A survey of information systems development project performance.
Wright, Keith ; Capps, Charles
CURRENT INFORMATION TECHNOLOGY (IT) ISSUES
The rate of information systems development project failure in the
1980s and 1990s was routinely documented to be above 50%, the larger the
development; the more likely it was unsuccessful (SIMPL & NZIER,
2000). A 1994 study of IS development projects in the British public
sector estimated that 20% of expenditures were wasted, and a further 30%
to 40% did not produce perceivable benefits (Wilcocks, 1994). Also in
1994, the U.S. General Accounting Office reported that spending of more
than US$200 billion in the previous twelve years had led to few
meaningful returns. A 1995 study of over 8,000 IS projects by Johnson
revealed that only 16% were completed on time and within budget
(Johnson, 1995). The U.S. Internal Revenue Service, with an annual
computer budget of US$8 billion, managed "a string of project
failures that have cost taxpayers $50 billion a year [mainly defined as
revenue forgone]--roughly as much as the yearly net profit of the entire
computer industry" (James, 1997). Collins and Bicknell (1997)
estimated that public sector failures in the United Kingdom cost 5
billion [pounds sterling]. The Wessex Health Authority's Regional
Information Systems Plan was cancelled after more than 43 million
[pounds sterling] had already been spent, with little achieved (Collins
et al., 1997). The New Zealand Police abandoned an IS development in
1999, at a cost of more than NZ$100 million, after years of development
provided little more than an e-mail system and a number of terminals run
by a 1970s-era mainframe. A study by SIMPL & NZIER (2000) found that
the success rate was only 55% for projects under US$750,000; however,
for those with budgets over US$10 million, no projects were successful.
A 2001 U.S. Standish Group survey of IS projects found success rates
were as follows: 59% in the retail sector, 32% in the financial sector,
27% in manufacturing, and 18% in government. Overall, the average
success rate was 26%. In all, 46% of the projects had problems,
including being over budget, behind schedule, or delivered incomplete.
Another 28% failed altogether or were cancelled, and cost overruns
averaged nearly 200% (SIMPL & NZIER, 2000).
The beginning of the 21st century showed little improvement in IS
development project performance. In 2002, the United Kingdom's
National Health Service initiated the largest-ever public sector project
at an estimated cost of 11 billion [pounds sterling]. This led to the
introduction of new information systems in almost every hospital, but it
was still considered a failure (Rainer & Turban, 2009). A benefit
payment scheme involving the British Post Office, the Department of
Social Security, and the computer company ICL was abandoned after three
years and a cost of 300 million [pounds sterling] (The Economist, 2002).
An already obsolete air-traffic support system opened at Swanson in the
United Kingdom, in 2002, six years late and 180 million [pounds
sterling] over budget (The Economist, 2002). The Canadian Firearms
Program increased from initial estimates of C$113 million to more than
C$1 billion, an overrun of almost 900% (Auditor, 2002). Georgiadou
(2003) found five out of six corporate projects are considered
unsuccessful, with one-third cancelled. Of the two-thirds that were not
cancelled, price and completion times were almost twice what had
originally been planned. Dalcher and Genus (2003) reported US$150
billion was wasted per annum on information and communications
technology failures in the public and private sectors in the United
States and US$140 billion in the European Union. A 2004 Standish Group
report estimated a success rate of 29%, with 53% of the projects having
problems, and a failure rate of 18%. The Royal Academy of Engineering
and the British Computer Society (2004) found that 84% of public sector
projects resulted in failure. Vast sums of money, mostly provided by aid
agencies, have been spent on health and other information systems in
South Africa, on donor-funded IS projects in China, and on World Bank
funded projects in Africa. Overwhelmingly, these projects have resulted
in varying degrees of failure (Heeks, 2002, 2004). The Standish
Group's 2009 report showed only 32% of all projects succeeded,
while 44% were problematic and 24% failed. In the United States the best
known IS project failures are the FBI Trilogy Project (Knorr, 2005; US
GAO, 2006), the California Motor Vehicles Driver Licensing System
(Bozman, 1994), and the Denver airport baggage handling system
(Montealegre & Keil, 2000).
In summary, the consensus is that 20% to 30% of all IS development
projects are perceived as overwhelming failures, while 30% to 60% are
partial failures (Collins et al., 1997; Corner & Hinton, 2002;
Georgiadou, 2003; Heeks, 2002; Iacovou, 1999; James, 1997).
IS projects that run wildly over time and budget have been labeled
"runaways" (Glass, 1998; Mann, 2003). Runaway projects have
been said to take on a life of their own without adding business value
(Zmud, 1980; DeMarco, 1982; Abdel-Hamid & Madnick, 1991; Johnson,
1995; Mahring & Keil, 2008). One of the main reported causes of
"runaway" projects has been said to be management over-
commitment to the project (Keil, 1995). The management behavior that
underlies runaway projects resembles what IS researchers have called the
process of "escalation of commitment to a failing course of
action" (Brockner, 1992; Keil, 1995; Schmidt & Calantone,
2002). The reverse of this process has been defined as IS project
de-escalation (Keil & Robey, 1999; Montealegre & Keil, 2000;
Royer, 2003; Heng et al., 2003). The literature suggests four general
types of determinant factors of project commitment: project,
psychological, social, and organizational. (For a good review see Newman
& Sabherwal, 1996). The tendency for managers to over-commit to an
obviously failing project has lent credence to the strategy that it is
sometimes better to radically change the entire organization rather than
incrementally improve the immediate project team (Pan et al., 2006a,
2006b). This line of research stems from punctuated equilibrium models
that have their roots in biology (Eldredge & Gould, 1972) and are
increasingly being proposed in the organizational sciences (e.g.,
Tushman & Anderson, 1986; Mokyr, 1990; Gersick, 1991).
