Soil improvement using a combined vacuum and fill surcharge preloading method.
Chu, Jian ; Yan, Shuwang
A vacuum preloading technique and its implementation in soil
improvement projects are introduced in this paper. A case study using
the combined vacuum and fill surcharge preloading method is discussed to
show how vacuum load can be combined with fill surcharge to consolidate
soil when a surcharge higher than 80 kPa is required. Settlements and
pore pressures data measured during the preloading are analyzed and used
to indicate that the vacuum preloading method and the combined vacuum
and fill preloading scheme adopted are effectiveness.
INTRODUCTION
One of the commonly used soil improvement methods for soft clay is
vacuum preloading. This method has been successfully used in a number of
countries for land reclamation and soil improvement work (Holtz 1975;
Chen and Bao 1983; Bergado et al. 1998; Chu et al. 2000; Yan and Chu
2005). Sand drains and recently prefabricated vertical drains (PVDs)
have often been used to distribute vacuum load and discharge pore water.
A vacuum load of 80 kPa or above can be applied and maintained as long
as it is required. When a higher surcharge load is required, a combined
vacuum and fill surcharge can be applied. Compared with the fill
surcharge method for an equivalent load, the vacuum preloading method is
cheaper and faster (Chu et al. 2000). The vacuum preloading method has
also been incorporated in the land reclamation process when clay slurry dredged from seabed is used as fill material for land reclamation. As
the clay slurry fill is too soft for fill surcharge to be applied, the
vacuum preloading method is ideally used for the consolidation of the
clay slurry. Thousands of hectares of land have been reclaimed in
Tianjin, China, using this method. When the reclaimed land is
subsequently used for industrial or infrastructure developments, the
vacuum preloading method is used again to improve the foundation soil
that consists of a layer of consolidated slurry fill and the underlying
seabed marine clay (Chu et al. 2000; Yan and Chu 2003).
The principles and mechanism of vacuum preloading have been well
explained in the literature, e.g., Kjellman (1952), Holtz (1975) and Chu
et al. (2000). For illustration, the pore water pressure and effective
stress change processes in both fill and vacuum preloading cases can be
explained using a spring piston analogy model shown in Fig. 1.
[FIGURE 1 OMITTED]
The consolidation process of soil under a surcharge load has been
well understood and can be illustrated using the model shown in Fig.
1(a). For the convenience of explanation, the pressures in Fig. 1 are
given in absolute values and [p.sub.a] is the atmospheric pressure. As
shown in Fig. 1(a), the instance when a surcharge load, [DELTA]p, is
applied, it is the excess pore water pressure that takes the load.
Therefore, for saturated soil, the initial excess pore water pressure,
[DELTA][u.sub.0], is the same as the surcharge [DELTA]p. Gradually, the
excess pore water pressure dissipates and the load is transferred from
water to the spring (i.e., the soil skeleton) in the model shown in Fig.
1(a). The amount of effective stress increment equals to the amount of
pore water pressure dissipation, [DELTA]p--[DELTA]u (Fig. 1(a)). At the
end of consolidation, [DELTA]u = 0 and the total gain in the effective
stress is the same as the surcharge [DELTA]p (Fig. 1(a)). It should be
noted that the above process is not affected by the atmospheric
pressure, [p.sub.a].
The mechanism of vacuum preloading can also be illustrated in the
same way using the model shown in Fig. 1(b). When a vacuum load is
applied to the system shown in Fig. 1(b), the pore water pressure in the
soil reduces. As the total stress applied does not change, the effective
stress in the soil increases. The instance when the vacuum
load,--[DELTA]u, is applied, the pore water pressure in the soil is
still [p.sub.a]. Gradually the pore pressure is reducing and the spring
starts to be compressed, that is, the soil skeleton starts to gain
effective stress. The amount of the effective stress increment equals to
the amount of pore water pressure reduction, [DELTA]u, which will not
exceed the atmospheric pressure, [p.sub.a], which is normally 80 kPa in
practice.
