摘要:In this paper an analysis of the feasibility of locating a 110 kV line in a 400 kV line right-of-way in terms of electromagnetic interaction is presented.The analysis was performed in a model system with the use of the EMTP-ATP simulation program.Construction conditions of the 110 kV line and its subsequent operation were considered.Normal operation conditions and short-circuit in 400 kV line were taken into account.The paper presents the results of the calculation of the prospective touch voltages and touch currents in the 110 kV line.
关键词:overhead power lines;electromagnetic interaction;designing.