Most of the research on IS project failure was conducted prior to
the age of IT governance practices put in place after the 2002 Sarbanes
Oxley Act. IT governance implies a management system in which top
management has a much larger influence on IS development project
decision-making. The exploratory research presented here responds to the
need for an improved understanding of IS project performance in the
post-Sarbanes Oxley environment. The primary purpose of this study was
to determine the extent to which, given recent increase in IT governance
practices, runaway projects continue to be common and to help determine
promising new areas for future research in preventative measures.
Another purpose of the study was to determine if, as predicted by
punctuated equilibrium theory, radical organizational changes are more
effective in withdrawing commitment to runaway projects than are
incremental measures.
The remainder of the paper is organized as follows. Next is a
review of the literature around the social and psychological causes of
"runaway" projects. Then we present our research method
followed by a discussion of the results conclusions.
SOCIAL AND PSYCHOLOGICAL CAUSES OF "RUNAWAY" PROJECTS
Management literature identifies four general types of
determinantal factors of project commitment: project, psychological,
social, and organizational (Newman & Sabherwal, 1996; Keil &
Robey, 1999; Pan et al., 2006; Hirschheim, Klein, & Newman, 1991).
Project factors include the costs and benefits as perceived by
management. Projects are considered prone to over-commitment when they
involve a large potential payoff, when they require a long-term
investment before substantial gain, and when setbacks are perceived as
temporary surmountable problems (Keil, 1995; Keil, Man & Rai 2000).
Psychological factors cause managers to believe the project will
eventually be successful (Brockner, 1992). Contributing causes include
the manager's previous experience, the degree to which the manager
feels personally responsible for the outcome (Newman & Sabherwal,
1996), and cognitive biases (Tversky & Kahneman, 1981). Other
research has suggested that managers may engage in a kind of
"self-justification" behavior committing additional resources
to a project instead of ending it and admitting that their earlier
decisions were flawed (Whyte, 1986; Staw & Ross 1987; Ross &
Staw, 1993). This line of research, known as self-justification theory
(SJT), is grounded in Festinger's (1957) theory of cognitive
dissonance. Prospect theory focuses on the cognitive biases that
influence human decision- making under uncertainty. A derivative of this
theory is the so-called "sunk cost" effect in which decision
makers exhibit a tendency to "throw good money after bad"
(Garland & Conlon, 1998). That research suggests that sunk costs may
influence decision makers to adopt a negative frame, promoting
risk-seeking (IS project escalation) behavior. Approach-avoidance theory
suggests there is a natural tendency for management to over-commit to IS
projects because of the "completion effect," which suggests
the motivation to achieve a goal increases as an individual gets closer
to that goal (Garland & Conlon, 1998; Pan et al., 2006). The
completion effect is particularly relevant to software projects, which
frequently exhibit the so-called "90% complete" syndrome
(DeMarco, 1982; Garland & Conlon, 1998).
Social factors also promote IS project over-commitment (Newman and
Sabherwal, 1996; Pan et al., 2006). Social factors include competitive
rivalry with other social groups, the need for external justification,
and norms for consistency (Brockner et al., 1979; Hirschhem, Klein,
& Newman, 1991). Projects are prone to over-commitment when
competitive rivalry exists between the decision-making group and another
social group, when external stakeholders believe the project will be
successful, or when norms of behavior favor persistence (Ross &
Staw, 1993). One social determinant of commitment is "the desire
not to lose face or credibility with others" (Staw & Ross
1987). The concept of "face saving" is grounded in
self-justification theory (Whyte, 1986; Staw & Ross, 1987; Ross
& Staw, 1993) and is discussed in the IS project de-escalation
literature (Montealegre & Keil, 2000).
Organizational factors in project over-commitment include the
structural and political factors that form the "ecosystem" of
a project. Information systems researchers (e.g., Keil, Mann & Rai,
2000) have referred to several other organizational factors that may
affect commitment to an IS project: top management's knowledge of
information technology (Vitale et al., 1986), information intensity of
the organization's value chain (Johnston & Carrico, 1988), and
the maturity of the IS function (Sabherwal & King, 1992). Other
organizational factors identified in the literature include top
management support for the project, administrative inertia in the
organization, the extent of project institutionalization, and the extent
to which it is perceived as strategic (Johnston & Carrico, 1988).
More recent work on IT project de-escalation suggests projects may
be resistant to de-escalation because long periods of organizational
"equilibrium" periods are difficult to disrupt because of the
constancy of the "deep structure" of the organization
(Gersick, 1991; Pan et al., 2006; Orlikowski, 1993). As a result,
organizations may be unable to change substantially unless forced by a
radical organization change or other crisis (Tushman & Romanelli,
1985; Sastry, 1997). In a number of industries, it has been observed
that long periods of unsuccessful "incremental" organizational
change tend to be interrupted by short periods of radical change called
"revolutionary periods" (Abernathy & Utterback, 1978;
Utterback & Suarez, 1993). This pattern termed "punctuated
equilibrium," was originally identified in the biological sciences
(Eldredge & Gould, 1972) and was subsequently adopted in the
management literature (e.g., Tushman & Anderson, 1986; Mokyr, 1990).
