Some problems of an as-built survey and setting out accuracy/ Kai kurios statybos kontroliniu nuotrauku ir nuzymejimo problemos.
Kala, Vello
1. Introduction
Accuracy is the closeness of an agreement between an actual
measured value and its true value ([TEXT NOT REPRODUCIBLE IN ASCII.] ...
1987). Nowadays, the accuracy acceptance criteria of setting out are
stated by the articles of ISO 4463-1 'Measurement Methods for
Building - Setting-out and Measurement' (ISO 1989).
The present publication deals with the values of permitted
deviations only.
Let us have a look at the setting out accuracy of the position
points (detailed setting out). There are three groups of requirements
(International ... 1989), related to:
* earthwork without any particular accuracy requirements, for
example excavations, slopes;
* earthwork subject to normal accuracy requirements, for example
road works, pipe trenches;
* in situ cast concrete structures, precast concrete structures,
steel structures.
The latter one is the examination object of the present paper. In
this case, setting out error ([[delta].sub.SO]) in the position should
not exceed 1.5[square root of ([L.sub.m])]; horizontal/vertical angles
should be measured and set out with angular reading to 1' (or
better) and optical plumbing error should not exceed 1. 5[square root of
([H.sub.m])] (where [L.sub.m] is the distance from a control point to a
position point and [H.sub.m] is the height from the reference level to
the erecting level, both in metres) (International ... 1989).
Consequently, the farther is the position point from the control
point, the larger are permitted deviations from the carried out
measurements. At the same time, permitted deviations from construction
works the accuracy of which the survey should assure and assess, should
remain independent from the location of the survey control points.
Obviously, in this case, the essential conflict exists.
This contribution presents an alternative approach: to the location
of the control points and to the selection of equipment and technology
so that the error of setting out and the error of the as-built survey
should not exceed the predetermined absolute limits.
Formerly, several previous studies have dealt with the problem of
what ratio of surveying permitted deviations and what permitted
deviations from construction works should be adopted. We suppose that
version 2 is the most reasonable as it states that the permitted
deviation of setting out makes up to 80% and the permitted deviation of
the as-built survey - up to 40% of corresponding permitted deviation
from construction works.
However, at present, a new problem arises. Which permitted
deviations from construction works are the most important and which are
in accordance with achievable and required accuracy? This subject is
discussed in the sequel.
2. Accuracy of Surveying the Construction of Single Storey
Buildings
2.1. Assembling Permitted Deviations that Might Determine the
Accuracy of Setting out and As-Built Survey
This section focuses on examining the buildings of factories,
storehouses and super-markets. The geometrical accuracy of construction
is determined by permitted deviations from assembling foundations or its
anchor bolts and columns. This is due to conceptual design
considerations. The cases of the reinforced concrete skeleton and the
metal skeleton will be discussed separately.
The most important permitted deviations of assembling [delta]constr
are as follows:
* for prefabricated foundations ([TEXT NOT REPRODUCIBLE IN ASCII.]
... 1987) - 12 mm;
* for concrete columns in its lower end (RT 02-10102) - 20 mm;
* for steel columns in its lower end ([TEXT NOT REPRODUCIBLE IN
ASCII.] ... 1987) - 5 mm.
2.2. Presumable Accuracy of Surveying
In this case, the evaluation of accuracy relays on some simplified
scheme assuming that the as-built survey and setting out are executed in
a section between expansion joints (in the majority of cases, an
interval of expansion joints is about 70 m). In addition, it is supposed
that control points are located about on the diagonal of the section at
a distance of 30 m from the buildin. Subsequently, the maximum distance
from the control point to the position point is 130 m.
Permitted deviations from construction works are generally
presented across the axes. Therefore, permitted deviations from position
points are also presented across the axes. As site grid axes are
generally parallel to building axes, the mean square errors (MSE) of
setting out and the as-built survey are presented by means of its
projections on the coordinate axes. Moreover, the use of a total station
Leica TC1100 (or an instrument of equal precision) is assumed in the
following calculations.
Thus, MSE is computed by the next equations:
[MATHEMATICAL EXPRESSION NOT REPRODUCIBLE IN ASCII.] (1)
where: [m.sub.s] - the mean square error (MSE) of distance
measurement ([+ or -]2,0 mm); [alpha] - medium direction angle in the
site grid system (45[degrees]); s - average distance to the position
point (130/2 = 65 m); [m.sub.[alpha]] = MSE of direction angle (it is
presupposed to be equal to the nominal MSE of angle measurement with one
full set [+ or -]4,5"); [rho] - 206 265"; mC = MSE of centring
the instrument on either x or y direction ([+ or -]0,4 mm); [m.sub.M] -
MSE of marking position points on either x or y direction ([+ or -]1
mm); [m.sub.NS] - MSE due to natural sources (a priori equal to
[m.sub.M]); [m.sub.ID] - MSE due to initial data (in case it is used as
the only control point and initial direction proposing that the error is
insignificant).
