首页    期刊浏览 2025年11月05日 星期三
登录注册

文章基本信息

  • 标题:Critical factors to be monitored for successful completion of construction projects.
  • 作者:Divakar, K. ; Subramanian, K.
  • 期刊名称:International Journal of Applied Engineering Research
  • 印刷版ISSN:0973-4562
  • 出版年度:2009
  • 期号:August
  • 语种:English
  • 出版社:Research India Publications
  • 摘要:Project schedules are invariably dynamic and uncertain. Various controllable and uncontrollable factors can adversely affect the project schedule and cause delays. Contractors and owners are prone to view most delays as the responsibility of the other person concerned. Consequently, delays may lead to some form of disputes In terms of responsibility, delays can be classified as owner caused, contractor caused or third party caused delays. As their names suggest, an owner-caused or contractor-caused delay is within their control. The third party caused delay is attributable to neither the owner nor contractor.
  • 关键词:Building;Construction;Construction industry;Consulting services;Industrial project management;Management science;Project management;Time management

Critical factors to be monitored for successful completion of construction projects.


Divakar, K. ; Subramanian, K.


Introduction

Project schedules are invariably dynamic and uncertain. Various controllable and uncontrollable factors can adversely affect the project schedule and cause delays. Contractors and owners are prone to view most delays as the responsibility of the other person concerned. Consequently, delays may lead to some form of disputes In terms of responsibility, delays can be classified as owner caused, contractor caused or third party caused delays. As their names suggest, an owner-caused or contractor-caused delay is within their control. The third party caused delay is attributable to neither the owner nor contractor.

Delay in a particular item due to unexpected events puts the contractor in jeopardy. Delayed completion an activity due to various factors may cause delays in succeeding activities in a collection of activities. Construction planners determine the sequence of activities necessary to complete a project. They identify critical activities that are to be completed in time and activities which have flexibility in time of completion.

The project managers are however responsible for the overall success of the project. They have to develop a plan for directing and controlling resources in a coordinated and timely fashion so as to deliver a project within limited and available time. This has limitations in that there is no certainty in factors causing delay and that only certain variables are being monitored (Jeffrey et. al. 1997). As a result, the identification of factors causing delays becomes essential. They are however, onerous tasks.

Critical factors are those few key areas of activity in which favourable results are absolutely necessary for a particular project participant to achieve the target (Rockart 1982). Another perspective for critical factor is that those fundamental issues inherent in the project, that requires day-today attention and operate throughout the life of the project.

Schultz et al. (1987) classified critical success factors in to two groups which affect project performances at different phases of implementation. The first group is referred to as the strategic group that consists of factors like project mission, top management support, and project scheduling. The other group is the tactical group, which consists of factors like client consultation and personnel selection and training.

Pinto and Slevin (1989) through a study identified, project mission; top management support; project schedule-plans; client consultation; personnel; technical tasks; client acceptance; monitoring and feedback; communication; and trouble-shooting as factors influencing the success of a project .

Chan et al. (2001) investigated the project success factors for design and build projects and identified six project success factors. These are project team commitment; client's competencies; contractor's competencies; risk and liability assessment; End users' needs; and constraints imposed by end-users.

Iyer and Jha (2002) identified critical success factors and failure factors and highlighted the essential role of project managers, client's and builder's responsibility to highly influence the project success.

Critical activities identified through scheduling and evaluation techniques such as PERT and CPM involve identification of an activity as a whole to be critical. Even the literature studies referred identify the critical factors in a different perspective. There are involved in the completion of each and every activity whether it is critical or otherwise. Completion of each and every activity is influenced by many underlying factors not only during the course of the activity but also by certain other factors right from the tendering stage of the project.

All aspects or factors that are involved in the project right from the tendering stage, through planning and execution stage are to be studied and the construction planning and scheduling should be done accordingly. Failure to do so at the appropriate stage may finally lead to disputes resulting in the suspension of works or termination of contract.

It is in this context identification of critical factors causing the delay of an activity and hence the project, becomes essential. These factors should be the actual real-time difficulties faced by the project engineers, project managers and builders in the field at the time of execution of the works. The factors so identified should be given high priority at various stages of a project.

Methodology of the Study

The study was taken up in two phases. The first phase involved in the identification of various factors that are likely to cause delay of various activities involved in the project. This was done through personal discussions with various project participants--consultants, builders, project engineers and project managers. About 106 factors were identified in these stages. These factors were analysed and classified under 5 aspects and grouped under 2 stages. The stages considered were: (1) Pre-tendering Stage and (2) Post-tendering Stage.