According to punctuated equilibrium theory, organizations tend toward
"equilibrium" because of the permanence of the
organization's "deep structure." The deep structure of an
organization consists of its "alliances, associations and co
operations with interlocking interests" (Anderson & Tushman,
1990). This analysis complements Tushman and Romanelli's (1985)
identification of "performance pressures ... whether anticipated or
actual" as the fundamental agents of organizational reorientation.
Tushman, Newman, & Romanelli (1986) described the scenario of an
organization falling into serious trouble before responding by replacing
its top management as typical. They found "externally recruited
executives are more than three times more likely to initiate
frame-breaking change than existing executive teams ... Failures caused
by inappropriate deep structures are destined to elude the (misdirected)
efforts of current system members to correct them. Unless such failures
kill the system, they command increasing attention and raise the
likelihood that newcomers will either be attracted or recruited to help
solve the problems. The newcomer has the opportunity to see the system
in an entirely different context than incumbent members, and he or she
may begin problem solving on a new path" (Tushman, Newman, &
Romanelli, 1986).
The preceding review demonstrates the extreme complexity of the
study of information system (IS) development project performance.
Existing research demonstrates the presence of many important factors
that affect such a project. This raises the question of the most
important areas for further IS practice research: Should the focus be on
the subtleties of the various indirect psychological and social factors
mentioned above? Or, is it more practical to concentrate on the practice
of project management itself? The answers to these questions are the
impetus for this study.
RESEARCH METHOD
In order to address these research questions concerning IS
development projects a simple questionnaire was developed to survey IT
audit professionals. The design of the survey was based on
Dillman's (1978) "total design method." Auditors were
selected for the study because they are likely to be more objective than
other IS project stakeholders, such as managers directly responsible for
problematic projects. The sample was designed to select professional IT
auditors who would be most likely to be involved in information systems
development. The pool of individuals represented approximately one
thousand (1000) Information Systems Audit and Control Association
(ISACA) members in the Houston, Texas area. The survey was designed to
gather data concerning the perceived frequency of problematic IS
development projects, the perceived major sources of problems, and the
recommended magnitude of corrective actions. A survey is usually the
most cost-effective way of collecting data on a large number of IS
projects (Mann, 1996). To get a reasonable response rate, the survey was
designed to be completed in less than ten minutes. To ensure the survey
questions demanded minimal cognitive effort, questions consisted mostly
of paired category choices.
The pool of one thousand auditors (1000) was emailed a link to the
survey that was posted on the international ISACA web site. The
approximately one hundred (100) respondents were asked to consider
projects with which they were familiar that fit the definitions of
"problematic," "runaway," and "failed" on
the survey form. The survey had five sections: introduction,
demographics, project performance, corrective actions, and closing.
Please see Appendix A for the actual survey questions. The survey was
refined through two iterations of pre-testing.
The demographics of the sample are shown in Tables 1, 2, 3 and
Table 12 below. Almost half the respondents reported having more than
fifteen years experience, while over 40% reported having more than five
years experience. Almost 80% reported having the Certified Information
Systems Auditor (CISA) certificate; and, about half reported they had
been involved with either a problematic or a runaway project (Table 12).
Variables, such as auditor experience, could have affected the
results. However, a similar survey of IT auditors showed these variables
did not affect overall results (Keil et al., 2000). Thus, to keep the
survey brief, we chose not to control for these factors. Furthermore, as
was the case in Keil et al. (2000), our method did not allow us to
measure non-response bias. To increase the reliability of the survey
instrument, three different measures of project performance were
operationalized: (1) "failed" projects, (2)
"problematic" projects and (3) "runaway" projects
RESULTS AND DISCUSSION
OVERALL PROJECT PERFORMANCE
The results for overall project performance are shown in Table 4.
Significantly more of the respondents reported the overall rate for both
problematic and failed projects are above 50%. These high frequencies
are corroborated by the fact that 40% of the respondents reported having
been involved with a "runaway," and 60% reported involvement
with a "problematic" project (See Table 12). The findings
regarding "runaways" reported here appear to contrast sharply
with researchers who contend that software project runaways are rare
events (Glass, 1997).
SOURCES OF PROJECT PROBLEMS
As can be seen in Tables 6 and 7, the most important sources of
problems for both problematic and runaway projects were perceived to be
formal attributes of the project team such as size, skills, etc., rather
than informal social or psychological attributes of project
stakeholders.
GOVERNMENT VERSUS PRIVATE SECTOR PERFORMANCE
Table 8 shows significantly more respondents believed that all
three project types--failed, problematic, and runaway--are more likely
to occur in government than industry. We argue that this result is
consistent with that predicted by punctuated equilibrium theory (the
argument is presented as an informal theorem in Table 7).
THE ROLE OF "COLLECTIVE BELIEF" IN MANAGEMENT
OVER-COMMITMENT
Another important determinant of management commitment to an IS
project has been termed the "collective belief" in the
eventual success of the project (Royer, 2002). Our results suggest that
government managers seem less confident in their abilities than do
private sector executives (See Table 8, question 2.2) and that
government is more likely to produce runaways and failures than is the
private sector (Table 9, question 3.11). However, these results run
counter to that reported in Royer (2002). There it was found that
"collective belief" in the eventual success of the project was
a primary determinant of management over-commitment.
