Geosynthetics in the rehabilitation of failed slopes.
Ooi, T.A. ; Tee, C.H. ; Dobie, M.J.D. 等
This paper discusses the use of geogrids in the rehabilitation of
failed slopes in restricted sites. Failed slopes are often associated
with prolonged intense rainfall and lack of slope internal drainage. The
consequences of a landslide in the case of a highway or railway can be
very grave. The instant reinstatement of the same is almost demanded by
the general public. In one particular failed slope measuring about 36m
high, sheet piles were used as a temporary measure at the slope toe to
stop the movement of the sliding mass. However, with sheet piling, the
flow of groundwater was cut off and pore water pressure built up. This
pore water pressure built-up caused the soil strength to decrease and
the sheet piles began to rotate and tilt towards the railway lines. This
steady movement of the sheet piles posed an immediate danger to the safe
operation of the railway and daily movements of the goods train.
Geogrids were used to mitigate this continuing ground movement and
prevent further slope failure. The use of geogrids in the speedy
rehabilitation works has been well established. However, the methodology
in the application of the right technology is still not well understood,
particularly for very high slopes. This paper reports case histories of
landslide occurrences and the solutions successfully applied.
INTRODUCTION
The Tsunami that struck the Indian Ocean on 26 December was a
global catastrophe that caught many in the world by surprise. The most
devastated area happened at Bandar Acheh where the town was completely
demolished. The coastal areas of the Indian Ocean were hit by Tsunami to
varying degree. The world all over started the massive relief operation
by way of sending aids and donations. The whole world was shocked when
faced with such unexpected nature's calamities and steps are being
taken to monitor such oceanic ground movements that triggered tsunami
with devastating power so as to mitigate the damages and loss of lives.
Landslide is one of nature's calamities that occur on land when
there is excessive amount of water in the soil slopes. The excessive
amount of water in soil slope occurs usually during the incessant period
of rain. This paper reports case histories of slope failures
rehabilitated by using Tensar Geogrids.
MOTEL DESA SLOPE FAILURE
In early 1980s, part of the Motel Desa slope in Terengganu
collapsed during the heavy monsoon rainfall period and left the kitchen
of the motel hanging precariously on top of the failed slope. The failed
slope was about 30m high and 25m wide. It was important to ensure that
the kitchen did not collapse. The access to site was difficult and
speedy rehabilitation of the slope was necessary. The technology of
geogrid reinforcement of slope was new at that time in Malaysia and
careful instrumentation and testing was carried out during the
construction stage. In view of the difficult access and the urgency to
safeguard the motel kitchen, the upper half of the failed slope was
stabilized by using a combined technology of geogrid reinforced soil
slope of about 5m wide x 6.7m high supported on micro-piled platform
while the lower half failed slope was reconstructed using traditional
method of compacted fill without any soil reinforcement but to a gentle
slope of not more than 1:2. Beyond the geogrid reinforced slope at the
top similar unreinforced soil slope of not more than 1:2 was also
adopted. Fig. 1 shows the general cross section of the rehabilitation
scheme. The details of this landslide rehabilitation scheme were
reported and discussed by Toh et al (1986) and Ooi & Tee (2004). The
Motel Desa project has given designers an opportunity to make further
improvement to the design of geogrid reinforced slope through in-situ
monitoring of actual completed works. The rehabilitation work was
completed more than 20 years ago and the slope has performed
satisfactorily and remained stable.
[FIGURE 1 OMITTED]
RAILWAY LINE SLOPE FAILURE
A railway line cut slope in the east coast state of Malaysia
measuring some 36m in height failed during a severe monsoon rain season.
The failure threatened the safety of the railway line as the debris
encroach the railway side drain and sub-ballast. Immediate action was
taken to put a team of workers with plant and machinery on standby round
the clock to remove any debris that come close to 4m from the centerline of the railway tracks. A speed restriction was imposed to enable the
operator of the train to bring the train to an immediate stop upon
sighting of any sign of further slope movement and at the same time a
row of steel sheet piles was driven to refusal as an attempt to stop the
flow of the debris and prevent the movement of the failed slope. Fig. 2
shows a general view of the landslide and the steel sheet piles at the
slope toe near the railway line. It can be seen that the hill slope is
too close for comfort to the railway line. An analysis shows that the
landslide that had occurred was due to toe softening of the slope. The
results of analysis show slope toe failure with factor of safety of
1.03. The provision of sheet piles driven to refusal however could not
provide the embedment depth required and at the same time cut off the
flow of ground water and thus caused built up of water pressure.