About 23 factors were classified as Project Background Aspects in the Pretendering Stage. In the Post-tendering Stage four aspects were identified: (a) Planning/Scheduling Aspects consisting of 14 factors, (b) Technical Aspects consisting of 20 factors, (c) Execution Aspects consisting of 30 factors and (d) Management Aspects consisting of 19 factors.

The second phase involved in the identification of the most critical factors which has high influence in causing the delay of the project and that requires the most critical attention at various stages in the real-time monitoring of a construction project. This was done through a questionnaire, circulated to 250 project participants. The respondents were requested to rate each factor on a four point scale indicating the effect it has in the delay of an activity. The ratings are 1--No Effect, 2--Marginal Effect (The delay caused can be fully revived), 3--Significant Effect (the delay caused can be partially revived), 4--Adverse Effect (the delay caused is beyond revival). Background information about the respondents, consisting of their role in construction field, their experience in construction and the size of the projects they are involved were collected. It was decided to study each aspect separately so that the significance of important factors may not be lost. The study about the Technical Aspects of the project is dealt in this paper. About 20 factors identified under this aspect are given in Table 1.

About 60 responses were received. The responses received in the form of ratings on a 4 point Lickert Scale was studied carefully. The respondents included Project Engineers, Project Managers, Builders, Consultants and also Engineers from Government Departments.

Descriptive Statistics of the responses were studied. Ranking of the factors based on the mean of the responses through descriptive statistics was done. A mean value of 2.5 was selected as the base and the factors with a mean of more than 2.5 were identified as critical. The criteria for selecting mean value is that, it is necessary to identify those factors which has significant and adverse effect on the completion of the project.

Test of Analysis of Variance (ANOVA) was done to study the difference in the perception of the importance of these factors by the three group of respondents, namely Project Managers/Engineers, Consultants and Builders. Factors with less than 5% significance is said to have a different perception among the respondents. The results of the ANOVA test are given in Table 3.

To study which group of the respondents perceived differently, Post Hoc (Tukey's B) test was conducted for the factors whose significance value is less than 5%. The test compares the means of the group of respondents. The result of the Post Hoc test is shown in Table 4.

Factor Analysis by Principal Component Analysis Method was done to extract the critical underlying factors. For this purpose the factor with highest mean value of response and less significance in the perception of the respondents was selected as the dependant variable.

Oblique rotation of the reference axes called Varimax Rotation with Kaiser Normalization Criterion was done since the initial factors were initially orthogonal. Factors with Eigen value greater than or equal to 1 were extracted and the initial 20 factors were grouped under the extracted factors based on their loading and the variance explained by each of them. The extracted underlying factors were given a common explanatory name.

The underlying factors extracted were subjected to Stepwise Linear Multiple Regression in order to find out the extent of cause and effect of these factors on the dependent variable.

Results

Descriptive statistics identified 9 factors to have a mean value of more than 2.5. These factors are ranked according to their means and are shown in Table 2.

The ANOVA test indicated that only one factor, Factor No C14--Site area restrictions for fabrication works, storage of building materials and form work and scaffolding materials--was said to have different perception by the respondents. The results of the Test of ANOVA for these factors are given in Table 3.

Post Hoc test indicated that the Consultants perceive the factor differently. The reason may be that they are not experiencing this problem at site as they are not always present at the site during the execution of the works. The result of the Post Hoc test is given in Table 4.

Factor analysis with Varimax Rotation with Kaiser Normalization Criterion, revealed that the 19 independent factors under the Technical Aspects of a construction project identified in this study can be grouped under FOUR underlying factors. The factor C02--Frequent changes in plan, designs and working drawings was selected as dependent variable. The summary of the results of the Factor Analysis is shown in Table 5.

The underlying factors extracted were named as: (1) Utility, Specifications and Technical Details, (2) Role of Consultants, (3) Technical Aspects in respect of Execution (4) Unexpected Changes during Execution. The initial factors grouped under the extracted factors are shown in Table 6.

Linear Multiple Regression of these factors with the dependent factor Frequent Changes in plans, designs and working drawings, revealed that the underlying factor Role of Consultants was said to have a more cause and effect on the dependent variable Frequent changes in plan, designs and working drawings. The summary of the regression with coefficients for the regression model is shown in Table 7.

A regression model equation which is not a functional equation but a cause and effect model was written as follows.