CORRECTIVE ACTIONS, INCREMENTAL OR RADICAL?
Survey section three (corrective actions) was designed in part to
measure whether, as predicted by punctuated equilibrium theory,
respondents thought it more effective to apply radical (aka
"revolutionary") measures to turn around "runaway"
projects than to apply more moderate (aka "incremental") ones
(Gersick, 1991). These results are consistent with the punctuated
equilibrium argument presented as an informal theorem in Table 9: for
"runaway" projects, question 3.8 (See Table 11) respondents
believed it more beneficial to choose the radical action of replacing
project management rather than the incremental action, simply educate
them. However, for "problematic" projects, the respondents
reported the opposite conclusion: that an incremental change (i.e.,
education) is more beneficial than the more radical change, replacing
staff (See Tables 11 and 12). Overall though, our results strongly
support the conclusion that project factors are more important than
organizational factors in determining project failure or success.
CORRECTIVE ACTIONS, TOP MANAGEMENT OR MIDDLE MANAGEMENT?
In all cases, our respondents believed it more beneficial to take
corrective action at the project management level than at the top level
of management (See Tables 11 and 12). These results suggest the most
important causes and remedies for poor project performance have to do
more with project management practices than with the structure of the
surrounding organization. This does not support the notion that IT
governance initiatives introduced by many large organizations early in
the 21st century have improved performance of IS development projects.
RISK AVERSION IN RUNAWAY PROJECTS
Another purpose of the study is to help managers decide on an
appropriate level of risk aversion in "runaway" projects. On
survey question 3.12 (See Table 4) respondents reported an insignificant
difference between those that believe managers prematurely kill runaway
projects less than 20% of the time, and those that believe mangers
prematurely kill runaway projects more than 20% of the time. Thus, we
speculate that managers actually kill projects prematurely about 20% of
the time. How managers feel about this likelihood is important to the
organization's bottom line. For example, suppose management decides
to kill any project at the first sign it is escalating. If so, the
organization may often kill good projects prematurely, experiencing loss
and committing what Keil and his colleagues (Keil et al., 2000) called a
"Type 1" error. On the other hand, allowing too many cases of
escalation to be continued on the grounds the project may be incorrectly
classified (a "Type 2" error) causes loss by wasting valuable
resources. These results suggest that managers tend to be too
risk-aversive to runaway projects. Consequently, we believe managers
should include this new information in determining an appropriate
balance between Type 1 and Type 2 errors.
SUMMARY AND CONCLUSION
IMPLICATIONS FOR PRACTICE
In summary, we believe this study's primary contribution to
the practice of IS project management is the evidence it provides
concerning the prevalence of project over-commitment in both government
and private industry in the 21st century. The results suggest most large
IS projects will exceed their original budgets and timelines by more
than 50%, and much more often in government than in private industry.
Second, the study provides evidence corroborating Keil et al. (2000)
that "runaway" projects occur frequently, and new empirical
evidence that they occur more often in government. Furthermore, the
study supports other research that suggests "runaway" projects
should be treated fundamentally differently from merely problematic
projects, in that more radical organizational changes are needed to
reduce management commitment ((Pan et al., 2006a, 2006b; Wright &
Capps, 2010). In addition, the results imply managers should consider
being more aggressive in promptly shutting down projects that show signs
of over-commitment before they needlessly waste valuable resources. The
results suggest mangers prematurely kill escalating projects only about
20% of the time. Finally, the results support the idea that nothing is
more important in promoting successful IS development project outcomes
than best project management practices.
Our survey respondents consistently rated project management
factors more important than top management factors in determining
project success. Furthermore they rated formal organizational factors
more important than informal social or psychological factors. (See
Tables 5 and 6).
These particular results underscore the importance of good
monitoring of projects. And as Keil et al. (2000) suggest: "To
minimize the problems associated with project escalation, managers would
do well to implement early warning systems aimed at detecting escalation
as early as possible. One way to minimize budget and schedule escalation
is to define the de-escalation trigger points at the outset of the
project. In this way, when the cost and schedule begin to approach the
predefined trigger points, managers can take steps to de-escalate the
project and contain the damage. Another related tactic is defining
termination conditions at the outset of the project" (Keil et al.,
2000). There is a wealth of information on the best practices in IS
software development published by Carnegie Mellon's Software
Engineering Institute (http://www.sei.cmu.edu/) and the University of
Texas' software quality institute
(http://lifelong.engr.utexas.edu/sqi/index.cfmj (See also Wright &
Capps, 2008).
To sum up, our study's data does not support a conclusion that
IT governance measures implemented by many large organizations in the
early 21st century have measurably improved IS development project
performance. On the contrary, our results support the Standish Group
2009 report, which indicated that such projects are performing worse
than they did in the 20th century.
IMPLICATIONS FOR FUTURE RESEARCH
The most interesting research questions this exploratory study
raises are related to why IS development projects "run away"
or fail significantly more often in government than in private industry.
The results indicate that all three project types--failed, problematic,
and runaway--are much more likely to occur in government than industry.
