摘要:The objective of this paper is to evaluate factors affecting the progress of completing construction of irrigation projects using state budget funds. To achieve the goal, to research and conduct surveys of investors, contractors, managers of irrigation construction investment projects. Analysis results from 269 valid questionnaires using SmartPLS 3.6 software showed that all 6 factors: Investor, Peripheral, Capital, Contractors, Consultant, Convenience, all factors have a positive impact on progress of completing irrigation construction projects using state budget funds in Thai Binh province, Vietnam.
关键词:Progress of completing; Irrigation construction project; Vietnam; Project delay; Project Scheduling