Application of freezing method to recover tunnel accident in complex stratum of Nanjing subway.
Ping, Yang ; Feng-Bin, Zhu
By the application of the freezing method to handle several
engineering accident in Nanjing subway's complicated stratum, this
paper presented the freezing design method, and analyzed the monitoring
result and pattern of freezing-induced ground surface deformation in the
sites. It is suggested that bore-unloading could counteract a portion of
frost heave deformation and the grouting was to be the key measure to
minimize the thaw settlement. Guidelines are provided for the
application of the freezing method to deal with related engineering
accident and construct subway in complicated stratum.
INTRODUCTION
The main stratum which the shield tunnel of Nanjing subway line #1
traversed are peaty clay, silty soil and fine sand. The peaty clay
possesses high compressibility and easily fluid. Silty soil and fine
sand with high water content and strong penetrability easily bring about
spurting water and gushing sand. Because of the soft and weak stratum,
several methods of improving soil have been used at the entrance of
Zhang Fuyuan southern shield tunnel (Yang et al., 2003) and in five out
of six corridors of line #1, but all was failing, only the freezing
method succeeds to reconstruct and guarantee the safety.
HANDLING THE ACCIDENT AT SHIELD ENTRANCE
Permeability grouting and soil mixing methods for soil improvement
were used at the entrance of Zhang Fuyuan southern shield tunnel .When
punching concrete wall, a great deal of flow-sand twice gushes from both
sides around the cave for shield, the quantity of which estimated to be
about 110[m.sup.3]. The ground surface's settlement is about 1.5m
in the 20[m.sup.2] area of the east, and about 1m in the 1.5[m.sup.2]
zone of the south west. The settlement of the whole region near shield
entrance is larger (Fig.1). In order to insure the pipelines and the
transportation being in normal usage and safety, and to guarantee the
shield machine safely passing doorway, the freezing method was applied
to improve the stratum.
[FIGURE 1 OMITTED]
Frozen wall and freezing parameter
By experiment, obtained the compression strength of frozen silty
soil and fine sand is 9.95MPa and 9.57MPa at -10 [degrees]C, and the
tension strength is 1.81MPa and 1.72Mpa, respectively. The thickness of
frozen wall can be calculated by empirical formula:
e = kB x D x p / [2[sigma].sub.c] 1/2 (1)
where e is frozen wall's thickness; k is safety coefficient,
adopting 3; B is empirical coefficient, adopting 1.2; D is excavation
diameter, 6.5m; p is the total water and earth pressure, 0.217Mpa;
[[sigma].sub.c] is the compression strength of frozen soil.
The thickness of frozen wall is calculated to be 0.5m. The
overlapping length between the frozen wall and concrete wall which is
around the cave for shield is usually 1-2m according to experience, and
taking the larger water-earth pressure into account, the width and depth
of frozen wall are designed to be 9.5m and 18.5m, respectively. The
freezing depth above the cave is 3m. The zone from 3m above the cave to
the ground surface is not frozen so as to reduce freezing-induced
influence on ground surface.
Freezing pipes are set up perpendicular to ground surface. Because
there have been soil mixing piles in the zone out of frozen wall ,which
can bear lateral earth pressure, the design of the frozen wall should be
calculated according to the demand of sealing water and according to the
distance between soil-cement mixing piles and concrete wall. The
thickness of 0.5m is deemed enough. It is more difficult to freeze soils
near the concrete wall due to the large thermal conductivity of
concrete. Freezing pipes should be lay near the concrete wall, And
should take measures to preserve heat of the wall.
The layout of freezing pipes and frozen wall are shown in Fig.1.
the 21 freezing pipes with diameter of 108mm and 2 temperature holes
were laid out with the bottom at a depth of 18.5m. The distance between
two pipes is 450mm and the distance between the freezing pipes and
concrete wall is 200mm. The brine temperature should come to -22
[degrees]C after freezing for 7days and start excavation of the cave of
shield after freezing for 15 day. The lowest temperature of recycling
brine is -24 [degrees]C ~ -28[degrees]C and the average temperature of
the frozen wall is no more than -10[degrees]C. When excavating the cave
for shield, the temperature at interface between the frozen wall and
concret wall is less than -3 [degrees]C.
Monitoring and analysis of the temperature and deformation
In order to monitor the temperature and displacement during the
freezing, measured temperature holes C1and C2 have been set up in frozen
wall. And there are totally 24 points of monitoring displacement on the
ground surface. Fig.2 shows the temperature change of the temperature
holes with freezing time. C1 is near the concrete wall, where there is
direct exchange of heat with hot atmosphere(20 [degrees]C).So its
temperature descends slowly, but is basically uniform at various depth.
The temperature come to -7 [degrees]C after freezing for 15 days.
Whereas, the C2's temperature descends quickly to a lowest value of
-16.5 [degrees]C as it is adjacent to the side of mixing piles.
Moreover, because the hole leans to freezing pipes with the increase of
the depth, the temperature discrepancy at different depth is very large.
Such as ,the temperature at the depth of 3m is only -8 [degrees]C, while
it is -16.5 [degrees]C at 9m. The figure also shows it is read for
excavation after freezing for 15 days
[FIGURE 2 OMITTED]
Fig.3 shows that the measured points 15# and 18#, which lie in the
flow sand area east to the frozen wall(Fig.1). It appears that quite
large initial settlements before freezing, and there is frost heave
deformation of 4mm when the temperature descends, but the total
settlement is 3-4mm at last. The settlement at the point 2# and 19# are
not too large, with a maximum value of 5mm at 2# and only 1mm at 19# .
This is because point 19# lies in the accident-induced subsiding zone.