Is this because the deep structure of government organizations is more
resistant to change than that of the private sector? Such a result would
be consistent with that predicted by punctuated equilibrium theory (See
Table 7). Other unanswered questions related to punctuated equilibrium
theory are whether government projects are more often
"over-committed" than those in private industry; and, what are
the conditions under which incremental organizational changes are
preferable to radical changes? Our results suggest that under certain
conditions an incremental change, education, is more beneficial than a
more radical change, replacing staff (See Tables 9 and 10). However, for
"runaway" projects, question 3.8 (See Table 11), this pattern
was reversed: the respondents believed it more beneficial to replace
project management staff rather than simply educate them.
Because project failure is a politically sensitive subject, and
thus difficult to study empirically, many more in-depth case studies are
needed, with an aim of generating an explanatory theory of project
escalation and de-escalation cycles (Pan et al., 2006a, 2006b; Wright
& Capps, 2010). Our results support the claim others have made that
further insights can and will come from punctuated equilibrium theory
(Eldredge & Gould, 1972; Tushman & Anderson, 1986; Mokyr, 1990;
Gersick, 1991; Wright & Capps, 2010) as well as from other
organizational theories (Sutton, 1987; Eisenhardt, 1989; Ancona, 1990;
Isabella, 1990; Pettigrew, 1990; Elsbach & Sutton, 1992; Shenhar,
1998; Cule & Robey, 2004).
What's more we believe there is a need for the IS audit and
academic community to join hands in conducting further pragmatic
research. Global surveys of IS auditors concerning the frequency,
circumstances and characteristics of problematic IS development projects
would be helpful. There are several advantages of relying on IS auditors
for this type of research. As reported by Keil et al. (2000) these
include: "... IS auditors do not have directly vested interests in
project outcomes because their careers are unlikely to be made or broken
by a project's success or failure; IS auditors can be expected to
report more objectively than managers and other project participants; IS
auditors have access to objective data on project performance; and IS
auditors have experience with multiple projects and formal standards for
judging projects" (Keil et al., 2000). Unfortunately, the
Information Systems Audit and Control Association in recent years has
reduced its support for global survey research.
The outsourcing literature (See Tiwana & Bush, 2007) also
promises to be of help in the study of IS development project
performance. The relationship between control practices and the project
commitment escalation process is an additional promising area for future
research (See Kirsch, 1997; Mahring, 2002; Kirsch, 2004; Tiwana &
Bush, 2007). Another area for research would be to go beyond the results
of Mahring (2002) and Kirsch (2004) to explore whether the constitution
and effectiveness of Information Technology Governance is inversely
related to management over-commitment to projects. Specifically, it
would be of interest to determine if the organization's ability to
adapt control practices to the dynamic nature of complex projects
reduces the likelihood of escalation periods. The relationship between
over-commitment and the requirements determination process is also a
promising one for future research (See Kirsch & Haney, 2006).
LIMITATIONS OF THE STUDY
Because our research was limited to proxy measurements consisting
of the beliefs of self-reported information systems (IS) auditors, the
conclusions drawn herein must be interpreted with caution. Admittedly,
this method raises the possibility of bias or an error in the data set.
It is conceivable auditors are more likely to be assigned to troubled
projects and thus their estimates of the frequency of project problems
may be biased upward. Conversely, IS auditors may tend to be employed by
organizations more aware of the need for good project management. If so,
it is possible that IS auditors' estimates of project problems may
be biased downward. Further, this study's data may have been more
reliable if it had been gathered from specific individual projects.
However, such an approach was not deemed appropriate or necessary
for an initial exploratory study. Because the study relied on
self-reported information concerning past events, the results are also
limited by possible recall bias. However the same research method has
been used in similar research (i.e., Keil et al., 2000) and we know of
no effective methods for avoiding subject recall bias. Despite these
limitations of the methodology, we believe this study contains important
contributions to research and practice of information systems
development.
REFERENCES
Abernathy, W. & Utterback, J.M. (1982). Patterns of industrial
innovation. In M. Tushman and W. Moore (eds.) Readings in the Management
of Innovation, 97-108. New York: Harper Business.
Abdel-Hamid, T. & Madnick, S.E. (1991). Software project
dynamics: an integrated approach. Englewood Cliffs, NJ: Prentice-Hall,
Inc.
Ancona, D. (1990). Outward bound: strategies for team survival in
an organization. Academy of Management Journal, 33 (2), 334-365.
Anderson, P. & Tushman, M.L. (1990). Technological
discontinuities and dominant designs. Administrative Science Quarterly,
35, 604-633.
Auditor General of Canada (2002). Report of the Auditor General of
Canada to the House of Commons. Toronto: Office of the Auditor General.
Be skeptical about what can be achieved by IS developments. Pessimism,
Computer Failure, and Information Systems Development 927 www.oag-
vg.gc.ca/domino/reports.nsf/html/02menu_e.html.
Bozman, J. S. (1994). California kills failed $ 44M project.
Computerworld, May 9, 1994.
Brockner, J. (1992). The escalation of commitment to a failing
course of action: toward theoretical progress. New York: Wiley and Sons.
Collins, T. & Bicknell D. (1997). Crash: learning from the
world's worst computer disasters. New York: Simon & Schuster.
Corner, I. & Hinton M. (2002). Customer relationship management
systems: implementation risks and relationship dynamics. Qualitative
Market Research, 5 (4), 239-51.