Consequently, with accumulation of water and the loss of soil strength
due to soaking of the slope toe, the sheet pile rotated and tilted
forward towards the railway line. Fig. 3 shows the picture of tilted
steel sheet piles and the railway line. Slope stability analysis show
that the steel sheet piles are within the localized sliding circle with
factor of safety of less than unity. In view of this critical situation,
it was necessary to carry out urgent repair before the arrival of the
next monsoon. Tensar geogrid reinforced block of 8m high was chosen as
the solution to stabilize the toe area of the slope and at the same time
provide support for the 36m high failed slope. Fig.4 shows the results
of the slope stability analysis. In the rehabilitation of this type of
high failed slope, it is very important that the correct technology with
the right construction methodology is used so as to ensure successful
implementation of the reconstruction of the slope. The provision of
internal and external drainage system of the slope and the geogrid block
remains as an important factor to be considered in design and
construction of the rehabilitation works.
[FIGURES 2-4 OMITTED]
DESIGN METHODOLOGY
The design analysis must first start with the analysis of failure
mechanism based on site information and relevant soil parameters. Having
established the correct failure mechanism, it is then logical to proceed
to find a solution that is most economic based on the local conditions
and situations. Many designers often failed to consider the effect of
ground water table on the stability of slope. This can give rise to
wrong solution being prescribed and resulting in distress and/or failure
of the slope when the rehabilitation work is completed or during
service.
CONSTRUCTION METHODOLOGY
In the rehabilitation work, the landslide areas were divided into 3
sections namely, section A, B and C as shown in Fig.5. It is important
to rehabilitate the slope in sections and to ensure failure of slope
does not happen during construction. The site was first drained and the
top 1m of the foundation soil for the base of the geogrid block was
re-compacted with two layers of geogrid reinforcement to receive the
geogrid block to be constructed. Suitable drainage layer is then
installed with sand columns placed at the back slope and compacted in
layers with geogrid reinforcement. The geogrid block is built to a safe
height before excavation of the next section is started. This second
section is similarly built to a safe height before the third section is
excavated. The process is repeated until all the geogrid reinforcement
blocks are completed. Surface drainage system of the slope is
constructed as soon as it is possible and the completed slope is covered
with closed turf. Figs.6 shows the completed slope.
[FIGURE 5-6 OMITTED]
CONCLUSIONS
From the case histories presented by Toh et al (1986) and Ooi &
Tee (2004) as well as the railway project it can be concluded that:
1. Slope failures usually occurred during incessant raining season
like that of the monsoon period.
2. Different solutions are used in different case histories even
though the Geosynthetics of geogrid type were used, they were applied
differently.
3. The need for foundation soil improvement was found necessary to
support the geogrid reinforced block in order to reduce settlement and
movement of slope during and after construction of the slope.
4. It is important to provide internal and external drainage system
to ensure that groundwater table is lowered sufficiently to ensure
long-term stability of slope.
5. Slope rehabilitation is often required when slope collapses
threaten lives and or properties. We need to ensure the slopes are
designed to withstand long-term slope stability for such cases and not
wait for it to fail before something is done.
6. Combined technology is useful to provide economic solution to
slope rehabilitation works.
REFERENCES
Ooi, T.A. and Tee, C.H. (2004). "Reconstruction of failed
slopes using Geosynthetic Reinforcement in Malaysia", Proceedings
Malaysia Geotechnical Conference, MGC 2004, Kuala Lumpur, P435-447.
Toh, C.T., Chee, S.K. and Ting, W.H. (1986). "Design,
construction and performance of a geogrid reinforced high slope and
unreinforced fill slopes", Proceedings Joint Symposium on
Geotechnical Problems, Kuala Lumpur, P.90-111.
T.A. OOI
TAO Consult Sdn Bhd, 17A, Jalan Awan Hijau, Taman Overseas Union,
Batu 5, Off Jalan Klang Lama, 58200 Kuala Lumpur, Malaysia
C. H. TEE
Mega Geoproducts And Services Sdn Bhd, 40-1, Jalan 2/109E, Desa
Business Park, Taman Desa, Off Jalan Klang Lama, 58100 Kuala Lumpur,
Malaysia
M. J. D. DOBIE
Tensar International Limited, Wisma Sejahtera, Room 407, Jalan
Letjen S Parma, Kav 75, 11410 Jakarta, Indonesia