VACUUM PRELOADING TECHNIQUE
The schematic arrangement of the vacuum preloading method adopted
is shown in Fig. 2. The construction procedure can be described as
follows. 1). PVDs are installed at a closing spacing of normally 1.0 m
in square grid through the entire depth of the soil that needs to be
treated. If the ground is too soft, a fill of 1 to 2 m can be applied
using sand or other competent fill materials to form a working platform
for the PVD installation rigs. A layer of geogrid can be used in lieu of
fill. Alternatively, a portable, lightweight drain installation rig may
be used. 2). After the installation of PVDs, main corrugated flexible
pipes of 100 mm diameter are laid horizontally to link the PVDs to the
main vacuum pressure line. The pipes were perforated and wrapped with a
permeable fabric textile to act as a filter layer. 3). A sand blanket of
0 .3 m on top is then placed to cover the pipes. 4). Three layers of
thin PVC membrane are laid to seal each section. The membranes are
anchored in a trench at the four sides and backfilled with clay to form
a small dike of 0.3 to 0.5 m to contain the water that will drain out
the PVDs. To cover the membrane with a layer of water can slow down the
deterioration of the membrane caused by direct sun exposure. More
importantly, when the membrane is immersed in water, leakage can be
identified easily by the formation of air bubbles. 5) Vacuum pressure is
then applied using a patented vacuum pumping system. The vacuum pressure
will be applied continuously for several months until the required soil
improvement objectives are achieved. A vacuum pressure of 80 kPa or
above can be achieved and maintained easily using this system. The total
surcharge applied will then be the vacuum pressure plus the fill or sand
blanket used. When a higher surcharge is required, fill surcharge can be
applied in stages after some consolidation of the soil under the vacuum
load.
[FIGURE 2 OMITTED]
Fielding monitoring of vacuum pressure applied to the drain,
settlements and pore water pressure changes are an essential part of a
vacuum preloading project, as whether the method is effective or
implemented properly or not can only be evaluated using the field
monitored data. The field monitoring scheme and the methods of
evaluation will be discussed using the following case study.
CASE STUDY
The described vacuum preloading method has been used in many
projects in China and elsewhere (Shang et al. 1997; Chu et al. 2000; Yan
and Chu 2003). The case presented by Yan and Chu (2005) is used as an
example to illustrate the use of the vacuum preloading technique in soil
improvement works.
A storage yard of 7433 m2 was to be constructed at the Tianjin
Port, China. The storage yard was located on a 16 m thick soft clay
layer. The top 3 to 4 m of the clay layer was reclaimed recently using
clay slurry dredged from seabed. The rest 16 to 19 m was original seabed
clay. The soil in both layers was soft and was still undergoing
consolidation. This soft clay layer needed to be improved before the
site could be used as a storage yard.
Preloading using fill surcharge alone was not feasible as it was
difficult to place a fill embankment several meters high on soft clay.
The vacuum preloading method could be used. However, the nominal vacuum
load of 80 kPa was not sufficient for this project. Therefore, a
combined vacuum and fill surcharge preloading method was adopted. Fill
surcharge of a height ranging from 2.53 to 3.50 m was applied in
addition to the vacuum load and a 0.3 m of sand blanket. The fill was
applied in stages partially for stability consideration and partially
due to practical constraints in transporting fill. The fill used was a
silty clay with an average unit weight of 17.1 kN/[m.sup.3].
The layout of the storage yard is shown in Fig. 3. It was a L-shape
with a total area of 7433 [m.sup.2]. For the convenience of
construction, the site was divided into three sections, I, II and III,
as shown in Fig. 3. The soil conditions in the 3 sections were very
similar. The idealized soil profile together with the typical liquid
limit (LL), plastic limit (PL), water content (w/c), and the field vane shear strength profiles as measured for Section II are shown in Fig. 4.
The water content of the soil was higher than or as high as the liquid
limit at most locations in the soft clays. The field vane shear strength
of the soil was generally between 20 to 40 kPa.
[FIGURES 3-4 OMITTED]
The soil improvement work was carried out by following the method
described in the preceding section. The loading sequence and the ground
settlements induced by the vacuum and surcharge loads for Section II are
shown in Fig. 5. The vacuum load was applied for about 6 weeks before
fill surcharge loads were applied in stages. The total fill height
applied was 3.5 m. The maximum surface settlement induced by the vacuum
and surcharge loads was 1.614 m for Section II. As shown in Fig. 5, a
vacuum pressure of 80 kPa or above was maintained for the whole duration
of soil improvement.