According to the results measured at 24 points, it is found that the
maximal frost heave deformation is no more than 5mm.
[FIGURE 3 OMITTED]
THE APPLICATION OF FREEZING METHOD TO TUNNEL CORRIDOR
Corridors of tunnels of subway line #1 in Nanjing are almost
located at depth of 14m to 17m below ground surface. The stratum
consists of silt clay layer, silty soil and fine sand layer, which have
the properties of high moisture content, high sensitivity, low strength,
large voids ratio and big penetrability, They belong to unstable
stratum. The construction of five corridors once used several methods ,
but all was failing, only the freezing method succeed to reconstruct
them. The freezing method is very effective on improving soil in weak
layer with rich water. Sometimes ,it may be unique method.
Taking only San-Zhang corridor for example, the layout of freezing
pipes, freezing parameter and monitoring frost heave and thaw settlement
in the site are presented below. The corridor with a diameter of 3.2m is
at depth of 17.13m located in liquefiable fine sand layer. The corridor
and pumping-pit are constructed in one operation (Fig.4).
[FIGURE 4 OMITTED]
Layout of freezing pipes and determining freezing parameters
The freezing pipes were in line with rectangle, and two upper
angles of wall were changed into arc(Fig.5). Excavation outline of the
corridor is a height of 4.24m and breadth of 4.16m. Frozen wall was
designed according to frozen powder sand strength for the corridor
located in powder sand layer ,and a design thickness of 1.6m and average
temperature of -10 [degrees]C were obtained. The horizontal freezing
pipes with 108mm diameter were installed in the direction of parallel to
corridor axis, as shown in Fig.4 and fig.5. The detail parameters about
freezing method applied to the corridor are shown in table 1.
[FIGURE 5 OMITTED]
Monitoring and analysis of frost heave and thaw displacement
Twelve monitoring points(1 to 12) of displacement were positioned
on the ground surface in the direction perpendicular to the corridor
axis(Fig.5).The frost heave and thaw displacement were obtained during
different construction stages and shown in Fig.6.
[FIGURE 6 OMITTED]
Fig. 6 shows that the displacement above corridor axis is the
biggest and it decreases with the increase of the distance from
centerline. The deformation is divided into four stages. The first is
drilling holes and installing pipes stage(25days), during which the
settlement of ground surface is not big with a maximum value of 10.3mm.
This is due to partial water and soils running off holes and the ground
volume is lost a little. But grouting into holes is adopted for reducing
the settlement, which is very effective. The second is freezing stage
after installation of pipes (32 days), during which the frost heave
deformation is small at the beginning of freezing for the temperature of
most soils being above 0 [degrees]C, but the frost heave deformation
increases greatly when soil temperature falls below zero degree. The
reason is that original water and water migrating to the freezing front
at 0 [degrees]C is changed into ice and the soil swells rapidly. The
figure shows the maximum heave deformation is 16.5mm after taking the
measure of drilling four unload holes. The third is maintained freezing
stage, i.e. excavation and installing lining stage (35days), during
which the heave displacement rate reduces with an increment of only
2.6mm. The final maximum frost heave is 19.1mm. The fourth is unfreeze
stage, during which thaw zone is grouted with injecting-pipes placed in
advance to prevent the large ground surface subsidence, As such, the
maximum thaw settlement is 20.4mm. The deformations during every stage
are satisfied with allowance deformation of structure.
The soil will be disturbed during improving stratum with freezing
method, especially, when the unfreezing time lasts longer. The
disturbance may influence and even damage tunnel lining and buildings
and pipelines around the tunnel(Brown et al.,2003). Some research
results show that freezing-induced deformation may be bigger. Moreover,
thaw settlement was about two to three times larger than frost heave
without taking measures of unloading and grouting (Konrad J.M.,2002).
But the examples in this paper proved that drilling unload holes and
grouting with injecting-pipes placed in advance can effectively reduce
frost heave and thaw settlement in order to protect buildings and tunnel
lining.
CONCLUSION
Freezing method has been effectively applied to recover tunnel
accidents in complex stratum of Nanjing subway. The examples proved that
the frost heave and thaw settlement in the technique can be completely
controlled within allowance value by means of taking measures during
different stages. For example, partial frost heave can be compensated by
drilling unload holes and thaw settlement can be reduced by grouting. So
freezing method should be adopted prior to other methods when recover
accidents and improves soil of shield entrance ,corridors and
pumping-pit in weak stratum with rich water.
REFERENCES
Brown, D.A. (2003), "Hull wastewater flow transfer tunnel:
recovery of tunnel collapse by ground freezing", Geotechnical
engineering, Vol.157,No.2,77~83
Konrad, J.M. (2002). "Prediction of freezing-induced movements
for an underground construction project in Japan",
Can.Geotech.J.,Vol.39,No.6,1231-1242
Yang, P. and She, C.G. (2003), "Application of artificial
freezing method in Zhang Fuyuan station of Nanjing subway", Rock
and Soil Mechanics , Vol.24,No.2,365-368
YANG PING & ZHU FENG-BIN
Faculty of Civil Engineering, Nanjing Forestry University, Longpan
road 159#, Nanjing Nanjing, Jiangsu, China
able 1. Freezing parameters
Parameter name Value Parameter name Value
Design thickness of 1.6m Design space 0.6~0.84m
frozen wall of freezing
pipes
Recycling brine -22~-25 [degrees]C Bottom space 1.0m
temperature of freezing
pipes
Average temperature of -8~-10 [degrees]C Time of 25day
frozen wall forming sealed
wall
Amount of measure 10 Positive 32day
temperature holes freezing time
Freezing pipes Amount 55 Maintainance 35day
freezing time
Unload holes 4 Time of whole 95day
Construction