Applications of two costal pretection structure construction methods.
Yan, Shuwang ; Chu, Jian
Two methods that can be used for the construction of costal
protection structures are introduced in this paper. The first is the
geotextile bag method which uses either sand or clay to fill geotextile
tubes or bags to form dikes or breakwaters. The second is to a method
for using prefabricated semicircular reinforced concrete caissons to
construct offshore dikes or structures on soft soil. Two case studies
are presented to illustrate the applications of the two methods.
INTRODUCTION
The importance of costal protection has been highlighted during the
devastating tsunami in December 2004. However, a large amount of
resources are required to construct costal defence or protection
facilities. This is particularly true when the coast to be protected is
long. Therefore, the selection of the most cost-effective costal
protection structures and the construction techniques becomes important
in reducing the cost of the project. When the dikes or other types of
costal protection structures are long, a small improvement in the design
could result in a significant amount of saving. Therefore, it is
beneficial to review as many methods as possible so the most
cost-effective methods can be identified or to develop new methods that
suit the local conditions the best. In this paper, two methods that can
be used for the construction of costal protection structures or costal
disaster rehabilitation works are introduced. The first is the
geotextile bag method which uses either sand or clay to fill geotextile
tubes or bags to form dikes or breakwaters. The second is the use of
prefabricated semicircular reinforced concrete caissons to construct
offshore structures or dikes on soft soil. Both methods have been used
successfully in costal protection projects in China. Two case studies
are presented to illustrate the applications of the two methods.
GEOTEXTILE BAG METHOD
The traditional method of constructing shoreline structures is to
use rock or prefabricated concrete units. In recent years, several
methods have been developed to use geotextile materials for the
construction of coastal structures such as breakwaters and dikes.
One of the methods is to use geotextiles acting as formwork for
cement mortar units cast in situ (Silvester and Hsu, 1993). The mortar
mix need be only of sufficient compressive strength to support the
weight above, plus the moment from the side force of the waves. Since
the flexible membrane is required to hold the mixture in place until it
sets, any subsequent deterioration due to UV rays or other conditions is
of little concern. Thus, the method tends to be cheaper than the
conventional methods. Applications of the mortar filled geotextile tubes
are illustrated in Figs. 1 and 2. Details are referred to Silvester and
Hsu (1993).
[FIGURES 1-2 OMITTED]
Similar methods, but using sand or dehydrated soil as the fill
material have also been used for dike construction (Kazimierowicz, 1994;
Miki et al., 1996). Sand or sandy soil is the most ideal fill material
for this purpose. For near shore or offshore project, a suction dredger
can used to pump sand from the seabed or a sand pit directly into the
geotextile tubes. In case sand is not readily available, silty clay or
soft clay may also be used. In this case, the clayey fill would have to
be in a slurry state in order to be pumped and flow in the tube. The
slurry would have to be dewatered in the geotextile bags or tubes under
an ambient pressure. Then the selection of the geotextile used for the
bags or tubes becomes important. The geotextile has to be chosen to meet
both the strength and filter design criteria. Some analytical methods
have been developed to estimate the required tensile strength for the
geotextile (Kazimierowicz, 1994; Miki et al., 1996). The apparent
opening size (AOS) of the geotextile needs to be selected to allow the
pore pressure to dissipate freely and yet retain the soil particles in
the bags.
One technique of using clay slurry fill geotextile bags for dike
construction was developed in Tianjin, China, and used for one land
reclamation project along the coast of Tianjin. The cross-section of the
dike is illustrated in Fig. 3 and a picture showing the alignment of the
bags is given in Fig. 4. It can be seen that flat geotextile bags,
instead of tubes, are adopted in this method.
[FIGURES 3-4 OMITTED]
As shown in Fig. 3, the designed height of the dike was 4.8 m with
base and top elevations at 0.7 m and 5.5 m respectively. The top width
of the dike was 2.43 m. The water levels were at 4.7 m elevation during
high tide and at nearly 0.7 m elevation during low tide. The outer and
inner slopes of the dike were chosen to be 2L:1H and 1.5L:1H,
respectively. For the bottom bag, the dimension used was 30 m in
circumference. Clay slurry was dredged from the seabed of a selected
area and pumped directly into the bags through an injection hole. The
height of the bag after consolidation was around 0.5 m. Nine layers of
geotextile bags were used. The surfaces of the slopes formed by the
geotextile bags were to be covered with a cast-in-situ concrete layer of
25 cm. The concrete was cast-in-situ using moulds formed by geotextile
bags, a technique which is commonly used in China (Chi, 1991). As shown
in Fig. 3, berms were used to enhance the stability of the dike and to
protect the toes of the slopes. The berms were made of crushed stones of
50 to 80 kg. The slopes of the berms were 2L:1H for the inner side and
3L:1H for the outer side. A 4 m thick of hydraulically filled slurry was
to be placed behind the dike after the dike was constructed. An
instrumentation scheme was also suggested as shown in Fig. 3. A woven
polypropylene geotextile with a mass density of 120 g/[m.sup.3] was
chosen for the bags. It had a tensile strength of 28 kN/m in the
longitudinal and 26 kN/m in the transverse direction respectively. The
AOS ([O.sub.95]) of the geotextile was 0.145 mm. The bags are sewn
together using sewing machines on site. The soil used to fill the bags
was classified as SC-CL according to the Unified Soil Classification
System (USCS), that is, a borderline case between sandy clay and low
plasticity clay. The liquid limit and plastic limit of the soil were
20.4% and 8.9% respectively and the plasticity index was 8.9%.
