摘要:According to the latest experience of UHV transformer on-site installation work, according to the rules and regulations requirements, the construction process and process of UHV transformer are summarized, and a typical UHV transformer construction method commonly used at present is obtained. Operation comes down to the arrival of acceptance, annex installation, vacuum oiling and hot oil circulation, sealing inspection, standing five processes. In accordance with the above process steps, this paper is divided into five parts to introduce the process and method of UHV transformer construction in order to guide the on-site construction and training teaching.