Equations (1) give:
[m.sub.x] = [m.sub.y] = [square root of (2 + 1 + 0.2 + 0.5 + 1 =
2.2 mm)],
which indicates that the most influencal errors are due to distance
measurement.
By ISO 4463-1 (setting out the position points of concrete and
steel structures): ms = 1,5[square root of (65/2.5= 5 mm)],
[m.sub.[alpha]] = 1' and after putting these values into equations
(1) [m.sub.x] = [m.sub.y] = 14 mm. It is even more than permitted
deviations from assembling the accuracy of which setting out should
assure. Clearly, this is not acceptable.
2.3. Accordance with Presumable and Required Surveying Accuracy
As already mentioned in the introduction, GOST 26433.0-85 states
permitted deviations from setting out up to 80% and permitted deviations
from the as-built survey up to 40% in light of corresponding permitted
deviations from assembling.
First, the concrete skeleton is examined. Thus, according to section 1, MSE of the foundation as-built survey should not exceed the
value [m.sub.abs] = [[delta].sub.constr] x 0.4/2.5 = 12 x 0.4/2.5 = 2 mm
and MSE of setting out position points (axes, centre lines on pockets
for columns) should not exceed 4 mm. MSE of the column as-built survey
should not exceed [m.sub.abs] = [[delta].sub.constr] x 0.4/2.5 = 20 x
0.4/2.5 = 3 mm. As it stems from subsection 2.2, it is achievable by
using Leica TC1100 or an instrument of equal precision.
Second, the steel skeleton is examined. In this case, MSE of the
column lower end as-built survey should not exceed the value [m.sub.abs]
= [[delta].sub.constr] x 0.4/2.5 = 5 x 0.4/2.5 = 0.8 mm. Apparently, it
is too difficult to carry out on the occasion of large-lot erecting. In
this case, a simpler technology foresees the as-built surveying lower
end of the column in relation to centrelines or edge lines previously
had set out on the foundation for assembling. Naturally, it calls for
higher requirements for the persistence of the above mentioned lines.
3. Accuracy of Surveying the Construction of Multi-Storey Buildings
3.1. Erecting Permitted Deviations that Might Determine the
Accuracy of Setting out and As-Built Survey
This section focuses on surveying the construction of supermarkets,
offices, residential buildings, hotels and light industry buildings. The
most important permitted deviations from assembling [delta]constr are:
* Deviation from the column low end of the in-situ concrete
skeleton on the intermediate floor and from the upper end of the column
under the inter-mediate floor (mating eccentricity) that generally
cannot be directly surveyed. The permitted deviation is d/20 (RAK MK
20743) (d = the cross-section diameter of the column, generally 300/400
mm) so [[delta].sub.constr] = 15/20 mm.
* Prefabricated multi-storey concrete column deviation from
verticality that generally cannot be directly surveyed after assembling
intermediate floors. The permitted deviation is h/150 (RAK MK 20743) (h
= height of the column). The most common are columns for two storeys.
Taking the height of a storey as of 3 m, the height of the column is 2 x
3 = 6 m, and thus the permitted deviation from verticality becomes
[[delta].sub.constr] = 40 mm.
* Prefabricated single storey concrete column lower end deviation
from the designed position. On the occasion of the second class
buildings (ordinary dwelling houses, offices etc), [[delta].sub.constr]
= 20 mm (RAK MK 20743).
* A permitted deviation of the single storey steel column from
verticality is h/280 (RAK MK 20844). Thus, if the height of the storey
is 4 m, [[delta].sub.constr] = 14 mm.
3.2. Presumable Accuracy of Surveying
The designing procedure in this case differs from the procedure of
single-storey buildings. First, two orders of control systems are used
at multi-storey-buildings: the primary system is established on the
ground and the secondary one on assembling or form-work level. The
accuracy of position points is found by means of equations (1) where the
length of a section is taken for 70 m but maximum width is most likely
about 20 m. The control point of the secondary system will be positioned
in the middle of the section, so the maximum distance between the
control point of the secondary system and the position point is about 40
m. MSE of the secondary system control point in relation to the control
point of the primary system can be calculated by
[MATHEMATICAL EXPRESSION NOT REPRODUCIBLE IN ASCII.] (2)
where: s - the distance from the control point of the primary
system to the control point of the secondary system (70 m); [alpha] -
medium direction angle from the control point of the primary system to
the control point of the secondary system (45[degrees]); [m.sub.[tau]] -
MSE due to a deviation of instrument vertical axis from truly vertical
(plumb line); [m.sub.R] - MSE due to the centring error of prism; the
other symbols used are spent in equations (1).