Cule, P. & Robey, D. (2004). A dual-motor, constructive process
model of organizational transition. Organizational Studies, 25 (2),
229-260.
Dalcher, D. & Audley, G. (2003). Avoiding IS/IT implementation
failure. Technology Analysis and Strategic Management, 15 (4), 403-7.
Demarco, T. (1982). Controlling software projects. New York:
Yourdon Press.
The Economist (2002). The health service's IT problem. October
19, 2002, pages 51-52.
Eldredge, N. & Gould, S. (1972). Punctuated equilibria: an
alternative to phyletic gradualism, in T. J. Schopf (eds.), Models in
paleobiology, pages 82-115. San Francisco: Freeman, Cooper and Co.
Elsbach, K.D. & Sutton, R.I. (1992). Acquiring organizational
legitimacy through illegitimate actions: a marriage of institutional and
impression management theories. Academy of Management Journal, 699-738.
Festinger, L.A. (1957). Theory of Cognitive Dissonance. Evanston,
IL: Row, Peterson Publishers.
Garland, H. & Conlon, D. E. (1998). Too close to quit: the role
of project completion in maintaining commitment. Journal of Applied
Social Psychology, 28 (22), 2025-2048.
Georgiadou, E. (2003). Software process and product improvement: a
historical perspective. Cybernetics and Systems Analysis, 39 (1),
125-42.
Gersick, C. (1991). Revolutionary change theories: a multilevel
exploration of the punctuated equilibrium paradigm. Academy of
Management Review, 16 (1), 10-36.
Glass, R. L. (1998). Software runaways. Upper Saddle River, NJ:
Prentice-Hall, Inc.
Goldfinch, S. (2007). Pessimism, Computer failure and information
systems development in the public sector. Public Administration Review.
September/October 2007.
Heeks, R. (1999). Reinventing government in the information age:
international practice in IT-enabled public sector reform. London:
Routledge.
Heeks, R. (2002). Failure, success and improvisation of information
system projects in developing countries. Development Informatics Working
Paper Series, No. 11/2002. Manchester, UK: Institute for Development
Policy and Management. Public Administration Review. September/October
2007.
Heeks, R. (2004). eGovernment as a carrier of context. iGovernment
Working Paper Series, No. 15. Manchester UK: Institute for Development
Policy and Management, University of Manchester.
Heng, Tan, B. & Wei, K. (2003). De-escalation of commitment in
software projects: who matters? what matters? Information and
Management, 41, 99-110.
Hirschheim, R., Klein, H.K. & Newman, M. (1991). Information
systems development as social action: theoretical perspective and
practice, OMEGA, 19 (6), 587-608.
Isabella, L.A. (1990). Evolving interpretations as a change
unfolds: how managers construe key organizational events. Academy of
Management Journal, 33 (1), 7-41.
Iacovou, C. (1999). The IPACS project: when IT hits the fan.
Journal of Information Technology 14 (2), 267-275.
James, G. (1997). IT fiascoes and how to avoid them. Datamation,
November 1997, pages 84-88.
Johnson, J. (1995). Chaos: the dollar drain IT project failures.
Application Development Trends, 2 (1), 41-47.
Johnston H.R. & Carrico S.R. (1988). Developing capabilities to
use information strategically. MIS Quarterly, 12 (1) , 37-48.
Keil, M. (1995). Pulling the plug: software project management and
the problem of project escalation. MIS Quarterly, 19 (4), 421-447.
Keil, M. & Robey, D. (1999). Turning around troubled software
projects: an exploratory study of the de-escalation of commitment to
failing courses of action. Journal of Management Information Systems, 15
(4), 63-87.
Keil, M., Mann, J. & Rai, A. (2000). Why software projects
escalate: an empirical analysis and test of four theoretical models, MIS
Quarterly, 24 (4), 631-664.
Keil, M., Rai, A., Mann, J. & Zhang, G. P. (2003). Why software
projects escalate: the importance of project management constructs. IEEE
Transactions on Engineering Management, 50, pages 251-261.
Kirsch L.J. (1997). Portfolios of control modes and IS project
management. Information Systems Research, 15, 374-395.
Kirsch, L. J. (2004). Deploying common systems globally: the
dynamics of control. Information Systems Research, 15 (4), 374-395.
Kirsch, L. J. & Haney, M. H. (2006). Requirements determination
for common systems: turning a global vision into a local reality. The
Journal of Strategic Information Systems, 15 (2), 79-104.
Knorr, E. (2005). Anatomy of an IT disaster: how the FBI blew it,
Infoworld.com. March 21, 2005.
Mahring, M. (2002). IT project governance. Economic Research
Institute (EFI). Stockholm School of Economics: Stockholm, Sweden.
Mahring, M. & Keil, M. (2008). Information technology project
escalation: a process model. Decision Sciences, 39 (2) , 239-272.
Mann, J. (2003). Preventing runaway IT projects: protecting
auditors from entrapment. The Proceedings of Americas Conference on
Information Systems, August 4-5, 2003 in Tampa, FLA.
Montealegre, R., & Keil, M. (2000). De-Escalating information
technology projects: lessons learned from the Denver international
airport. MIS Quarterly, 24 (3), 417-447.
Mokyr, J. (1990). The lever of riches. Oxford UK: Oxford University
Press.
