are set and calculated in elements of
FMS in simulation model. Partial values of objective function are always
calculated when specific element of FMS is finishing its activity. Total
cost sum is calculated at the same time.
Discrete-event simulation allows this process. The objective
function can be defined in a simple way and it does not need to contain
input values. Its final value is given as a result of simulation run.
Selection of inputs parameters is realized by optimizing module.
The right values of input variables also have to be connected. It is
very important to constrain the input parameters meaningfully. We
recommend the constraints of input parameters to set up through special
designed preparatory simulation experiments.
The algorithm selection is a very important step for simulation
optimization usage. The software tools give more algorithms. These
algorithms do not need to search all set of possible combinations but
they have to find the global extreme of objective function. Here arises
a question if these algorithms do not find only local extreme. It is
typical for Hill climb algorithm.
The selection of algorithm has to respect mainly two basic factors:
* what data will include individual sets of variables;
* time of optimization process.
4. ADVANTAGES AND DISADVANTAGES
The simulation optimization is more accurate method for
determination of lot size than the classic methods because it is able to
respect much more number of factors which influence lot size. But it
also requires the existence of simulation model. On the other side the
simulation model allows research in the detail way the real
manufacturing process. Classic methods are fast and simple. Simulation
optimization can take long time according to the restriction of the
possible solving combinations. The length of duration seems as the
greatest problem of simulation optimization usage. Simulation
optimization is definitely proper method for accurate method for
determination of lot sizes, especially for FMS where the set up time is
markedly reduced.
5. CONCLUSION
There are more areas where simulation optimization would be used.
Of course the choice of the procedure for usage in simulation
optimization depends on the analyst and the solved problem. The
simplicity and good software aid appear as strong assumptions for real
using of simulation optimization. We are planning for the next step of
our research to realize extensive study. This study will compare
proposed procedure with classic methods for determination of lot size in
FMS.
6. REFERENCES
Fu C. M. (2001) Simulation Optimization In: Peters B.A., Smith
J.S., Medeiros D.J., Rohrer m.W.:Proceedings of the 2001 Winter
Simulation Conference. Arlington, USA, pp. 55-61
Gregor, M., Kosturiak, J., Mieieta, B., Bubenik, P., Ruzieka, J.
(2000) Dynamicke planovanie a riadenie vyroby, KPI-ZU EDIS, pp. 179-212.
Habchi G.1; Labrune C. (1995) Study of lot sizes on job shop
systems performance using simulation. In Simulation Practice and Theory,
Volume 2, Number 6, 15 May 1995, pp. 277-289, Springer.
Khan L. R., Sarker R.A. (2002) An optimal batch size for a JIT
manufacturing system. In Computers and Industrial Engineering Volume 42,
Issue 2-4 26th International conference on computers and industrial
engineering, pp. 127-136, ISSN:0360-8352
Potoradi, J.;(1999) Determining optimal lot-size for a
semiconductor back-end factory In Proceedings of the 1999 Winter
Simulation Conference Volume 1, pp. 720-726
Ramaswamy K.V.(2006) Optimal lot sizing in manufacturing revisited.
In: Journal of Information and Optimization Sciences. Vol. 27, 2006 no.1
pp 97-105
Swisher J.R., Jacobson S.H., Hyden P.D., Schruben L.W. (2000) A
survey of simulation optimization techniques and procedures. In Joines
J.A., Barton R.R., Kang K., Fishwick, P.A.,: Proceedings of the 2000
Winter Simulation Conference. Orlando, USA, pp. 119-128
TOMEK, G.--VAVROVA, V., (1999) Oizeni vyroby. Praha: Grada
publishing, 1999. ISBN 80-7169-578-5