PREFABRICATED CAISSON METHOD
The geotextile bag method may only be feasible when dikes are to be
constructed in relative shallow or quiet water. When water is too deep
or the wave is rough, gravity retaining structures using prefabricated
reinforced concrete segments or caissons may be a better option. The use
of caisson or concrete segments is not new. However, the most
cost-effective design methods are still yet to be established. These
concrete segments or caissons have to be tall enough to match the water
depth and heavy enough to provide stability against the waves. However,
when the concrete segments or caissons are too heavy, they cause
settlement or bearing capacity problems. This is particularly the case
when the foundation soil is soft. The weak foundation soil can be
improved. However, it is difficult and costly to treat soil offshore and
over a large area or distance. Therefore, it has become a challenge on
how to construct large size gravity structures on soft soil.
In one of costal protection projects along Yangtze Estuary, some
dikes for navigation purposes needed to be constructed. The method of
using prefabricated reinforced concrete caissons was adopted. The dike
was to be constructed at 40 km away from the coast. The water depth
ranged from 5.0 to 8.5 m. The design wave height was 3.32 to 5.90 m with
a return period of 25 years. The total length of the dike was about 17
km.
The design of the dike is schematically shown in Fig. 5. The
caisson used was prefabricated reinforced concrete hollow segment. It
was semicircle shaped, as shown in Fig. 5. The radius of the semicircle
was 5.7 m. The advantage of using a semicircular cross-section is that
the direction of the resultant wave force on the semicircular shaped
structure will always pass through the center of the circle, which will
greatly improve the loading condition of the structure. The hollow
caisson would be filled with sand after installation through a 600 mm
diameter hole on top of the caisson. In order to prevent the foundation
soil from scouring, a geotextile sheet was used to cover the seabed. A
cushion which acted as the foundation bed was placed on top of the
geotextile. The cushion was 1 to 2 m high. It was made of crushed stones
of 1 ~ 100 kg for the centre and 200 ~ 400 kg for the edge. After the
caisson was placed, berms were placed on two sides of the caisson. The
berms were made of 400 ~ 600 kg crushed stones.
[FIGURE 5 OMITTED]
The soil profile below the dike consisted of a 1.5 to 3.5 m thick
silt sand followed by 2 to 4 m thick clay mud and a roughly 30 m thick
soft clay underlying the mud. The basic properties of the soil are given
in Table 1. Although the soil below the dike was weak, with the use of
geotextile and the cushion, the bearing capacity was estimated to be
sufficient. However, the shear strength of the soil could be weakened by
the wave action, which in turns would affect the stability of the dike.
Nevertheless, due to time and other constraints, one section of the dike
was constructed without improving the soil first. As the dike was a
strip load, the load would only be distributed to a certain depth. It
was hoped that under the surcharge of the crushed stone and the
caissons, the geotechnical properties of both the upper silty sand layer
and the top few meters of lower soft clay layer would be improved with
time, and thus the stability of the dike would have been enhanced with
time.
However, this proved to be a mistake. Only 2 months after the
construction of the dike, an unusual strong storm took place in December
2002. The dike failed during the storm. Large settlements incurred
suddenly and some caissons large lateral movements. A picture of the
dike after the storm is shown in Fig. 6. It can be seen that the
caissons had undergone either large lateral or vertical movements. The
settlement versus time curve is shown in Fig. 7. The wave height versus
time curve is also plotted in Fig. 7. It can be seen that a sudden
settlement took place at the time when there was a surge in the wave
height. The dike had become unstable under the wave action. Apparently,
the soil needed to be improved. How to improve the seabed soil which was
5 to 8.5 m below the sea level with a wave height of 3 to 6 m in a
cost-effective way became the key issue.
[FIGURES 6-7 OMITTED]
Several soil improvement methods were considered. The soil
replacement method was not feasible as the amount of fill required and
the amount of excavated soil to be disposed were too excessive. The
method to accelerate the consolidation process of the soft clay using
prefabricated vertical drain (PVD) was considered the most economical.
This method was also relatively easy to implement. The influence zone of
the strip load was estimated to be 7.0 m below the seabed. Therefore, it
was only necessary to install the PVD to a depth of 10 m deep. The
weight of the crushed stone cushion was considered sufficient in
providing surcharge. A special vertical drain installation barge was
used to install the PVD offshore. The procedure for improving the soft
soil was as follows: (1) PVDs was installed from the PVD installation
barge at a spacing of 1.0 m to a depth of 10 m below the seabed; (2) The
crushed stone cushion was laid on the seabed as a surcharge to
consolidate the soil below; (3) The caisson segments were only placed
after an average degree of consolidation of 80% was achieved, which took
about 90 days after the placement of the crushed stone.