[FIGURE 5 OMITTED]
Instruments including surface settlement plates, multi-level
settlement gauges, inclinometers and standpipes were used. The
settlements monitored by the settlement gauges installed at different
depths during vacuum and surcharge loadings are plotted versus duration
for Section II in Fig. 6. The reductions in the pore water pressures at
different depths are also measured by the piezometers. Based on the pore
water pressure monitoring data, the pore water pressure distributions
with depth at the initial stage, 30 and 60 days and the final stage are
plotted in Fig. 7 for Section II. The hydraulic pore water pressure line
and the suction line are also plotted in Fig. 7. Before the application
of vacuum and surcharge loads, the initial pore water pressures,
[u.sub.0](z), were greater than the hydrostatic pore water pressure,
indicating that the subsoil was still under consolidation. These initial
excess pore water pressures were mainly the remaining pore water
pressures generated during land reclamation and the pore water pressure
induced by the placement of the sand blanket. The total fill surcharge
was about 60 kPa for Section II. The initial pore water pressure
distribution after the application of the fill surcharge is shown as
[u.sub.0] (Z) [DELTA][alpha] in Fig. 7. The suction line for a suction
of -80 kPa is also plotted in Fig. 7 as the line [u.sub.s]. The pore
water pressure distributions at 30, 60 days and the end of preloading
([u.sub.f] (z)) are also shown in Fig. 7. These curves show the changes
of the pore water pressure profiles with time. The area bound by the
final pore water pressure curve, [u.sub.f] (Z), and the suction line,
us, represents the remaining excess pore water pressures that have not
dissipated.
[FIGURES 6-7 OMITTED]
CONCLUSIONS
A vacuum preloading technique and its application in soil
improvement are introduced in this paper. A case study of using vacuum
preloading combined with fill surcharge is presented. The study shows
that the vacuum distribution system comprising PVDs at a square grid of
1.0 m together with horizontal 100 mm diameter corrugated flexible pipes
was effective in distributing the vacuum pressure and collecting drained
water. Vacuum load can be combined with fill surcharge to provide a
combined surcharge much higher than the vacuum load alone. In the case
presented, the ground settled for more than 1.6 m. The pore water
pressure reduced substantially. The case study has proven that the
vacuum preloading technique or a combined vacuum and fill surcharge
scheme is effective for soil improvement works.
REFERENCES
Asaoka, A. (1978). "Observational procedure of settlement
prediction." Soils and Foundations, Vol. 18, No. 4, 87-101.
Bergado, D. T., Chai, J. C., Miura, N., and Balasubramaniam, A. S.
(1998). "PVD improvement of soft Bangkok clay with combined vacuum
and reduced sand embankment preloading." J. Geot. Eng., Southeast
Asian Geot. Soc., Vol. 29, No. 1, 95-122.
Chen, H. and Bao, X.C. (1983). "Analysis of soil consolidation
stress under the action of negative pressure." Proceedings 8th
European Conference on Soil Mechanics and Foundation Engineering,
Helsinki, Vol. 2, 591-596.
Chu, J. Yan, S.W., and Yang, H. (2000). "Soil improvement by
the vacuum preloading method for an oil storage station."
Geotechnique, Vol. 50, No. 5, 625-632.
Chu, J. and Yan, S.W. (2005). "Estimation of Degree of
Consolidation for Vacuum Preloading Projects." International
Journal of Geomechanics, ASCE, Vol. 5, No. 2, 158-165.
Holtz, R. D. (1975). "Preloading by vacuum: current
prospects." Transportation Research Record, No. 548, 26-79.
Kjellman, W. (1952). "Consolidation of clayey soils by
atmospheric pressure." Proc. of a Conf. on Soil Stabilization,
Massachusetts Institute of Technology, Boston, 258-263.
Shang, J.Q., Tang, M. and Miao, Z. (1998). "Vacuum preloading
consolidation of reclaimed land: a case study." Canadian
Geotechnical Journal, Vol. 35, No. 5, 740-749.
Yan, S.W. and Chu, J. (2003). "Soil improvement for a road
using the vacuum preloading method." Ground Improvement, Vol. 8,
No. 2, 35-44.
Yan, S.W. and Chu, J. (2005). "Soil improvement for a storage
yard using the combined vacuum and fill preloading method."
Canadian Geotechnical. Journal, Vol. 42, No. 4, 1094-1104.
JIAN CHU
School of Civil and Environmental Engineering, Nanyang
Technological University, Singapore 639798
SHUWANG YAN
Geotechnical Research Institute, Tianjin University, Tianjin,
300072, China