First, let us find MSE due to a deviation of the vertical axis of
the instrument from true vertical (plumb line) that is computed from
[m.sub.[tau]] = h[tau]/[[rho].sup."] = 40000x1/206265 = 0.2 mm
(3)
where: h - height from construction ground level to erecting level
(let us take 40 m, which is relatively high for large-lot constructions
in Estonia); [tau] - MSE of tilt correction (1 " for Leica TC1100).
Thus, equations (2) and (3) give MSE of secondary system control
point [m.sub.PR](x) = [m.sub.PR](y) = 2.1 mm, equation (1) gives MSE of
the position point in relation to the control point of the secondary
system (s = 40 m) [m.sub.x] = [m.sub.y] = 2.1 mm and the total MSE of
setting out/as-built survey column lower end is
[m.sub.[SIGMA]XL] = [m.sub.[SIGMA]YL] = 2.12 = 3.0 mm.
Column verticality deviation as-built survey error consists of the
following components: [m.sub.[tau]] = MSE due to a deviation of the
instrument vertical axis from plumb line (supposed to be insignificant
if vertical axis tilt correction is used); [m.sub.P] = parallax MSE that
occurs due to nonparallel instrument collimation plane and mounting a
line of column row (0.2 mm, if the total station is positioned on the
mounting surface (the best sighting line) by visual adjustment and
column inclination from plumb line towards the line of sight direction
not exceeding 30 mm); [m.sub.V1] = primary sighting error (due to
instrumental and personal qualities), generally insignificant;
[m.sub.V2] - secondary sighting error due to the local asperities of the
column ([+ or -]1.0 mm, considering ([TEXT NOT REPRODUCIBLE IN ASCII.]
... 1987) with (International ... 1989)). Thus, MSE of column
verticality asbuilt survey [m.sub.i] = [+ or -]1.0 mm and the total MSE
of setting out/as-built survey column upper end
[m.sub.[SIGMA]XU] = [square root of ([m.sup.2.sub.PR(x) +
[m.sup.2.sub.x] [m.sup.2.sub.i] = 3,2 mm)]
[m.sub.[SIGMA]YU] = [square root of ([m.sup.2.sub.PR(y) +
[m.sup.2.sub.y] [m.sup.2.sub.i] = 3,2 mm)]
If column mating eccentricity cannot be directly surveyed, then MSE
of the mating as-built survey becomes
[m.sub.ex] = [square root of ([m.sup.2.sub.[SIGMA]XL] +
[m.sup.2.sub.[SIGMA]XU = 4,4 mm)],
and [m.sub.ey] = 4,4 mm
3.3. Accordance with Presumable and Required Surveying Accuracy
The first case in subsection 3.1 is decisive for in-situ concrete
skeleton as-built surveying accuracy. Let us assume the column
cross-section diameter being 400 mm, thus the promised MSE of mating
as-built surveying is [m.sub.x] = [m.sub.y] = 0.4 x 20/2.5 = 3 mm.
Although in subsection 3.2 it was found that the presumable MSE of
mating eccentricity as-built surveying [m.sub.ex] = [m.sub.ey] = 4.4 mm,
however, this accuracy is not sufficient. The usage of a more precise
EDM ([m.sub.s] = 1 mm) would not provide sufficient accuracy either. For
solving this problem, the following solution is recommended. As-built
surveying is not foreseen to assure the accuracy of construction works,
except from ascertaining its accuracy, the lower accuracy of as-built
surveying brings along further erroneously accepted or rejected
deviations. For example, if MSE of as-built surveying does not exceed
40/2.5 = 16% of [[delta].sub.constr], the amount of erroneously accepted
deviations is 2% and erroneously rejected deviations is 2.8%. In case
[m.sub.ex] = [m.sub.ey] = 4.4 mm (MSE [approximately equal to] 24% of
[[delta].sub.constr]), the amount of erroneously accepted deviations is
3% and erroneously rejected deviations is 4.5% (Egnus 1972). The
discrepancy is not large and might be acceptable. The limit to MSE of
setting out is more important and makes [m.sub.x] = [m.sub.y] = 0.8 x
20/2.5 = 6 mm which is satisfied under the assumed conditions.
