Casting of intake pipes by silicone rubber moulding.
Brajlih, T. ; Drstvensek, I. ; Balic, J. 等
Abstract: During the process of modifying and optimizing the intake
system of a two-stroke motorcycle engine the original position and
orientation of a carburettor were changed. Therefore a new design of an
intake pipe with different functional and constructional demands was
needed. In order to quickly produce a functional new pipe model for
engine testing, some rapid manufacturing procedures were used. Mould patterns were manufactured with rapid prototyping technology and the
functional parts were produced with silicon rubber moulds. Additionally
a small batch production of intake pipes using the silicone rubber moulding was investigated. It proved that silicone rubber moulding could
be a rational solution for series of up to hundred pieces if the mould
consists of multiple nests.
Key words: Rapid manufacturing, Rapid prototyping, Rapid tooling,
Silicon rubber moulding.
1. INTRODUCTION
Optimization of a two-stroke motorcycle engine has resulted in a
modified carburettor position. Therefore a new design of an intake pipe
was needed. In order to quickly test the new engine layout, several
functional models of the pipe had to be produced in a relatively short
time. It was decided, that rapid manufacturing procedures will be used
in production of this series of pipe models.
2. BUILDING A PROTOTYPE
For pipe's prototype production the PolyJet[TM] rapid
prototyping procedure has been chosen (Objet, 2005). Therefore a three
dimensional CAD model of the pipe was drawn according to the functional
and constructional demands of the modified intake system. Then the CAD
model was uploaded into the rapid prototyping machine software package
where the model orientation in the workspace and the support structure
was defined.
[FIGURE 1 OMITTED]
When the prototype's building was completed the support
material was removed with water jet. Then, the prototype was installed
in the engine's intake system, in order to test the constructional
properties. Functional properties on a working engine were tested also,
but the prototype could not be used in a long-term testing, because the
working temperature around the pipe is around 60-70[degrees]C and the
prototype's material softens considerably after being exposed to
such temperatures for some time.
3. PREPARING THE MOULDS
For the production of the functional intake pipe vacuum casting of
the two-component resin with the temperature resistance of 135[degrees]C
was used. Mould was made from silicon rubber. Because the pipe is
hollow, the mould with an inserted core had to be used, so the model can
be demould after the curing process is completed (Rapid tooling, 2005).
Then the inserted core must be removed from inside the pipe. In the case
of a straight pipe removing the core would not be a problem. But in our
case the pipe is curved, therefore the core can not be pulled out.
Instead the core must be melted out. So it is very important for the
core to be built from an appropriate material. The core must remain
solid up to the preheating temperature of the silicon rubber mould
(65[degrees]C). In addition the core material must be completely melted
at a temperature lower than the temperature resistance of the cast
material of the pipe (135[degrees]C), so it can be removed without any
influence on the shape and the structure of the pipe. Considering this
demands, the eutectic, low melting point (69[degrees]C) alloy
MCP69[TM]was chosen for the core (MCP, 2005). The pipe's core had
to be cast separately in a different silicon rubber mould. Because of
the chosen lost core casting procedure the original prototype could not
be used as a mould pattern. Instead the rapid prototyping procedure was
used to build two different patterns needed for the moulds. First
pattern was the pipe's core with two positioning elements and the
second pattern was the pipe together with the inserted core (and
positioning elements). Both patterns were built sliced in half, so the
parting plane could be added easily. After the prototype building was
completed, both patterns were polished, in order to improve the surface.
After the inlets and raisers were added, patterns were positioned inside
wooden boxes and the silicon rubber was poured around them. Then both
moulds were put into a vacuum chamber and decompressed in order to
remove air and water from the silicon rubber. When the silicon rubber
vulcanized, both moulds were cut and patterns removed (Drstvensek,
2004).
4. CASTING THE FUNCTIONAL PIPE
[FIGURE 2 OMITTED]
Core was cast with the low melting point alloy that was melted and
poured into the silicon rubber mould. The mould was preheated on
70[degrees]C to prevent the premature solidification of the alloy. After
the cooling phase the core was extracted from its mould and inserted
into the pipe's mould
[FIGURE 3 OMITTED]
Closed pipe's mould was preheated to 65[degrees]C (which is
lower than the melting point of the core's alloy (69[degrees])).
Then the mould was put into a vacuum chamber. Both components of the
resin were poured into two cups (each for one component) in appropriate
mixture ratio. The temperature of the curing process of the resin has
been set at 65[degrees]C for 45 minutes. Then the pipe (with the metal
core still inside) was demould.
For the core to be removed the part must be warmed above the
melting point of the core's alloy (69[degrees]) but still in the
limits of the temperature resistance of the resin that the pipe was cast
from (135[degrees]C). After the core's melting out, the inner
surface of the pipe could be further cleaned with hot water
(70-80[degrees]). Finished pipe was then mounted on the engine which
could now undergo more long-term testing than with the rapid prototype
of the pipe.
[FIGURE 4 OMITTED]
5. PRODUCTION OF SERIES
After successful testing of the pipe, demand was made for
production of 100 pieces series. At this point the main weakness of the
silicone rubber moulding has presented. Due to the complexity of our
model the existing two moulds would be unusable after casting app. 20
pieces. The simplest solution would be to prepare new moulds after the
previous moulds become unusable. But producing 100 pieces in such a
manner would not be time/cost efficient. Therefore it was decided to
prepare moulds with several nests. Simple calculation was made to
estimate the most cost efficient number of nest in a mould. It was taken
into considerations that to prepare a mould with more nests more
patterns are needed and have to be build with a RP machine.
[FIGURE 5 OMITTED]
Secondly the minimum number of moulds required to produce a series
of 100 pieces was estimated (presuming that one mould would endure 20
casts).
[FIGURE 6 OMITTED]
Figure 6 shows that common costs of production are decreasing until
the mould with 7 nests. Further increase to the number of nests results
in raise of production costs due to the higher number of patterns
required. However, regarding the small difference between 4 and 7 nests
mould (app. 2[euro] on individual piece) and the technical difficulties
in making the mould with seven nests the four nests mould version was
chosen for series production.
6. CONCLUSION
This project has presented a mayor weakness of the rapid
prototyping techniques. Because of the RP material's properties the
prototype can not always be functionally tested. It was shown that
vacuum casting into silicon rubber moulds with a wide array of different
resins with various properties available, can nicely solve such
problems. While the RP pipe was not suitable for engine testing the RP
procedure is still necessary for the quick manufacture of the mould
patterns. In a case of larger series of the parts (from the same resin)
is needed, the mould can be made with several nests and the costs of
part production can be considerably lowered.
7. REFERENCES
Drstvensek, I. (2004), Layered Technologies, Fakulteta za
strojnistvo, Maribor
MCP Rapid tooling homepage available at: http://www.mcp-group.de/,
Accessed: 2005 5 20
Object geometries homepage available at:
http://www.2objet.com/home.asp, Accessed: 2005 5 22
Rapid tooling survey page available at
http://home.att.net/~castleisland/tl_c.htm, Accessed: 2005 5 9