In addition to soil improvement, anti-slippery rubber pads were
also used for the caissons. The rubber pads were embedded into the base
of the caisson during the casting stage. Pins were also precast into the
base of the caisson to enhance the anchoring effect. Large scale
laboratory tests have shown that the use of rubber pads and pins can
enhance significantly the resistance of the caisson against sliding.
To assess the effectiveness of soil improvement, the undrained
shear strength profiles obtained from vane shear tests conducted before
and after the preloading are compared in Fig. 8. The duration of
consolidation was 90 days, It can be seen that the vane shear strength
increased by almost 2 folds as a result of consolidation using PVDs.
It can also be seen from Fig. 8 that there were little improvement
in the soil where PVDs were not reached. However, soils at these depths
were not affected by the cyclic wave loads.
[FIGURE 8 OMITTED]
The construction of the dike was completed in Dec 2003. The
settlements of the dike were monitored after the construction. The
settlements measured at six different sections with time are shown in
Fig. 9. The wave height versus time curve is also plotted in Fig. 9. It
can be seen from Fig. 9 that the dike had experienced several strong
storms caused by typhoons. Some of them were even stronger than the one
that caused the failure as shown in Figs. 6 and 7. Even through, the
dike was stable and there was no additional settlement caused by the
storms. The settlement also stabilized in 5 to 6 months. The total
settlements were within the expected range. Therefore, the use of PVDs
has proven to be a successful method for this project. The dike after
construction is shown in Fig. 10.
[FIGURES 9-10 OMITTED]
CONCLUSIONS
Two methods that can be used for the construction of coastal
protection structures or for costal disaster rehabilitation works are
introduced in this paper. The first is the geotextile bag method which
uses either sand or clay to fill geotextile tubes or bags to form dikes
or breakwaters. The second is to use prefabricated reinforced concrete
caissons to construct offshore dikes or structures on soft soil. The
applications of these methods are illustrated using case studies. The
following conclusions can be made on the two methods:
(1) The geotextile bag or tube method is suitable for the
construction of breakwaters or dikes in shallow water. The bags can be
fabricated using geotextile on site into any desirable dimensions.
Although sand or lean concrete mortar are normally used as the fill
materials, the presented case study has shown that clay slurry dredged
from the seabed can also be use as a fill material to fill the bags.
This method is cost-effective, particularly when sand or rocks are not
readily available as fill material.
(2) A method to use prefabricated reinforced concrete caissons to
construct dikes of offshore structures on soft clay is presented using a
case study. The study shows that it is necessary to improve the soft
seabed soil before constructing the dike even though a thick cushion
made of crushed rocks is used. The dike built on soil without
improvement failed during a heavy storm. For the case presented, the
soil can be improved by simply installing PVDs to accelerate the
consolidation process of the seabed clay. With the use of PVDs, the soft
soil would consolidate much faster and gain sufficient strength quickly
to maintain the stability of the caissons.
REFERENCES
Chi, J. K. (1991). Technical Report on the Technique of Pumping
Concrete into Geotextile Mould. Shanghai Geotechnical Research Institute
(in Chinese).
Kazimierowicz, K. (1994). "Simple analysis of deformation of
sand-sausages." Proc. 5th Int. Conf. Geotextiles, Geomembranes and
Related Products, Singapore, 5-9 Sept., Vol. 2, 775-778.
Miki, H., Yamada, T., Takahashi, I., Shinsha, H., and Kushima, M.
(1996). "Application of geotextile tube dehydrated soil to form
embankments." Proc. 2nd Int. Conf. on Environmental Geotechnics,
Osaka, 5-8 Nov, 385-390.
Silvester, R. and Hsu, J. R. C. (1993). "Costal
Stabilization--Innovative Concepts", Prentice-Hall Inc.
SHUWANG YAN
Geotechnical Research Institute, Tianjin University, Tianjin,
300072, China
JIAN CHU
School of Civil and Environmental Engineering, Nanyang
Technological University, Singapore 639798
Table l. Soil properties
Soil Water Unit Void Liquid
Stratum content weight ratio limit
(%) (kN/[m.sup.3])
Silt sand 29.3 19.0 0.827 -
Mud 57.5 16.4 1.672 45.2
Soft clay 51.5 16.8 1.470 45.8
Soil Plastic Undrained Compression
Stratum limit shear Index (2)
strength (1) [Mpa.sup.-1]
(kPa)
Silt sand - - -
Mud 23.6 13.4 1.59
Soft clay 23.8 22.0 1.31
(1.) The undrained shear strength was measured by Unconsolidated
undrained tests.
(2.) The compression index was measured by oedometer tests within
the stress range of 100 to 200 kPa.