In the second case, (prefabricated concrete skeleton construction
with multi-storey columns) the verticality deviation of the column is
decisive as it cannot be surveyed directly. Verticality deviation
([delta]constr = 40 mm) can be found as discrepancy in plane between the
projections of the upper and lower end of the column, so deviation from
the position in both ends should not exceed
[[delta].sup.'.sub.constr] = 40/[square root of (2)] = 28 mm. Thus,
MSE of the us-built survey should not exceed [m.sub.x] = [m.sub.y] = 0.4
x 28/2.5 = 4.5 mm. The values of [m.sub.[SIGMA]XL], [m.sub.[SIGMA]YL],
[m.sub.[SIGMA]XU], [m.sub.[SIGMA]YU] (as stated in 3.2) were smaller
than this value.
Let us have a look at the third case (prefabricated concrete
skeleton construction with a single-storey column). In this case, a
deviation of the lower end of the column from the designed position is
decisive because the inclination of the column from verticality can be
measured directly and with high accuracy. Correspondingly to subsection
3.1, [[delta].sub.constr] = 20 mm. Thus, [m.sub.x] = [m.sub.y] = 0.4 x
20/2.5 = 3.2 mm which does not create remarkable problems.
Although the fourth case (steel skeleton) is similar to the third
one, nevertheless, permitted deviations are much harder. It is expedient to examine accuracy from the point of view of setting out. Thus, if the
permitted deviation of the column (h = 3 m) from plumb line
[[delta].sub.constr] = 14 mm, the column end position permitted
deviation [[delta].sup.'.sub.constr] = 14/[square root of (2)] = 10
mm. and the permitted value of MSE of setting out [m.sub.x] = [m.sub.y]
= 0.8 x 10/2.5 = 3.2 mm. In subsection 3.2, MSE of setting out/as-built
survey of the column lower end [m.sub.[SIGMA]XL] = 3.0 mm was found
which is less than the permitted value of 3.2 mm.
4. Conclusions
It was assumed that secondary points at the erection level were
carried out every time from the same primary point. In case it is
impossible, it must be taken into consideration errors due to the
initial data.
At long last one should take into consideration errors due to the
thermal expansion of construction, but they are not well researched yet.
The above given information demonstrates that setting out and the
as-built survey in particular demand relatively high accuracy to get
satisfactory results.
Setting out position points and the as-built survey on assembling
concrete or steel skeleton need a total station where MSE of distance
measurement is [+ or -]2 mm or better and MSE of angle measurement is [+
or -]3" (DIN 18723) or better. However, even such accuracy
sometimes does not satisfy and one has to use extra concepts (see 3.3).
It is recommendable that the existing ISO standard (International
... 1989) should be revised in order to make it contemporary.
doi: 10.3846/1392-1541.2009.35.73-76
Received 03 12 2008; accepted 15 06 2009
References
International Standard (ISO 4463-1). Measurement methods for
building - Setting-out and measurement. Switzerland, 1989. 21 p.
Rak MK 20844. Terasrakenteet [Finnish Standard. Steel Structures].
Helsinki (in Finnish).
Rak MK 20743. Betonirakenteet [Finnish Standard. Concrete
Structures]. Helsinki (in Finnish).
RT 02-10102. Betonirakenteiden toleranssit [Finnish Regulations.
Tolerances of Concrete Structures]. Helsinki (in Finnish).
[TEXT NOT REPRODUCIBLE IN ASCII.] 26433.0-85. [TEXT NOT
REPRODUCIBLE IN ASCII.] [National Standard. System of ensuring
geometrical parameters accuracy in construction. Rules of measurement.
General]. MocKBa, 1985. 17 c. (in Russian).
[TEXT NOT REPRODUCIBLE IN ASCII.] [Standards and Regulations in
Construction. Supporting and barrier structures]. MocKBa, 1987. 187 c.
(in Russian).
[TEXT NOT REPRODUCIBLE IN ASCII.] [Dwelling and communal
houses' skeleton erection]. [TEXT NOT REPRODUCIBLE IN ASCII.],
1972. 293 c.
Vello KALA, lecturer, MSc, Tallinn University of Technology, Chair
of geodesy, Ehitajate tee 5, 19086, Tallinn, Estonia, Ph +372 620 2602,
Fax +372 620 2601, e-mail: vello.kala@ttu.ee.
Vello Kala
Tallinn University of Technology, Ehitajate tee 5, 19086 Tallinn,
Estonia E-mail: vello.kala@ttu.ee
The Author of 18 textbooks, handbooks, standards and more than 30
scientific and technical papers.
Research interests: construction surveys, precise levelling.