Frequent changes in plan designs and working drawings = 0.010 (constant) + 1.118 (Role of Consultants)

The initial factors which are included under the underlying factor Role of Consultants are, Timely availability of working drawings, Timely feed back from quality control reports, Finalization of working drawings based on field conditions, Changes in techniques as per architects/consultants instructions.

Discussions

The critical factors included in the underlying factor Role of Consultants which was identified by the factor analysis and hence multiple regressions are discussed below.

Timely availability of working drawings

It is the responsibility of the consultant to see that the working drawings are made available considerably in advance. This will enable the builder to plan and mobilize the resources required at the appropriate time.

Timely feed back from quality control reports

Periodic quality control tests are inevitable in large and important infrastructure projects. The reports should be studied by the consultants and the feed back should be given without delay so that the work proceeds without any delay.

Finalization of working drawings based on field conditions

All field data in respect of topography, borehole tests etc should be studied well in advance and the working drawings are finalized. This will avoid any changes in the construction at the later stage.

Change in techniques as per architects/consultants instructions

The changes in techniques suggested or insisted by the consultants frequently will cause re-work or an additional burden on the builder. The reason is that he is not prepared for or he has not anticipated it. The consultant should finalize it before the work commences.

Conclusion

Technical aspects of the project play a very important role in the successful completion of a construction project. The Role of Project Consultant is vital in this regard. Finalizing the techniques to be adopted in construction, collecting all necessary details of the site and the problems at the site and suitably finalizing the design and the working drawings is the main and important role of the consultant. As each and every activity is to go on as per the instructions and guidance of the consultant, the role of the consultant is vital in the successful completion of the construction project.

Hence the consultant should make sure that the finalized working drawings are made available to the builders in time, avoid frequent changes in the techniques and give timely feed back for the quality control reports.

References

[1] Chan, A. P. C., Ho, D. C. K., and Tam, C. M., 2001. "Design and build project success factors: Multivariate analysis." J. Construction Engineering and Management, 127(2), 93--100.

[2] Jeffrey, S. R., Edward, J. J., and Samuel, P. L "Continuous Assessment of Project Performance" Journal of Construction Engineering and Management, 123(1), 64--71.

[3] Pinto, J. K., and Slevin, D. P., 1989. "Critical success factors in R&D projects." Res. Technol. Manage., 32(1), 31--35.

[4] Rockart, J. F., 1982. "The changing role of the information systems executive: A critical success factors perspective." Sloan Manage. Rev., Fall, 3--13

[5] Schultz, R. L., Slevin, D. P., and Pinto, J. K., 1987. "Strategy and tactics in a process model of project implementation." Interfaces, 17(3), 34--46.

Divakar, K (1) and Dr. Subramanian, K (2)

(1) Corresponding Author, Research Scholar and Senior Lecturer in Civil Engineering, Coimbatore Institute of Technology, Coimbatore--641 014, India. Mobile: +91 94433 39279 Email: kdcitce@yahoo.co.in (2) Supervisor, Professor and Head of Civil Engineering Coimbatore Institute of Technology, Coimbatore--641 014, India. Mobile: +91 94434 81681 Email: drkscit@rediffmail.com
Table 1: List of Factors included under Technical Aspects

Factor No.                  Factor Name

C01           Timely availability of working drawings
C02           Frequent changes in plan, designs and working drawings
C03           Changes in techniques as per architects/consultants
                instructions
C04           Timely feed back from quality control reports
C05           Variations/ Difficulties at site in respect of planned
                details
C06           Change or re work due to mistakes
C07           Deviations or changes in the utility of the building
C08           Changes in design and method of execution due to the
                usage of alternate materials or equipments
C09           Implementation of alternate technology to reduce time
                and cost
C10           Finalization of working drawings based on field
                conditions
C11           Changes in planning and designing due to failure in
                obtaining more accurate information regarding site
                conditions
C12           Delay in decisions of location of special equipments
                and necessary constructional details and working
                drawings
C13           Site compatibility of certain equipments which was not
                accounted for at planning stage
C14           Site area restrictions for fabrication works, storage
                of building materials and form work and scaffolding
                materials
C15           Site area restrictions for erecting scaffolding and
                lifts for material handling
C16           Selection of right skilled worker
C17           Disputes in specifications
C18           Coordination/ Sequence among activities
C19           Implementation of new technologies
C20           Problems in the site such as foundation shoring,
                shifting of pipe lines, power lines etc.