Newman, M. & Sabherwal, R. (1996). Commitment determinants to
information systems development: a longitudinal investigation. MIS
Quarterly, 20, 23-54.
Orlikowski, W.J. (1993). CASE tools as organizational change:
investigating incremental and radical changes in systems development.
MIS Quarterly, 17 (3), 309-340.
Pan, S.L., Pan, S.C., Newman, M. & Flynn, D. (2006a).
Escalation and de-escalation for commitment to information systems
projects: insights from a project evaluation model. European Journal of
Operational Research, 17 (3), 1139-1160.
Pan, S.L., Pan, S.C., Newman, M. & Flynn, D. (2006b).
Escalation and de-escalation for commitment: a commitment transformation
analysis of an e-government project. Information Systems Journal, 16,
3-21.
Pettigrew, A.M. (1990). Longitudinal field research on change:
theory and practice. Organization Science, 1 (3), 267-292.
Rainer, R. & Turban, E. (2009). Huge problems at Britain's
national health system. In Introduction to Information Systems, (pages
321-323). Hoboken, NJ: John Wiley & Sons.
Ross, R.J. & Staw, B. M. (1986). Expo86: an escalation
prototype. Administrative Science Quarterly, 3 (1), 274-297.
Ross, R.J. & Staw, B. M. (1993). Organizational escalation and
exit: lessons from the Shoreham Nuclear Power Plant. Academy of
Management Journal, 36 (4), 701-732.
Royal Academy of Engineering, and British Computing Society (2004).
The Challenges of Complex IT Projects. London: Royal Academy of
Engineering.
Royer, I. (2002). Escalation in organizations: the role of
collective belief. Academy of Management Conference held in Denver, CO.
Royer, I. (2003). Why bad projects are so hard to kill. Harvard
Business Review, February, 2003, pages 49-56.
Sabherwal, R. & King, W.R. (1992). Decision processes for
developing strategic Apps of IS: a contingency approach. Decision
Sciences, 23 (4), 917-943.
Schmidt, J. B. & Calantone, R. J. (2002). Escalation of
commitment during new product development. Journal of the Academy of
Marketing Science, 30 (2), 103-118.
SIMPL (2000). SIMPL Group, and New Zealand Institute of Economic
Research (NZIER), 2000. Information Technology Projects: Performance of
the New Zealand Public Sector in Performance. Report to the Department
of the Prime Minister and Cabinet. Wellington.
Standish Group (2001). Extreme Chaos.
http://standishgroup.com/sample_research/register.php.
Standish Group (2004). Third Quarter Report.
http://standishgroup.com/sample_research/register.php.
Standish Group (2009). CHAOS Summary 2009.
http://standishgroup.com/sample_research/register.php.
Staw, B.M. (1997). "The escalation of commitment: an update
and appraisal," Chapter 9 in Organizational Decision Making. Z.
Shapira (eds.). Cambridge, UK: Cambridge University Press, pages
191-215.
Staw, B. M. & Ross, J. (1987). Behavior in escalation
situations: antecedents, prototypes and solutions. Research in
Organizational Behavior, pages 39-78. B. M. Staw and L. L. Cummings
(eds.), JAI Press Inc. of Greenwich, CT.
Sutton, R.I. (1987). The process of organizational death:
disbanding and reconnecting. Administrative Science Quarterly, 32 (4),
542-569.
Tiwana, A. & Bush, A. A. (2007). A comparison of transaction
cost, agency, and knowledge-based predictors of IT outsourcing
decisions: a U.S.-Japan cross cultural field study. Journal of
Management Information Systems, 24 (1), 259-300.
Tushman M. & Anderson A. (1986). Technological discontinuities
and organizational environments. Administrative Science Quarterly, 31,
439-465.
Tushman, M. & Romanelli, E. (1985). Organizational evolution: a
metamorphosis model of convergence and reorientation. In L. L, Cummings
and B. M. Staw (eds.), Research in organizational behavior, pages 171-
222.
Tushman, M. L., Newman, W. H. & Romanelli, E. (1986).
Convergence and upheaval: managing the unsteady pace of organizational
evolution. California Management Review, 29 (1), 29-44.
Tversky, A. & Kahneman, D. (1981). Framing of decisions and the
psychology of choice. Science, 211, 453-458.
US GAO. (2006). Weak controls over trilogy project led to payment
of questionable contractor costs and missing assets, GAO Report to
Congressional Requesters. Government Accountability Office. GAO-06-306
February 2006.
Utterback, J.M. (1994). Radical innovation and corporate
regeneration. Research Technology Management, 37 (4), 10-18.
Vitale, M., Ives, B. & Beath, C.M. (1986). Linking information
technology and corporate strategy: an organizational view. Proceedings
of the Seventh International Conference on Information Systems. San
Diego, CA; 265-276.
Whyte, G. (1986). Escalating commitment to a course of action: a
reinterpretation. Academy of Management Review, 11 (2), 311-321.
Whyte, G., & Fassina, N. E. (2007). Escalating commitment in
group decision-making. Proceedings of the Academy of Management, l-6.
Philadelphia: August 2007.
Wilcocks, L. (1994). Managing information systems in U.K. public
administration: issues and prospects. Public Administration, 72 (1),
13--32.
Wright, M.K. & Capps, C.J. (2008). Information technology
customer service: 'Best Practices' processes for operations.