Table 2: Ranking of Critical factors identified through
Descriptive Statistics

Factor                 Factor                        Mean   Std.
No.                                                         Deviation

C02      Frequent changes in plan, designs and       2.72   0.993
           working drawings
C12      Delay in decisions of location of           2.67   0.951
           special equipments and necessary
           constructional details and working
           drawings
C11      Changes in planning and designing due to    2.62   0.922
         failure in obtaining more accurate
           information regarding site conditions
C06      Change or re-work due to mistakes           2.6    0.960
C20      Problems in the site such as foundation     2.6    0.764
           shoring, shifting of pipe lines, power
           lines etc.
C16      Selection of right skilled worker           2.58   1.03
C03      Changes in techniques as per                2.55   0.91
         architects/consultants instructions
C13      Site compatibility of certain equipments    2.53   0.873
           which was not accounted for at
           planning stage
C07      Deviations or changes in the utility of     2.52   0.93
           the building

Table 3: Results of ANOVA for the Background Information--Role
in the Construction Field

Factor                   Factor                         Significance
No.

C01      Timely availability of working drawings        0.50
C02      Frequent changes in plan, designs and          0.30
           working drawings
C03      Changes in techniques as per architects/       0.86
           consultants instructions
C04      Timely feed back from quality control          0.87
           reports
C05      Variations/ Difficulties at site in respect    0.85
           of planned details
C06      Change or re-work due to mistakes              0.21
C07      Deviations or changes in the utility of the    0.07
           building
C08      Changes in design and method of execution      0.79
           due to the usage of alternate materials
           or equipments
C09      Implementation of alternate technology to      0.52
          reduce time and cost
C10      Finalization of working drawings based on      0.30
           field conditions
C11      Changes in planning and designing due to       0.96
           failure in obtaining more accurate
           information regarding site conditions
C12      Delay in decisions of location of special      0.98
           equipments and necessary constructional
           details and working drawings
C13      Site compatibility of certain equipments       0.10
           which was not accounted for at planning
           stage
C14      Site area restrictions for fabrication         0.03
           works, storage of building materials and
           form work and scaffolding materials
C15      Site area restrictions for erecting            0.47
           scaffolding and lifts for material
           handling
C16      Selection of right skilled worker              0.56
C17      Disputes in specifications                     0.37
C18      Coordination/ Sequence among activities        0.67
C19      Implementation of new technologies             0.06
C20      Problems in the site such as foundation        0.89
           shoring, shifting of pipe lines, power
           lines etc.

Table 4: Results of the Post Hoc (Tukey's B) Test

Factor Name : Site area restrictions for fabrication works,
storage of building materials and form work and scaffolding
materials

Respondent Group              N    Subset for alpha = 0.05

                                       1            2

Consultants and Others       18       1.83
Project Managers/Engineers   20                    2.45
Builders                     22                    2.5

Table 5: Summary of the Results of Factor Analysis

Extracted Factor Name          Percentage of        Cumulative
                                  Variance        Percentage of
                                 Explained      Variance Explained

Utility, Specifications and        50.30              50.30
  Technical Details
Role of consultants                 7.25              57.55
Technical Aspects in respect        6.80              64.35
  of Execution
Unexpected Changes during           5.98              70.33
  Execution

Table 6: List of Initial Factors included under Underlying
Extracted Factor

Extracted Factor          Initial Factors Included
Name

Utility, Specifications   Deviations or changes in the utility of
and Technical Details     the building

                          Delay in decisions of location of special
                          equipments and necessary constructional
                          details and working drawings

                          Site area restrictions for fabrication
                          works, storage of building materials and
                          form work and scaffolding materials

                          Disputes in specifications

                          Changes in design and method of execution
                          due to the usage of alternate materials
                          or equipments

                          Site area restrictions for erecting
                          scaffolding and lifts for material
                          handling

                          Implementation of new technologies

Role of Consultants       Timely availability of working drawings

                          Timely feed back from quality control
                          reports

                          Finalization of working drawings based
                          on field conditions

                          Changes in techniques as per architects/
                          consultants instructions

Technical Aspects in      Problems in the site such as foundation
respect of Execution      shoring, shifting of pipe lines, power
                          lines etc.

                          Implementation of alternate technology to
                          reduce time and cost

                          Coordination/ Sequence among activities

Table 7: Coefficients for Regression Model

                         Unstandardized   Standardized
                         Coefficients     Coefficients

                                 Std.
Model                    B       Error    Beta           t       Sig.

1 (Constant)             0.010   0.296                   0.034   0.973
   Role of Consultants   1.118   0.118    0.780          9.490   0.000
联系我们|关于我们|网站声明
国家哲学社会科学文献中心版权所有