Journal of Applied Business Research, 24 (3), 63-76.
Wright, M.K. & Capps, C.J. (2010). Runaway information
technology projects: a punctuated equilibrium analysis. International
Journal of Information Technology Project Management, 1 (4) October
2010.
Zmud, R. W. (1980). Management of large software efforts. MIS
Quarterly, 4, 45-55.
Keith Wright, University of Houston Downtown
Charles Capps, Sam Houston State University
Table 1: Length of Participant Professional Experience
Question # Category Responses
3.1 More than one year experience 87%
3.2 More than 15 years 48%
3.3 Between 5 and 15 years 45%
Table 2: Type of Participant Industry Experience
Question # Category Responses
3.3 Financial Services 22.4 %
US State Government 4.7 %
National Government 8.2 %
Manufacturing 31.8%
Trade 14.1 %
Health Care 10.6 %
Transportation 8.2 %
Table 3: Participant Credentials
Question # Category Responses
3.4 CIA (Certified Internal Auditor) 28.6 %
CISSP (Certified Information Systems Security 23.4 %
Professional)
CISA (Certified Information Systems Auditor) 77.8 %
PMP (Project Management Professional) 26.9 %
Table 4: Perceived Overall Project Performance
Measurement Construct Survey Response Choice Responses
Question #
Project failure rate 2.1 Greater than 50% 62.5%
Less than 50% 37.5%
Problematic project rate 2.5 Greater than 50% 65.0%
Less than 50% 35.0%
Problematic projects 3.5 Greater than 50% ** 66%
become runaway Less than 50% ** 33%
Rate at which runaways 3.10 Less than 20% 71.6%
are turned around Greater than 20% 28.4%
Premature project 3.12 Less than 20% 55.4%
termination rate More than 20% 44.6%
** Indicates that differences in the proportions are not
statistically significant
Table 5: Perceived Causes of Problematic Projects
Survey Response Choice Most likely Least likely
Question # cause cause
2.7 Formal attributes of the 68.0 % 31.7 %
project team (size,
structure, skills, etc.)
Formal attributes of the 63% 34 %
surrounding enterprise
(size, structure, skills,
etc.)
Informal social 31.0 % 68.3 %
relationships among the
project stakeholders
Psychology of individual 48 % 50 %
project stakeholders
(beliefs, fears,
motivations, confidence,
etc.)
Table 6: Perceived Causes of Runaway Projects
Response Choice Most Least
likely cause likely cause
Survey Formal attributes of the 75% 25%
Question 3.9 project team (size,
structure, skills, etc.) 63% 37%
Formal attributes of the
surrounding enterprise
(size, structure, skills,
etc.)
Informal social 27% 73%
relationships among the
project stakeholders
Psychology of individual
project stakeholders 45% 55%
(beliefs, fears,
motivations, confidence,
etc.)
Table 7: Punctuated Equilibrium: the "Deep Structure" Theorem
8.1 If an organizational structure is controlled by elected
government officials, its "deep structure" is harder to change
than that of private industry.
8.2 If the deep structure" of an organization is relatively harder
to change, it will be relatively more likely to produce
over-committed projects.
8.3 If management is over-committed to a project, it is more
likely to runaway or fail.
8.4 Therefore runaway projects and failed projects should be
expected to occur more often in government than in the private
sector, all other things equal.
Table 8: IS Project Performance: Government versus Private Sector
Measurement construct Survey Government Private
Question # Sector Sector
Most likely sector for 2.6 71.3 % 28.8%
problematic projects
Most likely sector for failed 2.3 78 % 21%
projects
Most confident sector 2.2 11.2 % 89%
Most likely sector for runaway 3.11 80.0 % 20.0%
projects
Table 9: Punctuated Equilibrium: the Revolutionary Changes Theorem
9.1 The "deep structure" of an organization consists of more
members of top management than of project management.
9.2 The deep structure of an organization is more likely to be
changed by a radical (or revolutionary) change than by a more
modest (or incremental) change (Gersick, 1991).
9.3 Replacing top management constitutes a more radical
organizational change than does educating top management.
9.4 Radical organizational changes are more effective in correcting
runaway projects than are incremental changes. (From 8.2, 8.3
and 10.1--10.3)
Table 10: Correcting Problematic Projects
Survey Question # Response Choices Responses
3.1 Improving top management 39.1%
Improving project management 60.9%
3.2 Replacing top management 4.3%
Educating top management 95.7%
3.3 Replacing project management 39.1%
Educating project management 60.9%
Table 11: Correcting Runaways Projects
Survey Question # Response Choices Responses
3.6 Improving top management 36.2%
Improving project management 63.8%
3.7 Replacing top management 18.8%
Educating top management 81.2%
3.8 Replacing project management 68.1%
Educating project management 31.9%
Table 12: Perceived Causes of Problematic Projects
Survey Response Choice % Responses
Question #
3.5 Rate that problematic Greater than Less than
projects become "runaways" 50% ** 60% 50% ** 40%
3.12 Premature runaway Less than Greater than
termination rate 20% ** 57% 20% ** 43%
2.4 Percent involved with a Yes? ** 60% No? ** 40%
"problematic" projects
3.4 Percent involved with a Yes? 38% No? 62%
"runaway" project
** Indicates that differences in the proportions are not
statistically significant